You are on page 1of 1

NO.

2024HINDxx
Date 30.1.2024

RFQ of ALDAS
Subject: Required Parameter for Active Line High Current Impedance testing Setup.

Requirement for Active Line Impedance testing setup

Sr.no Requirement Selection/Discription


1 Purpose of Impedance Measurement (please specify)
Target of Measurement (Device under test)
2
[EC stack/ Fuel Cell/Other (please specify)]
Operation environment
3
[Laboratory/indoor factory/outdoor/Other(Please specify)]
4 Total number of cells in a stack
5 Number of cells to be measured
6 Stack Measurement [Required/ Not Required]
Type of Cell
7
[PEM/SOFC/Alkali/AEM/Other(Please specify)]
8 Voltage of Stack [V]
9 Voltage per Cell [V]
10 Load Current (DC current provided to/from DUT) [A]
11 Measurement Frequency Range [Hz] to [Hz]
12 Estimated Resistance (Approximate Value is acceptable) [Ohm]
13 Area of Cell [mm2]

Questions from the customer:

Expected Installment Date: __ / __ / ____

General Manager

Hioki India Pvt. Ltd.