Windows Data:
Door Data:
Rooms Data:
D3 …………………………………………... 16
W3 …………………………………………. 12
Design Conditions:
Table 1.1
ROOM 1
A. Solar Gain – Glass
Southeast---------------------- 12 ft2
Southwest--------------------- 20 ft2
Btu
U = 0.94 2
ft −hr−℉
➢ To find the Temperature Difference (°F)
(ASHRAE GRP 158; Table 3.18, page 3.31) (see table 1.3)
ΔT of W1 at Southeast: 14 °F
ΔT of W4 at Southwest: 57 °F
Btu
For SE: 12 x 0.94 2
x 14 ℉
ft −hr−℉
Btu
Q = 157.92
hr
Btu
For SW: 20 x 0.94 2
x 57 ℉
ft −hr −℉
Btu
Q = 1071.6
hr
B. SOLAR AND TRANSMISSION GAIN (Walls and Roof)
X Y
4 0.71
6 0.91
8 1.11
Republic of the Philippines
CAMARINES SUR POLYTECHNIC COLLEGES
Nabua, Camarines Sur
COLLEGE OF ENGINEERING AND ARCHITECTURE
SI MATERIAL RESISTANCE
2 Btu
Qw ( SE)=78.84 ft x 0.38 2
x 30 ℉=898.776
f t −hr−℉
2 Btu
Qw ( S w )=148 ft x 0.38 2
x 24.5 ℉=1377.88
f t −hr−℉
C. Roof Ceiling:
➢ To find U of Roof/Ceiling
SI MATERIAL RESISTANCE
3 No insulation 0.00
5 Plywood 0.31
∑ R=2.4
1 1
U roof = = =u=0.4167
∑R 24
Transmission gain:
E. Partition, 𝑄 = 𝐴p 𝑥 𝑈p 𝑥 𝛥T
SI MATERIAL RESISTANCE
➢ To find 𝜟𝑻p
21.8 – 5 = 16.8 °F
➢ To find Qpartition
𝑄 = 𝐴p 𝑥 𝑈p 𝑥 𝛥T
Republic of the Philippines
CAMARINES SUR POLYTECHNIC COLLEGES
Nabua, Camarines Sur
COLLEGE OF ENGINEERING AND ARCHITECTURE
Btu
¿ 1829.34
hr
F. Ceiling: 𝑄𝑐𝑒𝑖𝑙𝑖𝑛𝑔 = 𝐴 𝑥 𝑈 𝑥 𝛥𝑇
Btu
= 105.98 ft x 0.4167 x 38 = 1678.1509
hr
G. Floor: 𝑄𝑓𝑙𝑜𝑜𝑟 = 𝐴f 𝑥 𝑈f 𝑥 𝛥𝑇
(Ashrae, Table 3.1A, Thermal properties of typical building & insulating materials)
Btu
= 105.98 x 0.05 x 16.8 = 65.1
hr
Internal Heat
(Latent Heat)
B. Lighting
Republic of the Philippines
CAMARINES SUR POLYTECHNIC COLLEGES
Nabua, Camarines Sur
COLLEGE OF ENGINEERING AND ARCHITECTURE
1 watt
Q lighting=105.98 x 2
x 3.4 1 = 361.3918 Btu
ft hr
C. Equipments
EQUIPMENTS Wattage
Laptop 70 watts
Incandescent Lamp 30 watts
Cellphone 3 watts
TOTAL: 103 watts
CFM = 5 x 2 =10
Q = 41.390352 𝐵𝑡𝑢/hr.
Qs =303.529248 𝐵𝑡𝑢/hr.
QL = 613.6592 𝐵𝑡𝑢/hr.
SF = 9908.769 x 0.05
SF = 495.44
Qt = SF + Qsubtotal
Tonnage, TR
Tonnage = 0.86