PÖYRY ENERGY AG
CONSORTIUM
AL - ARRAB CONTRACTING COMPANY LTD
SEPCOIII ELECTRIC POWER CONSTRUCTION CORPORATION
PROJECT: TITLE:
31002
LOCATION:
Commissioning Manuals
East Coast
PACKAGE:
Compilation of Electrical Commissioning Instructions
“P” Power Plant
SCALE: DOCUMENT No.: REV:
None 10 - B _ _ - EDC - 1 0 0 0 0 3 - 11 AA
CONTENTS
CONSORTIUM
AL - ARRAB CONTRACTING COMPANY LTD
SEPCOIII ELECTRIC POWER CONSTRUCTION CORPORATION
Inbetriebsetzungs-Anweisung Seitenzahl: 1 of 10
No. of Pages
Commissioning Instruction
Table of Contents
1 Task
2 Preconditions
3 Precautions
4 Scope
5 Execution
6 Documentation/Evaluation
7 Appendices
1. Task
In order to prove the integrity of the overall protection system in live operation it is
necessary to carry out primary tests with the running machine. Stability of differential
protection functions can only be verified by primary tests. Activation of the individual
protection functions during primary tests is in general not required for digital protection
systems.
*) Nicht zutreffendes
streichen Erstellt Erstellt/Geprüft*) Geprüft/Freigeg.*) Geprüft/Freigeg.*)
*) Delete as appropriate Prepared by Prepared/Verified by Verified/Released by Verified/Released by
Dienststelle
Department
Name
Name
Datum
Date
Unterschrift
Signature
Geändert: Geprüft/Freigegeben:
modified by: Reviewed/released by:
Verteiler:
Copies to
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Fossil Power Generation Offenders will be held liable for payment of damages. All rights created by patent grant or
Energy Solutions registration of a utility model or design patent are reserved.
Inbetriebsetzungs-Anweisung: Seite: 2 of 10
Commissioning Instruction Page
2. Preconditions
2.2 Documentation
2.3 Personnel
· 1 Multimeter (A;V;Ohms)
· 3 Voltmeters
· 3 fuseless Ammeters
· Adjustable Resistor of approx. 10kOhm, 10W
3. Precautions
· Inspect all barriers (operational and additional)
. Relevant isolations must be established
· Install equipment to allow emergency de-excitation from the protection cabinet
· Energised current transformers may not be open circuited on their secondary side
· Implemented simulations have to be checked regarding their validity and their
influence on the required test conditions prior to performing this test.
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Fossil Power Generation Offenders will be held liable for payment of damages. All rights created by patent grant or CI-B-702.1Main Unit Protection Primary
Energy Solutions registration of a utility model or design patent are reserved. Test Procedure.doc
Inbetriebsetzungs-Anweisung: Seite: 3 of 10
Commissioning Instruction Page
4. Scope
· Short circuit tests
· Earth fault tests
· Voltage tests
· Excitation tests (not part of this CI)
· Additional Voltage tests
· Synchronizing tests (not part of this CI)
· Load tests (after synchronisation)
· Evaluation of results.
5. Execution
· Where not otherwise expressly specified, the tests are performed using the original
settings of the protection relays.
· Communication between protection cabinet and excitation cabinet installed (via head
phone set)
· Communication between protection cabinet and HV substation installed (if applicable)
· Communication between protection cabinet and CCR installed
· Emergency push button for de-excitation at CHA - cabinet installed on spare trip
channel
· Temporary settings applied where necessary
· MV supplies established via BAT and BBT transformers.
. Record all results (checklists –if available- and/or print-out of protection test device).
· The protection relay setting study of the engineering department shall be regarded
during the tests.
· The protection relay manuals shall be regarded
If the stability of the Generator differential protection has been verified during SFC tests, a
three phase short circuit test at the generator terminals is not required
If the stability of the Generator differential protection could not yet be verified, the test
described under 5.2.1 is advisable. If a three phase short circuit test is not reasonably
practical, the stability of the generator differential protection may be tested on load as
described under 5.8.
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Fossil Power Generation Offenders will be held liable for payment of damages. All rights created by patent grant or CI-B-702.1Main Unit Protection Primary
Energy Solutions registration of a utility model or design patent are reserved. Test Procedure.doc
Inbetriebsetzungs-Anweisung: Seite: 4 of 10
Commissioning Instruction Page
增加励磁发电机的额定电· Increase excitation to 10% generator rated current; the protection relay should not
流的10%;继电保护不应 pick up. Record the values of differential and stabilising currents shown by the
该接。记录的微分值和稳 protection relay.
定的保护继电器的电流。
· Check indication of currents in all connected devices
增加励磁发电机的额定电流
为30%;继电保护不应该动
· Increase the excitation to 30% generator rated current; the protection relay should not
pick up. Record the values of differential and stabilising currents shown by the
作。记录的微分值和稳定的 protection relay.
保护继电器的电流。
· De-excite the generator.
