Professional Documents
Culture Documents
NBC 2016
DesignTree Service Consultants Pvt Ltd
FIRE & LIFE SAFETY,2016
NBC 2016
DesignTree Service Consultants Pvt Ltd
FIRE PROTECTION SYTEM - BASICS
NBC 2016
The triangle illustrates a fire requires three elements: heat, fuel, and oxygen . The fire
is prevented or extinguished by removing any one of them. A fire naturally occurs
when the elements are combined in the right mixture.
NBC 2016
NBC – National Building Code, 2016, Part 4
FM – Factory Mutual
BSI – British
Standards
* Though every nation has its own Standards, generally adopted in India are mentioned.
NBC 2016
Apart from standards & guidelines followed, one should also adhere to the Authority
how is holding the Jurisdiction.
CFO – Chief Fire Officer of respective State/ District, is the authority who directs the
general public, consortium of builders & developers to follow or to adopt certain
requirements which is essential to respective City, District, Town, State.
NBC 2016
5. Buildings with two basements or more or with one basement of area more than 500sq.m
Group A - Residential
Group B - Educational
Group C - Institutional
NBC 2016
Group D - Assembly
Group E - Business
Group F - Mercantile
Group G - Industrial
Group H - Storage
Group J – Hazardous
Part 01 – Definitions
Part 02 – Administration
Part 03 – Development control Rules and General building requirements
Part 04 – Fire & Life Safety
NBC 2016
Part 05 – Building materials
Part 06 – Structural Design
Part 07 – Construction Management, Practices and Safety
Part 08 – Building Services (HVAC)
Part 09 – Plumbing Services
Part 10 – Landscape development, signs and Outdoor display structures
Part 11 – Approach to sustainability
Part 12 – Asset and Facility management
Following Fire prevention, Fire fighting and Life safety measures, as stipulated in NBC
2005, which are required to be adhered
NBC 2016
Following Fire prevention, Fire fighting and Life safety measures, as stipulated in NBC
2005, which are required to be adhered:
A) Width of the Road – A road which abuts a high rise building to be constructed
should be more than 12 meters wide.
B) Strength of Road – The road should be hard surfaced to carry a minimum weight
of 45,000kgs.
C) Entrance width & height clearance – Width of the entrance / exit should not be
less than 6.00 meters. Height clearance of minimum 5.00 meters have to be
maintained over the entry point.
NBC 2016
individual occupancies.
Each occupancies to be separated by a
240min fire resistance rating.
3 Service ducts Plumbing shaft – 30 min
- Electrical shaft – 2 h
- Plumbing shaft – No mention
4 Refuse chute Refuse chutes, if any provided in a bldg.
- No mention shall have opening at least 1m above
roof level for venting purpose,
enclosure wall shd be 120 min.
5 Standby supply DG shall not be installed at any floor
- No mention other than ground, first basement.
DesignTree Service Consultants Pvt Ltd
ADAPTATION OF FIRE SAFETY REQUIREMENTS
Setbacks or Open spaces
required around each High Rise
building –
NBC 2016
DesignTree Service Consultants Pvt Ltd
ADAPTATION OF FIRE SAFETY REQUIREMENTS
Width & Means of access
NBC 2016
DesignTree Service Consultants Pvt Ltd
ADAPTATION OF FIRE SAFETY REQUIREMENTS
NBC 2016
DesignTree Service Consultants Pvt Ltd
ADAPTATION OF FIRE SAFETY REQUIREMENTS
NBC 2016
DesignTree Service Consultants Pvt Ltd
OCCUPANT LOAD
Remains Same !!!
The assembly occupancy and
call centers shall be required
to display, limiting occupant
load details positioned in a
conspicuous place, to avoid
possible overcrowding and
overloading.
NBC 2016
DesignTree Service Consultants Pvt Ltd
FIRE TOWER
Fire tower to be
provided for all type of
developments
NBC 2016
DesignTree Service Consultants Pvt Ltd
FAÇADE OPENING
NBC 2016
DesignTree Service Consultants Pvt Ltd
GENERAL EXIT REQUIREMENTS
NBC 2016
DesignTree Service Consultants Pvt Ltd
ARRANGEMENT OF EXITS
New Inclusion….
NBC 2016
DesignTree Service Consultants Pvt Ltd
CAPACITIES OF EXIT
Change, but no impact….
NBC 2016
DesignTree Service Consultants Pvt Ltd
TRAVEL DISTANCE
NO Change…
NBC 2016
DesignTree Service Consultants Pvt Ltd
DIFFERENT TYPE OF CONSTRUCTION
NO Change…
NBC 2016
DesignTree Service Consultants Pvt Ltd
HORIZONTAL EXITS
Refuge Area – To be provided building of height more than 24m. Refuge area
provided shall be planned to accommodate the occupants of 2 consecutive
floors by considering area of 0.3sq.m per person for the calculated number of
occupants and shall include additionally to accommodate one wheelchair space
of an area of 0.9sq.m for every 200 occupants, portion thereof, based on the
occupant load served by the area of refuge.
