Professional Documents
Culture Documents
A NEW SITE
GRP 1 ☺ – ANDREA – ANISH – DHARSHAN – SWETA – SHERAZ
INTRODUCTION
The construction industry, like any other industry, requires efficient management of
human resources and material for successful completion of a project at an optimum cost.
Building construction and management as a subject has a wide scope and to better
understand it, practical experience is essential. Problems that are bound to crop up in
every project, can be handled expertly by the site engineer. An efficient site set-up is one
of the most basic and the simplest aspect of a systematic, planned, economical and safe
construction. It ensures better utilization of available resources, equipments, materials and
a better control over the project. Detailed planning along with good management ensures
that the work is not held up at any stage. Periodical/inspection of the site coupled with
suggestions helps in completion of the work as per the time schedules and quality
standards.
RESPONSIBILITIES OF SITE STAFF
Successful completion of a project in all respects calls for the following qualities in the site staff :
▪ Hard work
▪ Complete devotion to work
▪ Consciousness of responsibilities
▪ Awareness of new techniques and products
▪ Decision making capacity to meet the challenges.
GENERAL SITE RULES
▪ The site engineer must strictly follow the working hours of the site. He is expected to report at the
site at least 15 minutes before schedule to ensure proper allocation of the work for smooth
functioning. Site in-charge may instruct a junior engineer/supervisor/storekeeper to be present on
site in case of unavailability.
▪ The site engineer/supervisor is responsible for the on-time completion of the targeted job. In case
of a backlog, extra hours should be put in to complete the work.
▪ Similarly, for every slab concreting. The site engineer and the supervisor should be present at the
site till the completion of the slab.
▪ Employment of child labour is forbidden.
▪ Any accident on site, should be reported to the Head Office immediately. This will enable the
management to take immediate action to help the affected employee.
Watch on Machineries
• All machineries should be under strict vigilance and suitable maintenance arrangements should be made on
site.
• Proper locking arrangements should be made for all the pumps and motors and electrical meter cabling and
motors witches should also be locked to avoid misuse and further damage to the machinery.
Cleaning/Boards/Gardening
• The site should be neat and clean.
• Signs/hoardings should be placed appropriately.
• The way to site' boards and any other board on site should be cleaned and properly painted with necessary
gardening plans and should be watered regularly.
SITE SET-UP &
DAY TO DAY WORKING
Initial planning, management and setting of project is the basis for successful execution of building construction
The following guidelines for starting a new project in a professional manner to give the right momentum to the
work from the word go.
- 7/12 extract copy, Agreement copy between the landlord and builder.
- Demarcation drawing copy from D.L.R.'s(District Land Record) office.
- Copy of the notice given by the legal advisor In local newspapers, about the project.
- Copy of the power of attorney issued by the owner, if any
- Copy of the layout plan showing boundaries of the plot from the concerned Architect.
- Copy of the N.A. Certificate. These documents prove very useful on the site while
commencing the project, to avoid any disputes of land with the adjacent plot holders,
government authorities or even the land owner.
- All the drawings of the proposed project should be at site before starting the work.
- The Architect should give all the drawings, including the layout drawings, well before starting the
project, excepting any revisions in the drawings.
- The site engineer should prepare the list of all the drawings required, from time to time.
- He should collect the drawings from the concerned Consultant/Architect, duly stamped and signed
by the chief engineer or other higher authority, as an approval for working at site.
PREPARATION ON SITE
CLEANING SITE AND LEVELLING: Before starting any work on the site the land should be cleaned unwanted trees should be
cut down.
BOUNDARIES MARKING: Before the commencing of work on site the project engineer should demand for the services.
A small temporary shed using G.I sheets should be erected at a location nearest to the proposed entrance of the project.
DEMARCATION OF THE THEODOLITE SURVEY: Theodolite survey for actual demarcation should be done with reference to the
existing boundaries .
