Professional Documents
Culture Documents
Report Details
Project: Newmarket Green - Display Suite, 152-154 Barker Street, Randwick, NSW 2031
Document: Fire Engineering Report
Report No.: F200372_NMG Display Suite_FER_02
Copyright ©
All rights reserved. No part of this document may be reproduced, published, transmitted or adapted in any form or by any means
without the written permission of CORE Engineering Group.
Disclaimer
The information contained in this document is provided for the sole use of the recipient and no reliance should be placed on the
information by any other person. In the event that the information is disclosed or furnished to any other person, CORE Engineering
Group accepts no liability for any loss or damage incurred by that person whatsoever as a result of using the information.
Page i www.coreengineering.com.au
Newmarket Green - Display Suite
09 June 2017 | Final Issue | Report No F200372_NMG Display Suite_FER_02
EXECUTIVE SUMMARY
CORE Engineering Group has been engaged by Cbus Property Pty Ltd to develop a Performance Solution for
the display suite located at 152-154 Barker Street, Randwick, NSW 2031. The project encompasses the
construction of a temporary display suite structure which will serve to promote and sell the prospective
residential buildings being constructed on the Newmarket Green estate.
This Fire Engineering Report (FER) highlights areas of non-conformance with the Building Code of Australia
2016 (BCA) [1] Deemed-to-Satisfy (DtS) provisions for the project.
The FER outlines the scope of work for the Fire Engineering Analysis, sets down the basis on which the
analysis has been undertaken (as agreed by the stakeholders), the necessary acceptance criteria and
specifies a Fire Safety Strategy and work schedule for compliance.
The following table lists the departures from the DtS provisions of the BCA for the works and those Fire
Engineering requirements formulated as part of the evaluation. The procedures outlined in BCA clause A0.7
has been used to identify the BCA DtS Provisions and Performance Requirements that are relevant to the
Performance Solutions. The assessment methodology for the Fire Engineering Assessment has been
prepared in accordance with the International Fire Engineering Guidelines (IFEG) [3].
A fully prescriptive approach of complying with the BCA DtS provisions for fire resisting construction would not
satisfy the desired architectural and client aspirations. As such, Performance Solutions have been developed
to account for the following issues which do not comply with the DtS Provisions:
Fire protection of external walls
Exposed openings
As detailed within this report, evaluation of those Performance Solutions has identified that the project will
comply with the Performance Requirements of the BCA.
Summary of Performance Solutions
Page ii www.coreengineering.com.au
Newmarket Green - Display Suite
09 June 2017 | Final Issue | Report No F200372_NMG Display Suite_FER_02
TABLE OF CONTENTS
1 INTRODUCTION _____________________________________________________________________ 1
1.1 OVERVIEW 1
1.2 FIRE SAFETY OBJECTIVES 1
1.3 REGULATORY FRAMEWORK OF THE FIRE ENGINEERING ASSESSMENT 2
9 NOMENCLATURE __________________________________________________________________ 20
10 REFERENCES _____________________________________________________________________ 21
APPENDIX A STATISTICS A-1
APPENDIX B ASSESSMENT METHODOLOGY B-1
Page iv www.coreengineering.com.au
Newmarket Green - Display Suite
09 June 2017 | Final Issue | Report No F200372_NMG Display Suite_FER_02
1 INTRODUCTION
1.1 OVERVIEW
This Fire Engineering Report has been undertaken to nominate proposed Performance Solutions for assessing
compliance with the nominated Performance Requirements of the BCA [1] in accordance with the
methodologies defined in the IFEG [3] and provide a workable and safe Fire Safety Strategy through a trial
design. In order to develop and assess the nominated non-compliances the following flowchart process is to
be adopted.
Dominant • Defines occupant characteristics which may affect their Each characteristic can affect the
Occupant ability to respond and evacuate in fire conditions outcome of the fire strategy when
Characteristics assessed in conjunction with each
other i.e. occupants requiring
assistance may require increased
passive and active fire protection.