NBC 2016
• Signage bearing REFUGE AREA shall be installed having height of letters of
minimum 75mm and also containing information about location.
• Refuge area shall be ventilated and provided with first aid box, fire
extinguishers, public address speakers, fireman talk back and emergency
lighting as well as drinking water.
• Refuge area shall connect to firefighting shaft.
• Entire refuge area shall be provided with sprinklers
• Refuge areas for Apartment buildings of height above 60m, while having
balconies shall be provided with refuge area at 60m and thereafter at every
30m.
NBC 2016
EXTERNAL STAIRCASES
Few change
• Minimum width should be 1.5m
(1500mm).
• If any window openings, doors
exists within 3m from an external
stairs, they shall be fire rated of
60min.
• Any doors leading to occupied
space shall be 120min fire rated.
NBC 2016
DesignTree Service Consultants Pvt Ltd
BASEMENT VENTILATION
Changed….
NBC 2016
DesignTree Service Consultants Pvt Ltd
MECHANICAL VENTILATION
NBC 2016
DesignTree Service Consultants Pvt Ltd
GAS SUPPLY
NBC 2016
DesignTree Service Consultants Pvt Ltd
PUMP ROOM
NBC 2016
DesignTree Service Consultants Pvt Ltd
RESIDENTIAL BUILDING
Subdivision A3: Sleeping rooms having occupancy of more than 10 persons
shall have two separate & distinct exits.
Subdivision A4: Naturally ventilated staircases may not require the provision of
fire door.
Subdivision A5: Panic bars shall be provided for all fire exits.
NBC 2016
All guest rooms to have extended throw, quick response sprinklers. Also with
sounder based detector with sound level of 75dB.
EDUCATIONAL BUILDING
Every room with a capacity of over 45 persons shall have two separate
doorways.
NBC 2016
• Aisles, corridors, ramps through which patients are moved shall be of
minimum 2.4m wide.
• Minimum width of door for,
Single or double occupancy room – 1.25m
Wards for 3 to 5 patients – 1.5m
Wards with more than 5 beds – 2.0m
• A stretcher lift in a lift bank shall also act as fireman’s lift.
NBC 2016
D6 Occupancy:
• Rows of seats between aisles shall have
not more than 14seats.
• Rows of seats opening on to an aisle at one
end only shall have not more than 7 seats.
• Refuge area : Refuge area to be provided
on the floor at or immediately above 18m
shall be not less than 10% of gross area of
floor. Next refuge area to be at/on the floor
immediately above 24m.
NBC 2016
DesignTree Service Consultants Pvt Ltd
ELECTRICAL SYSTEM
NBC 2016
DesignTree Service Consultants Pvt Ltd
Standards Adopted
Bureau of Indian
NBC 2016
Standards NBC - 2005 Indian Electricity Act - 2003
NBC 2016
provided in the basement. Also, the
floor level of the substation shall not
be lowest point
of the basement.
3 In order to prevent storm water In order to prevent storm water Vol 2 , Part 8 , 4.2
entering the transformer and switch entering the transformer and switch
rooms through the soak- pits, the rooms through the soak-pits, the
floor level of the floor level, the substation shall be at
substation/switch room shall be at least 15 cm above the highest flood
least 300 mm above the highest water level that may be anticipated
flood water level that may be in the locality. Also, facility shall be
Anticipated in the locality. Also, provided for automatic removalof
facility shall be provided for water.
automatic removal of water.
5 All door openings from substation, All door openings from substation,
electrical rooms, etc, should open electrical rooms, etc. should open
outwards. Vertical shutters (like fire towards outside.
NBC 2016
rated rolling shutters) may also be
acceptable provided they are combined
with a single leaf door opening
outwards for exit in case of emergency.
For large substation room/electrical
room having multiple equipment, two
or more doors shall be provided
which shall be remotely located from
each other.
6 Conditions of supply of electricity Conditions of supply of electricity NBC 2016: Vol 2, Part 8
boards or licensees stipulate the lower boards or licensees stipulate the lower- 3.4.1 Power Factor
limit of power factor which is generally limit of power factor which is generally Improvement.
0.90 or better. 0.85 NBC 2005: Vol 2, 3.4.1,
Part 8 Power Factor
Improvement.
