WMS - Cable Fiber Optic Rev.01
WMS - Cable Fiber Optic Rev.01
Contract No:
1
Doc. No.
CABLE FIBER OPTIC INSTALATIONS BAP-EL-HNG-WMS-0003
Revision: 00 Doc. Status:
Contract No:
Contract No:
Table of Contents
3
Doc. No.
CABLE FIBER OPTIC INSTALATIONS BAP-EL-HNG-WMS-0003
Revision: 00 Doc. Status:
Contract No:
BAB 1. INTRODUCTION 5
BAB 2. REFERENCE 5
BAB 3. FLOWCHART 6
BAB 4. RESOURCES 7
BAB 5. PREPARATION 9
4
Doc. No.
CABLE FIBER OPTIC INSTALATIONS BAP-EL-HNG-WMS-0003
Revision: 00 Doc. Status:
Contract No:
BAB 1. INTRODUCTION
The Internet service is a high-speed service based on MPLS VPN technology with lastmile
fiber optics, thereby providing the best service quality and network security. Additionally
There are various methods of communication. The only method is CWDM (Coarse
which has a wider channel distance than previous WDM technology. This CWDM method is
applied as a development in the data transmission process to speed up data transfer and
increase bandwidth. Apart from using fiber optic and CWDM methods to communicate,
internet services also use switches as devices to support the service. Where the Switch
device is placed on the user's side and configured by providing VLAN and IP Address
according to the required allocation. In this case the author focuses on analyzing the
installation results of fiber optic cables and the advantages of the CWDM method as well as
the results of testing switch devices by monitoring via web speedtest and producing a
bandwidth of 50 Mbps.
BAB 2. REFERENCE
Indicated related approved shop drawing & Material for project instalation at Hanggar
5
Doc. No.
CABLE FIBER OPTIC INSTALATIONS BAP-EL-HNG-WMS-0003
Revision: 00 Doc. Status:
Contract No:
6
Doc. No.
CABLE FIBER OPTIC INSTALATIONS BAP-EL-HNG-WMS-0003
Revision: 00 Doc. Status:
Contract No:
BAB 4. RESOURCE
7
Doc. No.
CABLE FIBER OPTIC INSTALATIONS BAP-EL-HNG-WMS-0003
Revision: 00 Doc. Status:
Contract No:
1. Manpower
a. ICT Engineer
b. ICT Supervisor
c. HSE Officer
d. Labours
2. Equipment
a. Excavator
b. Hoe
d. MEASUREMENT TOOLS
g. Tang
h. Screwdriver (+/-)
j. Rope
k. Carpentry tools
3. Material
b. HDPE pipe
c. Insulation
d. Pipe clamp
e. Flexibelt
g. Joint Closure
Contract No:
BAB 5. PREPARATION
9
Doc. No.
CABLE FIBER OPTIC INSTALATIONS BAP-EL-HNG-WMS-0003
Revision: 00 Doc. Status:
Contract No:
Check the drawings for the floor to be worked on.Make sure it is already
approved. Lighting approval material will submitted to Project Management &
Construction Management .After we get an approval, we wil lrelease PO to
supplier & estimate delivery schedule. Preparation of ground rod,cable,clamp,
isolator,and work tools needed,quantities and sizes in accordance with the RKS.
In the installation of the Fiber optic work, coordination is carried out with
structural works due to the penetration of concrete floor sandwalls.
C. The fiber optic cable used for the ICT Hangar installation uses a single
mode cable with 24 cores and is a type that has good insulation,
making it easier to install and repair installation into the installation
pipe (HDPE).
D. Installation Pipe
All fiber optic installations are inserted into HDPE pipes (Sub duct)
with a diameter of 32 mm or 40 mm with a standard pipe thickness of
PN 10 so that the conductors are safe from mechanical impact,
besides that the conductors will be isolated and easy to maintain if
damage occurs during repairs.
10
Doc. No.
CABLE FIBER OPTIC INSTALATIONS BAP-EL-HNG-WMS-0003
Revision: 00 Doc. Status:
Contract No:
- The first cable installation is carried out namely fiber optic cable
from the existing location to ODP location. Type of fiber optic cable
used namely single mode 24 cores. The length of the cable drawn
according to shop drawings. The length of the cable cannot be less
because can cause the signal not to reach the user.
- Jointing the FO cable with the existing process is carried out after
the fiber optic cable installation is complete. This jointing process
is carried out between the fiber optic cable from the existing fiber
optic cable in the direction of the ODP hangar. Jointing is carried
out in the position of the existing fiber optic cable using a joint
closure and then closed using a control box. The fiber optic cable
used has a capacity of 24 cores. The existing fiber optic cable has
a capacity of 6 cores.
11
Doc. No.
CABLE FIBER OPTIC INSTALATIONS BAP-EL-HNG-WMS-0003
Revision: 00 Doc. Status:
Contract No:
- Jointing fiber optic cable with pigtail The next process is jointing
the fiber optic cable which has been successfully pulled into the
room server (indoor) with pigtail on ODP device. Jointing process
adjust the number of cores on the Fiber optic cable used.
Testing fiber optic installations using an Optical Power Meter (OPM). Optical Power
Meter (OPM) is an important equipment for power measurement in fiber optic
communication systems. The way OPM works in carrying out attenuation
calculations is:
1. Turn on the OPM by pressing the power button.
2. Install the two connectors on the TX adapter on the OLT or other optical
device and the adapter on the OPM.
3. Adjust the wavelength in the OPM printed on the OLT by pressing the
button with the lambda symbol, until the value is the same.
4. So from the OPM displa y you can know the power received by the OPM
12
Doc. No.
CABLE FIBER OPTIC INSTALLATIONS BAP-EL-HNG-WMS-0003
Revision: 00 Doc. Status:
Contract No:
13
Doc. No.
CABLE FIBER OPTIC INSTALLATIONS BAP-EL-HNG-WMS-0003
Revision: 00 Doc. Status:
Contract No:
14
Doc. No.
CABLE FIBER OPTIC INSTALLATIONS BAP-EL-HNG-WMS-0003
Revision: 00 Doc. Status:
Contract No:
1. Conduct HSE Induction for all new employees and provide ID card also
relevant.
2. Use the mandatory and standart of PPE, there are helmets, safety glasses,
masks, vests, and safety.
3. Use the additional of PPE, there are face shield, full body harness, and rubber
gloves.
4. Ensure all power tool to be used has been inspected by HSE and Mechanical
personnel.
5. Ensure that the scaffolding to be used has been checked and inspected by a
certified scaffolding expert.
6. Ensure the Driving Licence are appropriate and still valid for vehicle (pick up),
truck mixer, dump truck and water tank.
7. Create Job Safety Analysis (JSA) of site office consultant and work permit.
8. Conducting HSE Morning Talk and Toolbox Meeting before starting work.
12. There are signs for evacuate directions, muster point and provide the
first aid bag equipment at the work site.
Approved by,
Kediri,
Prepared by,
Abdul Rohman 15
Manager Of HSE Wewen Juni Putra
Project manager