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Fossil Power Generation Offenders will be held liable for payment of damages. All rights created by patent grant or CI-B-702.1Main Unit Protection Primary
Energy Solutions registration of a utility model or design patent are reserved. Test Procedure.doc
Inbetriebsetzungs-Anweisung: Seite: 5 of 10
Commissioning Instruction Page
· Install a single phase earth fault (L1-E) at *BAA01GS081 (i.e. by closing one phase
only) or by other suitable means
Note: The earth fault connection must be able to withstand the expected earth fault
current which is to be determined before commencing the test.
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Fossil Power Generation Offenders will be held liable for payment of damages. All rights created by patent grant or CI-B-702.1Main Unit Protection Primary
Energy Solutions registration of a utility model or design patent are reserved. Test Procedure.doc
Inbetriebsetzungs-Anweisung: Seite: 6 of 10
Commissioning Instruction Page
Preparations
Check of VT circuits
· Block relay
· An earth fault is simulated via a resistor of approximately 90% of the trip
resistance.The resistor is placed in machines with excitation via slip rings between
one slip ring and earth.
· Excite Generator to the rated voltage
· Check the operational measured value Rearth and the pickup indication· („REF 1-
3Hz Fault“) and, after T-TRIP-RE<< (10 s on delivery) has expired, check the trip
indication („REF 1-3Hz Trip“).
· Set the resistance to approx. 90 % of the warning stage (RE< WARN).read out the
operational measured value „Re =“, and check the warning message („REF 1-3Hz
Warn“). If there is heavy interference from the excitation system, it may be necessary
to reduce the resistance set for the warning threshold.
· Remove the earthing resistor and check the operational measured values as well as
the measuring circuit supervision „REF 1-3Hz open“ under fault-free conditions. If
spontaneous indications are issued by the measuring circuit monitoring, reduce the
pickup value (Qc <) or deactivate the monitoring.
· For generators with excitation via slip rings, repeat test on the other slip ring.
· Deexcite generator.
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Fossil Power Generation Offenders will be held liable for payment of damages. All rights created by patent grant or CI-B-702.1Main Unit Protection Primary
Energy Solutions registration of a utility model or design patent are reserved. Test Procedure.doc
Inbetriebsetzungs-Anweisung: Seite: 7 of 10
Commissioning Instruction Page
· On completion of the voltage test runs the voltage regulator can be released for
· optimisation in ”MANUAL” and „AUTOMATIC“ mode in accordance to
· Commissioning Instruction CI-B-703 (Excitation and Automatic Voltage Regulator
(AVR)Test Procedure).
Overvoltage protection
Overexcitation protection
Frequency protection
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Fossil Power Generation Offenders will be held liable for payment of damages. All rights created by patent grant or CI-B-702.1Main Unit Protection Primary
Energy Solutions registration of a utility model or design patent are reserved. Test Procedure.doc
Inbetriebsetzungs-Anweisung: Seite: 8 of 10
Commissioning Instruction Page
· On-load measurements straight after first synchronisation of the unit will prove the
stability of the differential protection.
· Therefore, co-ordinate with the GT commissioning engineer the load jump after first
synchronisation. Ensure the load level after first synchronisation is below the trip
value of the differential protection.
· Ensure generator current is sufficient to prove stability and correct function.
· Measure and record voltage, load, earth and stabilising currents for the relevant
protection relays.
· Increase excitation to 10% generator rated current; the protection relay should not
pick up.
· Check indication of currents in the protection device
· Check indication of currents in Generator Transformer differential protection device
· Increase the excitation to 30% generator rated current; the protection relay should not
pick up.
· Record the values of differential and stabilising currents shown by the protection
relay.
· Normalise all temporary settings (if applied)
· On-load measurements straight after first synchronisation of the unit will prove the
stability of the differential protection.
· Ensure generator current is sufficient to prove stability and correct function.
· Measure and record voltage, load, earth and stabilising currents for the relevant
protection relays.
Underexcitation protection
· Verify correct measurement and polarity of active and reactive power by comparing
the measured values of the I&C System and the protection relay.
· By reducing the generator voltage or operation of the generator transformer OLTC
check underexcitation limiter in excitation, no protection alarm should occur
· Pick up of protection function is not required if secondary testing has been completed
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Fossil Power Generation Offenders will be held liable for payment of damages. All rights created by patent grant or CI-B-702.1Main Unit Protection Primary
Energy Solutions registration of a utility model or design patent are reserved. Test Procedure.doc
Inbetriebsetzungs-Anweisung: Seite: 9 of 10
Commissioning Instruction Page
Out-of-step protection
· Check direction on load by recording active load, reactive load and impedance
· Record load point in R/X diagram
· Confirm during generator operation that the measured power is positive and plausible
· Adjust reactive power to approx. Q= 0MVA
· Block reverse power protection (both relays in case of redundant protection)
· Close the control valve fully by reducing the setpoint of the turbine controller;
determine smallest value of reverse power
Caution!
Operating the turbine without a minimum steam throughput (cooling effect) can cause
the turbine blades to overheat!
Input of reverse power is admissible with a turboset only for a short period.