8 Lighting Wire Size – 1.5Sq.mm Lighting Wire Size – 1.0 Sq.mm Vol 2 , Part 8 , 5.8
Water Heater (3kW) - 2.5Sq.mm Water Heater (3kW) - 1.5Sq.mm Installation circuits
Water Heater (3 – 6 kW) - 4Sq.mm Water Heater (3 – 6 kW) - 2.5Sq.mm
Free Standing Electric Range – 4Sq.mm Free Standing Electric Range – 6 Sq.mm
NBC 2016
DesignTree Service Consultants Pvt Ltd
38
GUIDELINES – SOLAR ENERGY UTILIZATION
SOLAR PHOTO VOLTAIC POWER GENERATION SYSTEM : SOLAR WATER HEATING SYSTEM :
Power Generation using solar is made mandatory & Following The following building occupancy types shall
Guide has been suggested to local authority to specify the install solar assisted water heating system
minimum power generation from Solar energy for Various for supplying hot water
housing Facilities
NBC 2016
REF:
Vol 1 , Part -3 Development Control
Rules & General Building
Requirements
Section: 21.2.1
NBC 2016
REF:
Vol 2 , Part -8, Solar Photovoltaic
Power Generating System
EMERGENCY POWER FOR FIRE & LIFE SAFETY SUBSTATION & TRANSFORMERS:
SYSTEM :
• Electrical MV main distribution panel
Power supply to the below systems and equipment and lift panels shall be provided with
shall be from normal and emergency (standby CO2/inert gas flooding system for all
generator) power sources with changeover facility. panel compartments with a cylinder
located beside the panel.
NBC 2016
• All transformers where capacity
exceeds 10 MVA shall be protected by
high velocity water spray systems or
nitrogen injection system.
REF:
Vol 1 , Part -4 ,
Fire & Life Safety 3.4.6.2
NBC 2016
or below plumbing water tanks or sewage ground floor open to sky / inside utility
treatment plant (STP) water tanks at the same building. If inside utility building,
location. substation shall be at ground or first
• In case of HV panel and transformers located at basement only.
different floors or at a distance more than 20 m,
HV isolator shall be provided at transformer
end.
• In case transformer and main MV/LV panel room
are located at different floors or are at a distance
more than 20 m, MV/LV isolator shall be provided
at transformer end.
• If there is a floor directly below the ground floor
level or first basement where the oil-filled REF:
transformers and oil-filled circuit breakers are Vol 1 , Part -4 ,
placed, then they shall be separated by a fire Fire & Life Safety 3.4.6.2
barrier of appropriate fire rating
NBC 2016
The provision for installation and
removal of substation equipment
Figure-1
Vol 2 , Part -8 , Building Services
REF:
should be provided from inside or
outside the building without
disturbing the associated major
equipment in the substation.
NBC 2016
have proper ventilation. Special care
should be taken to dissipate transformer
heat and where necessary fresh air
Figure-1
Vol 2 , Part -8 , Building Services
REF:
louvers at lower level and exhaust fans at
higher level shall be provided at suitable
locations.
NBC 2016
Figure-2
Vol 2 , Part -8 , Building Services
REF:
SPACE PLANNING FOR SWITCH GEAR ROOM
In case of high rise buildings, the supplier or owner of the installation shall
provide at the point of commencement of supply a suitable isolating device
with cut-out or breaker to operate on all phases except neutral in the 3-phase,
4-wire circuit and fixed in a conspicuous position at not more than 1.7 m above
the ground so as to completely isolate the supply to the building in case of
emergency.
NBC 2016
In large multi-storeyed buildings, installation of a large number of energy meters
at the ground floor (or first basement) switch-room for the convenience of the
meter-reader poses high fire hazard. More than 24 energy meters on one
switchboard is undesirable. In such cases, where number of energy meters to be
installed for feeding exceeds 24, energy meters shall be installed at each floor
and therefore, the rising main (bus trunking) with tapping point at individual
floor shall be provided for meters.
REF:
Vol 2 , Part -8 , Building
Services 5.4.1
NBC 2016
retail store networks,
factories, or any building with multi- Function of Smart metering :
tenanted occupancy. Hourly energy demand and use;
Energy breakdown and mix and energy
Comprising consumption patterns;
Power quality analysis;
Main meters ( Digital meters)
Energy consumption by process,
Submeters
department, building, floor, etc;
Monitoring Functions
REF:
Vol 2 , Part -8 , Building Services
5.4.1.4.4
NBC 2016
cable is recommended.
Aluminium conductor cables in sizes less than
If a dedicated circuit is planned for 6A sockets 16 mm2 cause termination problems leading to
the load of such a circuit shall be restricted to heating at the terminals and enhance the
800 W or a maximum of 8 numbers, whichever is possibility of a fire. For conductor sizes less
lesser, controlling MCB should be sized than or equal to 16 mm2, only copper
accordingly. conductor cables should be used.
NBC 2016
REF:
Vol 2 , Part -8 , Building
Services 6 Wiring
NBC 2016
Vol 2 , Part -8 , Building Services
8 Earthing
REF:
DesignTree Service Consultants Pvt Ltd
50
NEW GUIDELINES - INCLUSIONS
ELECTRICAL VEHICLE CHARGING AVIATION OBSTACLE LIGHTS
NBC 2016
Vol 2 , Part -8 , Building Services
10.7
REF:
DesignTree Service Consultants Pvt Ltd
51
NEW GUIDELINES-LIGHTNING PROTECTION SYSTEM
NBC 2016
MESH METHOD
REF:
DesignTree Service Consultants Pvt Ltd
52
NBC 2016
DesignTree Service Consultants Pvt Ltd
53