BILL OF QUANTITIES SOLA ROOF STEEL STRUCTURE No. #162, St 271, Sangkat Bang Salang, Khan Toul Kork,
Phnom Penh, Cambodia .
Tel. +855 (0) 81-592-085
Email : vebolkooy5@gmail.com
a.2 Supervision and Indirect labour Ls 1.00 $ - $ - $ 1,000.00 $ 1,000.00 $ 1,000.00 $ 1,000.00
a.3 Safety Cost and Management Cost Ls 1.00 $ - $ - $ 1,500.00 $ 1,500.00 $ 1,500.00 $ 1,500.00
1.2 Rafter bracing element CHS 42x2.0mm Ton 1.05 $ 1,100.000 $ 1,151.17 $ 250.000 $ 261.63 $ 1,350.00 $ 1,412.80
1.3 Diagonal CHS 42x2.0mm Ton 0.70 $ 1,100.000 $ 767.45 $ 250.000 $ 174.42 $ 1,350.00 $ 941.87
1.4 Purlin CHS 49x2.0mm Ton 3.28 $ 1,100.000 $ 3,610.66 $ 250.000 $ 820.61 $ 1,350.00 $ 4,431.27
Anti rust paint, Welding ϕ2.5mm, ϕ3.0mm, Fixingscrew (RS)50 - CS-
1.5 Ls 1.00 $ 1,089.405 $ 1,089.41 $ - $ - $ 1,089.41 $ 1,089.41
5x60, accessories,…,etc
B.2 ZONE B,C,D_TRUSS STRUCTURE SHS235 (Fy=23.5 KN/cm2)
2.1 Rafter CHS 90x2.5mm Ton 1.18 $ 1,100.000 $ 1,294.92 $ 250.000 $ 294.30 $ 1,350.00 $ 1,589.22
2.2 Rafter bracing element CHS 42x2.0mm Ton 3.49 $ 1,100.000 $ 3,837.24 $ 250.000 $ 872.10 $ 1,350.00 $ 4,709.34
2.3 Diagonal CHS 42x2.0mm Ton 2.33 $ 1,100.000 $ 2,558.16 $ 250.000 $ 581.40 $ 1,350.00 $ 3,139.56
2.4 Purlin CHS 49x2.0mm Ton 11.24 $ 1,100.000 $ 12,360.15 $ 250.000 $ 2,809.13 $ 1,350.00 $ 15,169.28
Anti rust paint, Welding ϕ2.5mm, ϕ3.0mm, Fixingscrew (RS)50 - CS-
2.5 Ls 1.00 $ 3,937.183 $ 3,937.18 $ - $ - $ 3,937.18 $ 3,937.18
5x60, accessories,…,etc
B.3 EAST PARKING_TRUSS STRUCTURE SHS235 (Fy=23.5 KN/cm2)
3.1 Rafter CHS 90x2.5mm Ton 0.88 $ 1,100.000 $ 971.19 $ 250.000 $ 220.73 $ 1,350.00 $ 1,191.92
3.2 Rafter bracing element CHS 42x2.0mm Ton 0.58 $ 1,100.000 $ 639.54 $ 250.000 $ 145.35 $ 1,350.00 $ 784.89
3.3 Diagonal CHS 42x2.0mm Ton 0.54 $ 1,100.000 $ 596.90 $ 250.000 $ 135.66 $ 1,350.00 $ 732.56
3.4 Purlin CHS 49x2.0mm Ton 1.30 $ 1,100.000 $ 1,428.28 $ 250.000 $ 324.61 $ 1,350.00 $ 1,752.89
Anti rust paint, Welding ϕ2.5mm, ϕ3.0mm, Fixingscrew (RS)50 - CS-
3.5 Ls 1.00 $ 669.339 $ 669.34 $ - $ - $ 669.34 $ 669.34
5x60, accessories,…,etc
B.4 MOTORBIKE PARKING_TRUSS STRUCTURE SHS235 (Fy=23.5 KN/cm2)
4.1 Rafter CHS 90x2.5mm Ton 0.71 $ 1,100.000 $ 776.95 $ 250.000 $ 176.58 $ 1,350.00 $ 953.53
4.2 Rafter bracing element CHS 42x2.0mm Ton 0.48 $ 1,100.000 $ 532.95 $ 250.000 $ 121.13 $ 1,350.00 $ 654.08
4.3 Diagonal CHS 42x2.0mm Ton 0.52 $ 1,100.000 $ 575.59 $ 250.000 $ 130.82 $ 1,350.00 $ 706.40
4.4 Purlin CHS 49x2.4mm Ton 1.20 $ 1,100.000 $ 1,318.42 $ 250.000 $ 299.64 $ 1,350.00 $ 1,618.06
Anti rust paint, Welding ϕ2.5mm, ϕ3.0mm, Fixingscrew (RS)50 - CS-
4.5 Ls 1.00 $ 589.810 $ 589.81 $ - $ - $ 589.81 $ 589.81
5x60, accessories,…,etc
SUB TOTAL/B $ 46,550.00
PAYMENT TERMS
40% of the price shall be paid as a down payment ("Down Payment" and shall be paid not later than 07 days from the
1)
date of signing this Agreement. The balance of 60% of the Price("Balance Payment") shall be paid as follow:
2) 35% of constract value within 07 days from the date of delivery of all Materials at Site.
3) 25% of constract value within 07 days from the date of completion & hondower of the Work to Buyer.