K CONSTRUCTION & TRADING CO.

, LTD
BILL OF QUANTITIES SOLA ROOF STEEL STRUCTURE No. #162, St 271, Sangkat Bang Salang, Khan Toul Kork,
Phnom Penh, Cambodia .
Tel. +855 (0) 81-592-085
Email : vebolkooy5@gmail.com

Project Name : SOLA ROOF STEEL STRUCTURE AT ROYAL P.P HOSPITAL


Project No. : QT-KCT- SOLA ROOF STEEL STRUCTURE -002.. Rev.002 Up Date : 20-Sep-2019
Location : ROYAL PHNOM PENH HOSPITAL, CAMBODIA. 0 0.002
COST BREAKDOWN
UNIT PRICE AMOUNT
ITEMS DESCRIPTIONS UNIT QTY MATERIAL LABOUR
(USD) (USD)
RATE TOTAL RATE TOTAL
I SOLA ROOF STEEL STRUCTURE AT ROYAL P.P HOSPITAL
A Preliminary Work
a.1 Mobilization and Demobilization Ls 1.00 $ - $ - $ 1,000.00 $ 1,000.00 $ 1,000.00 $ 1,000.00

a.2 Supervision and Indirect labour Ls 1.00 $ - $ - $ 1,000.00 $ 1,000.00 $ 1,000.00 $ 1,000.00

a.3 Safety Cost and Management Cost Ls 1.00 $ - $ - $ 1,500.00 $ 1,500.00 $ 1,500.00 $ 1,500.00

SUB TOTAL/A $ 3,500.00

B SOLA ROOF STEEL STEEL STRUCTURE WORKS


B.1 ZONE A_TRUSS STRUCTURE SHS235 (Fy=23.5 KN/cm2)
1.1 Rafter CHS 90x2.5mm Ton 0.35 $ 1,100.000 $ 388.48 $ 250.000 $ 88.29 $ 1,350.00 $ 476.77

1.2 Rafter bracing element CHS 42x2.0mm Ton 1.05 $ 1,100.000 $ 1,151.17 $ 250.000 $ 261.63 $ 1,350.00 $ 1,412.80
1.3 Diagonal CHS 42x2.0mm Ton 0.70 $ 1,100.000 $ 767.45 $ 250.000 $ 174.42 $ 1,350.00 $ 941.87

1.4 Purlin CHS 49x2.0mm Ton 3.28 $ 1,100.000 $ 3,610.66 $ 250.000 $ 820.61 $ 1,350.00 $ 4,431.27
Anti rust paint, Welding ϕ2.5mm, ϕ3.0mm, Fixingscrew (RS)50 - CS-
1.5 Ls 1.00 $ 1,089.405 $ 1,089.41 $ - $ - $ 1,089.41 $ 1,089.41
5x60, accessories,…,etc
B.2 ZONE B,C,D_TRUSS STRUCTURE SHS235 (Fy=23.5 KN/cm2)
2.1 Rafter CHS 90x2.5mm Ton 1.18 $ 1,100.000 $ 1,294.92 $ 250.000 $ 294.30 $ 1,350.00 $ 1,589.22
2.2 Rafter bracing element CHS 42x2.0mm Ton 3.49 $ 1,100.000 $ 3,837.24 $ 250.000 $ 872.10 $ 1,350.00 $ 4,709.34

2.3 Diagonal CHS 42x2.0mm Ton 2.33 $ 1,100.000 $ 2,558.16 $ 250.000 $ 581.40 $ 1,350.00 $ 3,139.56
2.4 Purlin CHS 49x2.0mm Ton 11.24 $ 1,100.000 $ 12,360.15 $ 250.000 $ 2,809.13 $ 1,350.00 $ 15,169.28
Anti rust paint, Welding ϕ2.5mm, ϕ3.0mm, Fixingscrew (RS)50 - CS-
2.5 Ls 1.00 $ 3,937.183 $ 3,937.18 $ - $ - $ 3,937.18 $ 3,937.18
5x60, accessories,…,etc
B.3 EAST PARKING_TRUSS STRUCTURE SHS235 (Fy=23.5 KN/cm2)
3.1 Rafter CHS 90x2.5mm Ton 0.88 $ 1,100.000 $ 971.19 $ 250.000 $ 220.73 $ 1,350.00 $ 1,191.92
3.2 Rafter bracing element CHS 42x2.0mm Ton 0.58 $ 1,100.000 $ 639.54 $ 250.000 $ 145.35 $ 1,350.00 $ 784.89
3.3 Diagonal CHS 42x2.0mm Ton 0.54 $ 1,100.000 $ 596.90 $ 250.000 $ 135.66 $ 1,350.00 $ 732.56
3.4 Purlin CHS 49x2.0mm Ton 1.30 $ 1,100.000 $ 1,428.28 $ 250.000 $ 324.61 $ 1,350.00 $ 1,752.89
Anti rust paint, Welding ϕ2.5mm, ϕ3.0mm, Fixingscrew (RS)50 - CS-
3.5 Ls 1.00 $ 669.339 $ 669.34 $ - $ - $ 669.34 $ 669.34
5x60, accessories,…,etc
B.4 MOTORBIKE PARKING_TRUSS STRUCTURE SHS235 (Fy=23.5 KN/cm2)

4.1 Rafter CHS 90x2.5mm Ton 0.71 $ 1,100.000 $ 776.95 $ 250.000 $ 176.58 $ 1,350.00 $ 953.53
4.2 Rafter bracing element CHS 42x2.0mm Ton 0.48 $ 1,100.000 $ 532.95 $ 250.000 $ 121.13 $ 1,350.00 $ 654.08
4.3 Diagonal CHS 42x2.0mm Ton 0.52 $ 1,100.000 $ 575.59 $ 250.000 $ 130.82 $ 1,350.00 $ 706.40
4.4 Purlin CHS 49x2.4mm Ton 1.20 $ 1,100.000 $ 1,318.42 $ 250.000 $ 299.64 $ 1,350.00 $ 1,618.06
Anti rust paint, Welding ϕ2.5mm, ϕ3.0mm, Fixingscrew (RS)50 - CS-
4.5 Ls 1.00 $ 589.810 $ 589.81 $ - $ - $ 589.81 $ 589.81
5x60, accessories,…,etc
SUB TOTAL/B $ 46,550.00

SUB TOTAL(A+B) $ 50,050.00

DISCOUNT (2%) $ 1,001.00


VAT 10% ( Excluded VAT on
$ 4,904.90
DutyTAX)
I GRAND TOTAL ON EXSPENSE COST $ 53,953.90

PAYMENT TERMS
40% of the price shall be paid as a down payment ("Down Payment" and shall be paid not later than 07 days from the
1)
date of signing this Agreement. The balance of 60% of the Price("Balance Payment") shall be paid as follow:
2) 35% of constract value within 07 days from the date of delivery of all Materials at Site.

3) 25% of constract value within 07 days from the date of completion & hondower of the Work to Buyer.

4) Welding use Electrode JIS E43xx (Kobe Steel Product).

5) All main steel member are comply with strength (fy=235MPa).

6) All materials are Included TAXES.

7) We used black steel and painting U90 (Colour by owner).

8) Electricity supply by owner.

Customer read and approved


Authorized Signature
For..........................................................
For.......................................................

Mr. Yeng Seanghak


Mr. Lucas FERRAND
K CONSTRUCTION & TRADING Co., Ltd
GENESIS TECH Co., Ltd
(Managing Director)
(Project Manager)