This checklist provides instructions for commissioning Metrosil and non-linear resistor equipment. It includes steps to perform a mechanical check and visual inspection of the equipment bay and components. Electrical tests are also listed to check the characteristics of the Metrosil component. The document must be approved by the CSD and contractor and includes spaces for signatures and dates to confirm completion.
Original Description:
Metrosil checklist
Original Title
CL-NG-6460-002-067 Checklist for Metrosil and Non Linear Resistor Rev01
This checklist provides instructions for commissioning Metrosil and non-linear resistor equipment. It includes steps to perform a mechanical check and visual inspection of the equipment bay and components. Electrical tests are also listed to check the characteristics of the Metrosil component. The document must be approved by the CSD and contractor and includes spaces for signatures and dates to confirm completion.
This checklist provides instructions for commissioning Metrosil and non-linear resistor equipment. It includes steps to perform a mechanical check and visual inspection of the equipment bay and components. Electrical tests are also listed to check the characteristics of the Metrosil component. The document must be approved by the CSD and contractor and includes spaces for signatures and dates to confirm completion.
CL-NG-6460-002-067 Checklist for Metrosil and Non Linear Resistor Commissioning Page Number: 1 of 1
1.0 Equipment General Data and Information
2.0Substation Bay/Panel Equipment Serial No Mechanical Check and Visual Inspection Item Description Done Remarks General Visual Inspection. (check list CL-NG-6460-002-056 1. should be attached) Visual inspection of protective cover / shroud with high 2. voltage caution label 3.0 Electrical Test Item Description Done Remarks 1. Check the characteristics of the Metrosil