CONTOUR SURVEY: Contour survey means surveying the actual level i.e. ups and downs of the plot. This survey should be done
by Dumpy level. Fix the permanent benchmark with reference to the main road/approach road on existing main drainagè chambers
top. The site engineer has to decide the grid interval at 3-meter, 6 meter as per the plot conditions.
Grid interval depends on the plot conditions i.e. for plain ground, for sloping ground, for steep ground, hilly areas etc.
PLANNING FOR APPROACH ROADS AND TEMPORARY STRUCTURES WATER STORAGE AND OTHER STRUCTURES:
Approach road and Internal roads are very Important for vehicular transport.
The side boundaries of the approach road should be marked with lime powder and guard
stones. The side boundaries of internal roads should be, marked with lime powder or steel rods.
WATER ARRANGEMENT:
Water arrangement is an Important aspect a the construction area.
In case of lack of sufficient water from corporation/other authorities/open well, drilling a bore well is
advisable.
Scarcity or non-availability of water will require approaching the tropical geological area to
find out the maximum ground water table for drilling a bore well.
ELECTRICITY ARRANGEMENT:
Electricity arrangement is another important aspect to a new site.
For this, normally a three-phase meter line is required to operate pumps, polishing machine
etc. and single phase for the provision of temporary streetlights, site offices. Watch man
cabin and general lighting.
COMPOUND WALL/ FENCING/ SECURITY FENCING: The compound wall should be constructed right at the start with a
view to improving the overall security of the project and other structures like watchman's cabin, store, site offices,
godowns, steel yards etc.
For the construction of the compound wall and the gate, a drawing should be issued by the Architect.
The actual construction of the compound wall begins after approval of this drawing.
GATE: A main gate and two wicket gates should be provided. A single entry point to the project/plot helps avoid theft problems, checks the
outgoing/incoming materials, controls site staff timing restrictions and the visitors/customer entries.
If the main gate is not fixed at least a 'stop and start pole' should be used, to be operated by the watchman.
Once the compound wall and gate is complete, plantation of trees along the fencing should be started.
CHECKING OF THE LAYOUT WITH ACTUAL BOUNDARIES: Before the main building line out begins, the site engineer must confirm the actual
boundaries as per the sanctioned layout plan and check the set back margins simultaneously.
Temporary markings of external buildings corner and other structures like under ground water tank, swimming tank etc. should be marked with steel
rods fixed in. Cement, projected 15cm above ground and painted with white oll paint.
Cross check this marking with set back from actual plot boundaries.
At this stage, all buildings should be properly shown on layout with their set back as per rules. This layout drawing should be approved by the
Architect and confirmed by the Resident Architect.
While checking this layout, mark open spaces and road portion on ground as per the approved layout drawings to ensure that all temporary structures
can be accommodated without causing any hindrances to the future structure.
TEMPORARY WATER STORAGE TANK: Tanks should be located centrally /at a suitable place nearest to all buildings to minimize the length of the
pipe and leakage as well as head losses at the time of curing.
Pipe line network should not disturb the temporary roads.
OTHER STRUCTURES: They include steel yards and miscellaneous godowns.
Steel yard doors should be sufficiently wide for safe arrivals/ departures of trucks. Temporary steel yard should be covered with
G.1. sheets supported by vertical bullies 2.5 m height, around the yard, so that entry of unauthorized persons will be restricted.
CEMENT GODOWNS: Cement godown should be centrally located, near the buildings without obstructing the
proposed permanent structure or the vehicular movement around it.
Flooring of cement godown should be raised to 45 cm above the existing ground level with smooth 1.P.S. floor furnishing.
This temporary structure can be made from G.I. sheets.
It should be 100% water proof with minimum openings and perfect security.
It should have sufficient capacity of storage for minimum 400 to 600 bags.
WATCH TOWER: A large area can be in the range of vision trea the highest point.
Any trespassers can be easily spotted from a higher point.
Larger projects should therefore have a center located watch-tower approximately 15 to 20-I above the ground level.
Flood lights fitted on this tower are advantageous from the security point of vara.
THANK YOU ☺