Fire Hazards and • Establishes the likely risks for occupant and brigade life
Protective safety and suitable measures to address those risks
Measures
BCA DtS Non- • Details non-compliance/s for the building and relevant BCA clauses
Compliance • Provides methods for justifying the above risks
Assessment and
• Defines methods proposed for assessing the performance of the Performance Solutions and
Acceptance
Criteria objectives
Fire Engineering • Provides assessment of the BCA non-compliances utilising the methodology and acceptance
Assessment criteria to confirm compliance with the required performance Provisions
Fire Engineering • Details likely passive, active and management requirements to confirm the trial design
Requirements assesses the nominated non-compliances
Page | 1 www.coreengineering.com.au
Newmarket Green - Display Suite
09 June 2017 | Final Issue | Report No F200372_NMG Display Suite_FER_02
Page | 2 www.coreengineering.com.au
Newmarket Green - Display Suite
09 June 2017 | Final Issue | Report No F200372_NMG Display Suite_FER_02
(b) A Performance Solution will only comply with the NCC when the Assessment Methods used
satisfactorily demonstrate compliance with the Performance Requirements.
Section A0.5 of the BCA provides several different methods for assessing that a Performance Solution
complies with the Performance Requirements. These methods are summarised as follows:
(a) Evidence to support that the use of a material, form of construction or design meets a Performance
Requirement or a Deemed-to-Satisfy Provision.
(b) Verification Methods such as:
(i) the Verifications Methods in the NCC; or
(ii) such other Verification Methods as the appropriate authority accepts for determining compliance
with the Performance Requirements.
(c) Expert Judgement.
(d) Comparison with the Deemed-to-Satisfy Provisions.
Section A0.7 of the BCA provides methods for complying with provisions A1.5 (to comply with Sections A to J
of the BCA inclusive). The following method must be used to determine the Performance Requirements
relevant to the Performance Solution: These methods are summarised as follows:
(a) Where a Performance Requirement is satisfied entirely by a Performance Solution:
(i) Identify the relevant Performance Requirement from the Sections or Part to which the
Performance Solution applies.
(ii) Identify Performance Requirements from other Sections of Parts that are relevant to any aspects
of the Performance Solution proposed or that are affected by the application of the Performance
Solution.
(b) Where a Performance Requirement is satisfied entirely by a Performance Solution in combination with
a Deemed-to-Satisfy Solution:
(i) Identify the relevant Deemed-to-Satisfy Provisions of each Section or Part that is to be the subject
of the Performance Solution.
(ii) Identify the Performance Requirements from the same Section or Part that are relevant to the
identified Deemed-to-Satisfy Provisions.
(iii) Identify Performance Requirements from the other Sections and Parts that are relevant to any
aspects of the Performance Solution proposed or that are affected by the application of the
Deemed-to-Satisfy Provisions that are the subject of the Performance Solution.
Page | 3 www.coreengineering.com.au
Newmarket Green - Display Suite
09 June 2017 | Final Issue | Report No F200372_NMG Display Suite_FER_02
2 PROJECT SCOPE
2.1 OVERVIEW
CORE Engineering Group has been engaged to develop a Performance Solution for
the display suite located at 152-154 Barker Street, Randwick, NSW 2031. The
Project Scope
project encompasses the construction of a temporary display suite structure which
will serve to promote and sell the prospective residential buildings being constructed
on the Newmarket Green estate.
Specifically, this fire engineering report presents Performance Solutions to address the following items that do
not conform with the DtS Provisions of the BCA;
Fire protection of external walls
Exposed openings
Page | 4 www.coreengineering.com.au
Newmarket Green - Display Suite
09 June 2017 | Final Issue | Report No F200372_NMG Display Suite_FER_02
Page | 5 www.coreengineering.com.au
Newmarket Green - Display Suite
09 June 2017 | Final Issue | Report No F200372_NMG Display Suite_FER_02
3.1 OVERVIEW
Building characteristics are assessed as part of the Fire Engineering Review due the
following:
1. The location can affect the time for fire brigade intervention and potential
Principal Building external fire exposure issues.
