You are on page 1of 25

EC705 MSc.

Civil Engineering
(Construction)

ECM744 CONCSTRUCTION SITE AND


SAFETY MANAGEMENT
PROFESOR MADYA DR. AHMAD RUSLAN MOHD. RIDZUAN
M.C.S.M

FACULTY OF CIVIL ENGINEERING


UNIVERSITI TEKNOLOGI MARA
SITE ORGANISATION
Learning outcomes
• Be to plan and develop site organization
process [ CO2- PO4]
• Be to plan site organization with regard to
logistic, human resources, materials,
financial, operation and work schedule.
[ CO2- PO4]
Site Organisation
• Organising is the process of establishing orderly uses
for all resources within the management system.

• A primary focus is to determine what individuals will do


in an organisation and how their effort should be best
combined.

• An effective management system should take into


account the size, nature, complexity, scope and
purpose of the project.
Construction Team
Typical site organisation chart:

Site Manager

Senior Site
Safety Officer Q.S. Site Engineer
Supervisor

Site Supervisor Site Supervisor

Gangers Gangers

Operatives Operatives
Site Manager
• Check on quality of work and safety at
site.
• Prepare master program and site layout.
• Monitor progress of work and cash flow.
• Finalising the statement of construction
method.
• Control progress of the whole site.
• Allocate the number of labours needed at
site for certain work and time.
Quantity Surveyor
• Prepare progress payments, claims and
variation orders.
• Prepay payment certificate to sub-
contractors.
• Advice project manager on contractual
matters.
Safety Officer
• Advice Project Manager on construction
safety.
• Responsible for ensuring site workers
safety and all staff/personnel at site
obliged to site safety rules.
Site Engineer
• Supervision and co-ordination of civil and
structure work and ensure the quality of
work.

Site Supervisor
• Supervise and co-ordinate work at site.
• Liaise with consultant.
• Control document.
• Prepares daily report.
Ganger
• Allocate their workers for different trade of
works.
• Supervise daily work.

Operatives
• Work according to the instruction given by
the person in charge.
Site Records
• One of the main functions of the supervising team in a
construction project is to keep a good records of what
actually takes place during construction project.

• These records are kept in all construction sites in a


varies of different formats, ranging from written
documents to charts and drawings.

• Records are kept by two separate parties; contractor


and supervisor.

• Records related to Finance, Quality and Work


Progress.
IMPORTANCES OF RECORDS
• Establishing the basis of a claim for loss
and expense.
• Defending a counter claim from a client.
• Substantiating applications for extension
of time.
• Claiming payment for extra work not
included in the contract.
• Reporting to progress meetings.
Financial Records
• All measurements of work quantities plus
agreement of varied rates to allow proper
payments to be made to contractors.

Quality Records
• Related records document the result of
test carried out on materials used and on
the standard of workmanship.
Work Progress Record
• Aim to identify the works carried out during the
construction phase; include particulars showing
what happen, when it happen, the resources
used and any disruption or delay.

• Maintain through the contract period for different


purposes; providing a means of monitoring and
controlling, resolving conflict and disputes.
Progress Record
• Site diaries
• Weekly progress report
• Day work sheet
• Photographs
• As built programs/ schedules
• Minute of meetings
• etc…
Brief content in a construction progress
report
• Site organisation chart
• Work programme
• S-Curve
• Two weeks programme
• Material delivered to site
• Workforce record
• Rainfall record
• Arch/ engineer’s instruction
• Report on progress claim and payment
• Concrete test cube report
• Summary of work done
Site Planning & Management
Workers/Labour
• Proper management of workforce starts with
a good planning on the amount of workforce
needed to execute the task at hand.

• Includes labour, plant operator, site


supervisor and etc…

• No one should be kept idle at anytime


because it will waste money and time.
Material
• Proper planning of materials ensure every
materials is used wisely and fully to
minimise the probability of wastage.
• Eliminate double handling of materials.
Responsibilities can be divided as follows:
• Planning material delivery.
• Ordering the material.
• Checking delivery on site.
• Placing material on site.
• Processing delivery ticket and invoice.
• Controlling the use of materials.
• Producing a costing analysis.
• Paying for material
• Feedback and performance during construction.
Machineries
• Make full use of machineries.
• Improper planning will result either
insufficient machineries or wastage in
terms of working hours.
• Get the well trained and highly skill
operators.
• Maintenance.
Site Layout
Factors Influence Site Layout
• Location – urban, rural
• Space availability – open, confined
• Amenities, infrastructure, services
• Time of year – weather
• Plant & material – special plant, material nearby
• Access – how to get there, roads
• Material storage – space availability
• Workshop, pre-fabrication area
• Accomodation – workers accomodation
• Walfare facilities – canteen, toilet, water supply
• Security – theft, trespassing
• Health & safety – fire escape, dangerous materials

You might also like