You are on page 1of 2

 Implementation of Rural Water Supply Projects in the State of Uttar Pradesh under

the Jal Jeevan Mission- Third Party Inspection (TPI) and Monitoring of Physical &
Financial Progress of various Rural Water Supply projects of State Water &
Sanitation Mission(SWSM) in the State of Uttar Pradesh-Agra Cluster
 DURATION: -7TH FEB 2022 TO Till Date
JOB RESPONSIBILITY
 Review of the Geotechnical Reports such as preliminary layouts, SBC, settlement,
Bore logs, soil testing report( Lab & Field) and activity appropriately as
Geotechnical Engineer ensuring implementation of work as per IS specifications
and review of construction documents of substructures/super structures as per
approved design and drawings.
 Responsible for study of BOQ (Bill of Quantity) as per specifications and taking out
quantities from drawings.
 Preparation and Certification of RA bills.
 Preparation of monthly reconciliation statement of materials.
 Preparation Weekly, Monthly Progress Reports.
 Monitor the work plan, identify stakes, slippages, and suggest remedial measures
and Monitor adequacy of manpower, machinery and other resources to meet
target and ensure safety.
 Check Measurement and certify the RA bills of the contractor..
 Bill verification work after uploading bill online to JJMUP website.
 Design Review and inspection report formatting of submitted RFI by client.
 Inspection of materials, machineries and equipment at site.
 Inspection of Construction activities, testing of materials at site.
 Monitoring of the Cost Based project (Physical & Financial)
 Assist in commissioning activities.
 Existing Intake well Narora Barrage(Ganga River)-450 MLD and WTP-378 MLD
and the proposed Master MBR at Agra district level (GSR&PH)- 13 MLD
(Discharge 597 LPS, Head 70m, HSC Pump-6W+3S),Zonal MBR 600 KL to 1300
KL – 15 Zonal MBR, ESR 50 KL to 500 KL (Staging 12m to 18m)-293 Nos,House
Connection – 2,73,075, Raw water Rising Main from Intake well to WTP MS 2000
mm dia (14 mm Thickness)– 10.40 km, Clear water Rising Main from WTP to Agra
Master MBR (MS 2000 mm dia-90.50KM& MS 1800 mm dia-29.75 km) ,Clear
water Rising Main from Agra Master MBR to Zonal MBR (DI K-9 350-600mm dia.-
102.298 km & MS 650-1900 mm Dia -219.826 km) ,Clear water Rising Main from
Zonal MBR to ESR (DI K-9 100-600mm dia.-1495.32 km),Distribution Network -
5840.399 km (HDPE PE 100, PN6 pipe 63 mm to 200 mm Dia-5654.853& DI K-7
250mm,300mm,350mm Dia-185.546 Km),Clear water pumping Machinery at WTP
in 15 blocks of Agra district.

You might also like