Characteristics
2. The structure will impact on the ability to resist a developing fire and support
condition to allow occupants to escape the building and the fire brigade to
undertake firefighting to the degree necessary.
3. The floor area determines the potential fire size and area required to be
evacuated in the event of a fire.
4. BCA details such as Type of Construction, Class and Height will dictate passive
and active fire safety systems.
Page | 6 www.coreengineering.com.au
Newmarket Green - Display Suite
09 June 2017 | Final Issue | Report No F200372_NMG Display Suite_FER_02
Figure 3-3: Temporary Display Suite Location in relation to Newmarket Green Estate Plan
Page | 7 www.coreengineering.com.au
Newmarket Green - Display Suite
09 June 2017 | Final Issue | Report No F200372_NMG Display Suite_FER_02
The building site influences the likely fire brigade intervention times, and given the close proximity to the
nearest fire station is expected to facilitate a relatively convenient and expedient fire brigade response. The
two nearest fire brigade stations provided with permanent staff are Randwick and Maroubra which are
approximately 1.9 km and 3.5 km from the site respectively.
Page | 8 www.coreengineering.com.au
Newmarket Green - Display Suite
09 June 2017 | Final Issue | Report No F200372_NMG Display Suite_FER_02
Page | 9 www.coreengineering.com.au
Newmarket Green - Display Suite
09 June 2017 | Final Issue | Report No F200372_NMG Display Suite_FER_02
CHARACTERISTIC DESCRIPTION
Classification Class 6 (Display Suite)
Construction Type Type C required
Rise in Storeys One (1)
Effective Height 0 m (i.e. less than 12 m)
Floor Area Display Suite: 344 m²
Approximate – for Sales & Display: 177 m²
information only
Display Suite 1: 70 m²
Display Suite 2: 70 m²
Balcony: 27 m²
External Café: 9 m²
Courtyard: 111 m²
Page | 10 www.coreengineering.com.au
Newmarket Green - Display Suite
09 June 2017 | Final Issue | Report No F200372_NMG Display Suite_FER_02
4.1 OVERVIEW
The occupant characteristics are assessed within the Fire Engineering Report due
to the following:
1. Population numbers can dictate the time required to evacuate the building and
Dominant the required life safety systems to be provided due to evacuation times.
Occupant
Characteristics
2. Physical and mental attributes affect the occupants’ capacity to respond to
various fire cues and react accordingly.
3. Familiarity of occupants can affect the time taken to evacuate the building and
subsequent active / passive requirements.
Page | 11 www.coreengineering.com.au
Newmarket Green - Display Suite
09 June 2017 | Final Issue | Report No F200372_NMG Display Suite_FER_02
Page | 12 www.coreengineering.com.au
Newmarket Green - Display Suite
09 June 2017 | Final Issue | Report No F200372_NMG Display Suite_FER_02
5.1 OVERVIEW
The fire hazard analysis forms the basis for the review of non-compliances within the
building. In assessing expected and statistically validated hazards, preventative and
protective measures are developed commensurate with those expected risks. The
Fire Hazards and following section reviews applicable hazards and recommends possible measures
Protective to address those risks. Furthermore, hazards identified can form a justified basis for
Measures
selected scenarios.
Figure 5-1: Display Suite Exposure Separation Distances & Exit Locations
Page | 13 www.coreengineering.com.au
Newmarket Green - Display Suite
09 June 2017 | Final Issue | Report No F200372_NMG Display Suite_FER_02
5.2.2 Activities
It is not expected that regular hot work processes, use of highly flammable materials, manufacturing processes
or operation of high friction or high temperature machinery will be performed within the building. The
development is a display suite which provides an indicative prospective of a unit for potential property
customers.
Page | 14 www.coreengineering.com.au
Newmarket Green - Display Suite
09 June 2017 | Final Issue | Report No F200372_NMG Display Suite_FER_02
6.1 OVERVIEW
In this instance, the BCA DtS non-compliances have been formulated based on the
regulatory review as provided by the principal certifying authority. Where not listed
herein the building is required to achieve compliance with relevant DtS provisions or
BCA DtS Non- if existing, comply with relevant codes, reports and / or Standards approved at the
Compliance time of consideration.
