E I FIVE MASSIVE INFRA

& $UPPLY CORP


ffi E
Door 2 Mitra Building
San Pedro $t., Davao City
TrN 43S-364-629-S00
lrt t.r.lll

Tel # 285-4965

Engr. Jonathan S. Dapar, Jr.


Office of the Municipal Engineer
MENRO-LGU JAS
Jose Abad Santos. Davao Occidental

Project Description: Construction of Storage Facility

Subject: Construction Cost Vlaterials & Labor & Others.

SCOPE OF PROPOSED WORK:

ITEM l0l - Ren-roval of structttres and obstructiqrn


II'EN{ 103 - Structure Excavation
ITEM 900 - Reinlbrce Concrete Work
ITEM 1013 - Corrugated Metal Roofing
ITEM 7 12 - Structure Metal
ITEM 7A9 - Painting Work
SPL 1-Electrical Work

BILL OF MATERIALS AND COST OF LABOR WITH EQUIPMENT. NEEDED.

ITEM 101 -Removal of structure and obstruction Labor - 8,500.00


VatiEvat - s 10.00
Con. Prof-rt - 680.00
OCM 680.00
TOTAL - 10,370.00

ITEM 103 - Skucture Excavation Labor - 23,200.00


Vat/Evat - 1.392.00
Con. Profit - I,856.00
OCM 1.856.00
TOTAL - 28,304.00
ITEM 900 - Reinforce Concrete Work:
a. Materials - Foundation and Colurnn;
Portland Cement - 50 Bags @,320.00 16,000"00
Wash Gravel - 6 cu. m. r@. 1.000.00 6.000.00
Waslied Sand - 3 cu. nl. @. :
1,000.00 3.000.00
16mm def. Bars - 64 f.. @) 580.00 : 37,120.00
-
l0rnrn def. steel bar 80 L. @230.00 - 18,400.00
lx4x8 ord. Plyboard - 10 Shts. @ 1,350.00 13,500.00
Tie Wire #16 - l2k1s. @ 85.00 1.020.00
C.W.Nail#4 - 5kls.@80.00 400.00