Assessment and
Acceptance The following table lists the departures from the DtS provisions of the BCA for the
Criteria proposed building and the analysis methodology proposed for the Fire Engineering
assessment, which is to be generally in accordance with the IFEG [3].
Page | 15 www.coreengineering.com.au
Newmarket Green - Display Suite
09 June 2017 | Final Issue | Report No F200372_NMG Display Suite_FER_02
7.1 OVERVIEW
In order to establish that the required BCA Performance Requirements have been
adequately assessed the following section details the results of the analysis and
compares those results to each applicable Performance Requirement. The results
Fire Engineering of the analysis are collated and evaluated taking into consideration the DtS
Assessment requirements, assessment methodology, and acceptance criteria.
7.2.2 Introduction
The Display Suite is to be a temporary structure that will provide customers with the ability to inspect a typical
unit whilst works commence on the remainder of the Newmarket Green estate. The intended location for the
display suite is on what will become Lot N1, and is to be between an existing house and a stable building. Due
to its temporary nature, the Display Suite structure is proposed to not have its external walls achieve an FRL.
Furthermore, openings in its external walls will not be provided with protection to protect against potential fire
spread, as detailed within Clause C3.4 of the BCA.
Page | 16 www.coreengineering.com.au
Newmarket Green - Display Suite
09 June 2017 | Final Issue | Report No F200372_NMG Display Suite_FER_02
and the consequence of failure associated with an element. Further to this, the assessment of a building must
ensure that structural stability is maintained for occupant evacuation and for fire brigade intervention
operations.
The intent of Performance Requirement CP2 is to reduce the spread of fire both within a building and between
buildings. The Guide to the BCA states that the intent of Clause C3.2 is “to require any opening in external
walls to be protected, only where the wall is required to have an FRL, to prevent the spread of fire from the
boundary of an adjoining allotment, or one building to another on the same allotment”.
Page | 17 www.coreengineering.com.au
Newmarket Green - Display Suite
09 June 2017 | Final Issue | Report No F200372_NMG Display Suite_FER_02
Additionally, a reduced fire risk is expected to the south where the external walls are within 3 m of the site
boundary, but no buildings are present. The risk of a fire beginning in these adjacent buildings and impacting
upon the Display Suite building is then seen to be reduced to a level that is equivalent or improved to that
encountered within a DtS compliant scenario. Performance Solution CP2 can then be seen to be addressed.
Due to the largely open plan nature of the space and the minimal floor area of 344 m², it is anticipated that
should a fire occur that has the potential to impact the Display Suite building, occupants will be alerted to the
presence of a fire with minimal delay, resulting in a low pre-movement time. Given the retail nature of the
space, occupants within the building will be awake and alert, and can be relied upon to promptly evacuate
under the direction of the staff present once they become aware of a fire emergency. Occupants are seen to
be provided with compliant travel distances to an exit within the Display Suite building. Proulx [12] provides
data that the average travel speed of mobility impaired occupants is 0.8 m/s. By utilising a travel speed of
0.8 m/s, it is likely that it will take occupants 25 s to evacuate from the building once they have been alerted to
a fire emergency. Given the minimal floors area, the population within the Display Suite building is also
considered to be minimal which is expected to further assist in evacuation as queueing is unlikely to be an
issue. Occupants are provided with the ability to evacuate in the northern, western and southern directions,
reducing the risk of entrapment.
Furthermore, the Display Suite building is a single-storey structure and therefore the external wall does not
support any additional elements aside from the roof. Should a part of the building’s external wall be exposed
to the effects of a fire and collapse, the failure of elements is expected to be localised to the vicinity of the fire,
after occupants have egressed away from the area or evacuated from the building entirely. Elements of the
external wall are to be constructed from Colorbond Steel which, whilst not achieving an FRL, can be assumed
to not immediately fail in the event of exposure to a fire. Considering these factors, it can be assumed that
egress pathways will be maintained for occupant evacuation from the building before the exposed external
wall becomes structurally compromised. As a result, the intent of Performance Solution CP1 has been
addressed.
Fire Spread from the Display Suite to an Adjacent Building
Clause 5.1(b) of Specification C1.1 states that an external wall for a Type C construction building is not required
to achieve an FRL in the direction to outside. As such, the proposed design is compliant with respect to
considering fire spread from the Display Suite to an adjacent building. Nevertheless, it is discussed to
demonstrate that the solution proposed provides an appropriate level of safety.
As mentioned previously, the adjacent buildings are vacant and occupant presence within these buildings is
therefore not anticipated for the duration of the Display Suite’s intended lifetime. For this reason, the impact
upon the adjacent buildings is negligible as occupant life safety is not considered to be a factor.
In comparison to a typical Class 6 space that the DtS Provisions consider, the fuel loads and ignition sources
are reduced. The sales & display area will comprise a space more akin to an office, therefore being limited to
paper items, tables and chairs. For the display suites themselves, they are to include items typically found
within a unit – such as lounges, a bed, tables and chairs and a kitchen – to provide an indicative layout to
occupants. Whilst these constitute fuel loads that cannot be discounted from the analysis, the leading causes
of fires within retail areas are not present within this Display Suite building, such as but not limited to cooking
and heating equipment, smoking materials, and laundry appliances. For this reason, the risk of a fire within the
Display Suite building is expected to be reduced compared to a DtS compliant scenario. Further, the risk of
fire spread is not anticipated to be greater than that of a DtS compliant design given that the building’s space
will not consist of stored goods as it facilitates the movement of occupants as they inspect the display suites
and consult with the staff on hand.
In the unlikely event that a fire begins within the Display Suite building, the open plan nature of the Display
Suite building means that occupants are likely to be alerted to the presence of a fire within its early growth
phase. Combined with the provision of compliant travel distances to evacuate from the building, and the
presence of staff occupants, the successful evacuation of occupants is assumed to occur before egress
pathways become compromised. Thereafter, a fire within the Display Suite building will lead to structural failure
of elements, inclusive of the roof. In this case, the fire will then be provided with the ability to directly vent heat
to atmosphere before it can impact upon adjacent buildings.
7.2.6 Conclusions
It is demonstrated that the external walls of the Display Suite building are not required to achieve a fire-
resistance level as the risk of fire spread is comparative to that of a DtS scenario. As such, openings within
these external walls are not to be afforded protection in accordance with Clause C3.4.
The Performance Solution described herein has been assessed in accordance with A0.3(a)(ii) and A0.5(d) and
therefore complies with the requirements of A0.7 and Performance Requirements CP1 and CP2.
Page | 18 www.coreengineering.com.au
Newmarket Green - Display Suite
09 June 2017 | Final Issue | Report No F200372_NMG Display Suite_FER_02
8.1 OVERVIEW
The following are the design requirements, to be undertaken by others, to achieve
the nominated fire safety objectives of this report.
All other items not specifically addressed are to be in accordance with DtS provisions
Fire Engineering of the BCA or as accepted by the relevant authorities. Any change in this information
Requirements
to suit future building works or re-organisation will require further analysis to confirm
compliance with the regulations and this Fire Engineering Report.
Page | 19 www.coreengineering.com.au
Newmarket Green - Display Suite
09 June 2017 | Final Issue | Report No F200372_NMG Display Suite_FER_02
9 NOMENCLATURE
ACRONYM EXPANSION
ABCB Australian Building Codes Board
AFSS Annual Fire Safety Statement
BCA Building Code of Australia
CFD Computational Fluid Dynamics
DtS Deemed-to-Satisfy
EPA Environmental Protection Agency
FCC Fire Control Centre
FER Fire Engineering Report
FIP Fire Indicator Panel
FRL Fire Resistance Level
FRNSW Fire Rescue NSW
FSS Fire Safety Strategy
IFEG International Fire Engineering Guidelines
NCC National Construction Code
NFPA National Fire Protection Association
OHS Occupational Health and Safety
RTI Response Time Index
Page | 20 www.coreengineering.com.au
Newmarket Green - Display Suite
09 June 2017 | Final Issue | Report No F200372_NMG Display Suite_FER_02
10 REFERENCES
1. ABCB, “Building Code of Australia, Volume One”, CanPrint Communications, Canberra 2016.
2. ABCB, “Guide to the BCA 2016”, CanPrint Communications, Canberra 2016.
3. ABCB, “International Fire Engineering Guidelines”, ABCB, Canberra, 2005.
4. Alpert, Ronald L “Ceiling Jet Flows”, Chapter 2-2, The SFPE Handbook of Fire Protection Engineering
4th Edition, National Fire Protection Association, Quincy Massachusetts USA 2008, pp. 2-21-2-36.
5. Bryan, John L., “Behavioural Response to Fire and Smoke”, Section Three – Chapter 11, The SFPE
Handbook of Fire Protection Engineering, 4th Edition, National Fire Protection Association, Quincy
Massachusetts USA 2008.
6. BS 9999: Code of practice for fire safety in the design, management and use of buildings, October
2008.
7. England, J., “Guide for the design of fire resistance barriers and structures”, Building Control
Commission, Australia, 2000.
8. Evarts, B., “U.S. Structure Fires in Stores and other Mercantile Properties”, National Fire Protection
Association, Quincy MA, January 2011.
9. Fire Analysis Research Division, ‘Structure Fires by Occupancy’ 2007-2011 – Annual Averages’,
National Fire Protection Association, Quincy MA, April 2013.
10. “Fire Brigade Intervention Model V2.2”, Australasian Fire Authorities Council, October 2004.
11. National Fire Protection Association, ‘Fire Protection Handbook’, 19 th edition, Volumes I and II, 2003.
12. Proulx, G. Movement of People: “Evacuation Time”, Section 3-12, The SFPE Handbook of Fire
Protection Engineering (4th Edition), DiNenno, P.J. (ed.) National Fire Protection Association, Quincy,
MA 02269, 2008 pp. 3-355-372.
13. Spearpoint., M., “Fire Engineering Design Guide” Third Edition, New Zealand Centre for Advance
Engineering, May 2008.
14. Society for Fire Safety, NSW Chapter, “Practice Note for Tenability Criteria in Building Fires”, Version
2.0, Engineers Australia, April 2014.
15. Society of Fire Protection Engineers “Engineering Guide to Human Behaviour in Fire”, Review Draft
August 2002, The SFPE Engineering Guide to Human Behaviour in Fire, June 2002.
16. Society of Fire Protection Engineers, ‘Handbook of Fire Protection Engineers’, 3rd Edition, 2002.
17. Technical Report FCRC-TR 96-02: Building Fire Scenarios – An analysis of Fire Incident Statistics,
Fire Code Reform Research Program, March 1996.
18. Technical Standard, “NFPA 92B: Standard for Smoke Management Systems in Malls, Atria and Large
Spaces”, National Fire Protection Association (NFPA), 2009.
Page | 21 www.coreengineering.com.au
Newmarket Green - Display Suite
09 June 2017 | Final Issue | Report No F200372_NMG Display Suite_FER_02
APPENDIX A STATISTICS
FIRE STATISTICS
In order to assess the most likely fire hazards within the building, and subsequently the risk presented by these
hazards it is necessary to develop an understanding of the factors that have an influence on the fire safety of
building occupants. The best method in doing so is to review existing statistical data.
Existing data is an invaluable tool in providing an overview of the situations in which occupant deaths have,
and are likely to occur, and factors that contribute to more severe fires. This aids in understanding, and helps
evaluate the effectiveness of, and the need for various fire safety systems. Reference is made to the American
database as it is significantly larger than Australian data sets, but is generally considered to be representative
of the Australian situation.
Table A-1: Civilian fatalities in various occupancy types
Alarm time
Figure A-1 presents the percentage of fires by time of alarm. The figure shows fires are more common during
the day. The peak time for fires in these properties is between 09:00 and 21:00, accounting for 60% of fires.
However, the 12-hour night period of 21:00 to 09:00 still accounts for a large portion of the total fires (40%).
6%
5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5%
Percentage of total fires (%)
5%
4% 4% 4%
4%
3% 3% 3% 3% 3% 3% 3% 3% 3%
3%
2%
1%
0%
0000-0100
0100-0200
0200-0300
0300-0400
0400-0500
0500-0600
0600-0700
0700-0800
0800-0900
0900-1000
1000-1100
1100-1200
1200-1300
1300-1400
1400-1500
1500-1600
1600-1700
1700-1800
1800-1900
1900-2000
2000-2100
2100-2200
2200-2300
2300-0000
Figure A-1: Fires by alarm time for stores and other mercantile properties [8]
Causes of fires
Figure A-2 presents the leading cause of fire in stores and mercantile properties. The figure illustrates that
cooking equipment is the most probable cause of fires in these properties, accounting for 19% of fires.
Electrical distribution and lighting equipment was involved in 12% of the fires. And intentional ignition caused
11% of the total fires in these properties.
Smoking materials 9%
Intentional 11%
Figure A-2: Leading causes of fires in stores and other mercantile properties [8]
Office 3%
Bathroom/locker room 4%
Laundry area 5%
Storage area 7%
Figure A-3: Leading areas of origin of fires in stores and other mercantile properties [8]
Extent of fire spread
Figure A-4 presents data on the extent of fire spread for stores and other mercantile properties. Three-quarters
(77%) of the fires were confined to the room of origin. 3% of fires spread beyond the building of origin.
It should be noted that the probability of whether a fire spreads beyond the room of origin is considered
approximately equivalent to the occurrence of that fire reaching flashover [7]. This is based upon the
reasonable assumption that if automatic or human/manual fire suppression was to occur to control fire growth,
that this is likely to only be effective if it is carried out prior to a fire spreading beyond the room of origin - due
to high risk to life safety in the room of origin and the fact that if a fire has spread from a room, it has most
likely fully involved the room of origin.
3%
17% Confined or contained fire identified by
32% incident type
Confined to object of origin
4%
Confined to room of origin
29%
Figure A-4: Extent of fire spread for stores and other mercantile properties [8]
FIRE LOAD
The fire load within a room or compartment will influence the duration and severity of a fire and resultant hazard
to occupants. The effective fire load for the building has been estimated by consideration of the typical spaces
within the building.
The following fire loads have been extracted from Chapter 3.4 of the International Fire Engineering Guidelines
[3] and are listed in Table 6-1. This data is derived from Switzerland, however is also applicable to buildings in
Australia of similar use.
Table A-2: Fire Load Densities
The IFEG indicates that for well-defined occupancies, average values should be multiplied by a factor of 1.35
to 1.65 to reach the 90% fractile value and for isolated peak values a factor of 2 should be used.
(a) t-squared fire, rates of energy release (b) Relation of t-squared fires to some fire tests
Figure A-5: NFPA 92B Design Fires and Heat Release Rates
A slow fire growth is not considered to be the most challenging in terms of fire and life safety or fire brigade
intervention.
The continued growth of a fire defined by the above equation relies on both a sufficient source of fuel and air
and assumes that flashover has not been reached. The rate of fire growth can be estimated from data
published in British Standard (BS) 9999:2008 [6] as shown below.
Table A-3: Fire Growth Rates as Specified in BS 9999:2008
From the above table, it is concluded that the likely fire scenarios in this Display Suite building may be
approximated by the standard medium time-squared fire growth rate curve.
Margin of Safety
An important consideration in any timeline analysis is the margin of safety (tmargin) and is represented by the
difference between the ASET (tASET) and RSET (tRSET) as shown in the following equation:
tmargin= tASET - tRSET
Typically for a base case scenario the following relationship must be satisfied:
tASET ≥ 1.5 x tRSET