The test must be coordinated with the responsible turbine engineer
Impedance protection
· Carry out a direction check on load with minimum 30% relay current
· Record measured resistance and reactance
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Fossil Power Generation Offenders will be held liable for payment of damages. All rights created by patent grant or CI-B-702.1Main Unit Protection Primary
Energy Solutions registration of a utility model or design patent are reserved. Test Procedure.doc
Inbetriebsetzungs-Anweisung: Seite: 10 of 10
Commissioning Instruction Page
· Record the stator earth current and earth resistance values on load
· Record the Negative Sequence Current I2 during load operation with minimum 50% of
rated current
· Calculate the unbalanced load I2/In extrapolated to In The unbalanced load should be
negligable (<5%)
Overcurrent protection
· Record phase currents and temperature of cooling medium during full load operation
· Check for sufficient margin to trip value
6. Documentation/Evaluation
6.1 Documentation
· Refer to commissioning checklists.
6.2 Evaluation
· Compare measured results with protection relay setting study of engineering
department.
· Where necessary, amend settings after confirmation of engineering department.
· Where applicable, prepare/print off graphs and/or calculate values to support the
evaluation.
· Refer to relay manual.
7. Appendices
· None
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Fossil Power Generation Offenders will be held liable for payment of damages. All rights created by patent grant or CI-B-702.1Main Unit Protection Primary
Energy Solutions registration of a utility model or design patent are reserved. Test Procedure.doc
Inbetriebsetzungs-Anweisung Seitenzahl: 1 of 6
Commissioning Instruction No. of Pages
STANDARD
Table of Contents
1 Task
2 Preconditions
3 Precautions
4 Scope
5 Execution
6 Documentation
7 Appendices
1. Task
Commissioning of black start diesel generator unit itself and black start diesel generator
unit in an overall plant configuration.
*) Nicht zutreffendes
streichen Erstellt Erstellt/Geprüft*) Geprüft/Freigeg.*) Geprüft/Freigeg.*)
*) Delete as appropriate Prepared by Prepared/Verified by Verified/Released by Verified/Released by
Dienststelle
Department
Name
Name
Datum
Date
Unterschrift
Signature
Geändert: Geprüft/Freigegeben:
modified by: Reviewed/released by:
Verteiler:
Copies to
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Fossil Power Generation Offenders will be held liable for payment of damages. All rights created by patent grant or
registration of a utility model or design patent are reserved.
Energy Solutions
Inbetriebsetzungs-Anweisung: Seite: 2 of 6
Commissioning Instruction Page
STANDARD
2. Preconditions
NOTE: For the black start diesel generator function more than one diesel
generator is required (check overall SLD).
2.2 Documentation
- Circuit diagrams of black start diesel generator set.
- Logic diagram of diesel generator control.
- Product manuals of all affected equipment.
- Circuit diagrams of related switchgears.
- Commissioning checklists of related equipment/cables.
- Workshop test certificates/results.
- Settings for control and protection devices (manufacturer instruction/engineering
department).
2.3 Personnel
- 1 Commissioning engineer: qualified electrical engineer with experience in
commissioning of generator sets.
- 1 Helper: skilled worker who has received suitable training.
3. Precautions
- Observe standards for "Erection and operation of power installations".
- Before operating a synchronizing CB a local inspection shall be done.
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Fossil Power Generation Offenders will be held liable for payment of damages. All rights created by patent grant or
registration of a utility model or design patent are reserved.
Energy Solutions
Inbetriebsetzungs-Anweisung: Seite: 3 of 6
Commissioning Instruction Page
STANDARD
4. Scope
- Visual checks
- BSDGS tests
- Control centre
- Generator / Generator circuit breaker
- Cables
- Interface
- Sensors
- CT circuits
- Interlock
- Check of electrical protection circuits
- Synchronising equipment
- Initial start up
- Load tests / operation modes
5. Execution
NOTE: Since the BSDGS is a pre-assembled and tested component, workshop tests will
not be repeated on site. A list with workshop tests is available in the product
manual. IT IS MANDATORY TO OBSEREVE THE MANUFACTURER
INSTRUCTION.
NOTE:
Diesel engine supervisor shall be called to site when the tests have 5.1, 5.2.1 to
5.2.10 (including) have been performed successfully. Inform engineering department
of the anticipated date when above works are completed.
Tests 5.2.11 to 5.2.12.c) shall be performed in cooperation with the diesel engine
supervisor.
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Fossil Power Generation Offenders will be held liable for payment of damages. All rights created by patent grant or
registration of a utility model or design patent are reserved.
Energy Solutions
Inbetriebsetzungs-Anweisung: Seite: 4 of 6
Commissioning Instruction Page
STANDARD
5.2.2 Generator
An insulation test for the stator and rotor windings of the generator shall be done, if no
manufacturer test certificate is available.
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Fossil Power Generation Offenders will be held liable for payment of damages. All rights created by patent grant or
registration of a utility model or design patent are reserved.
Energy Solutions
Inbetriebsetzungs-Anweisung: Seite: 5 of 6
Commissioning Instruction Page
STANDARD
After test of the CT circuits (5.2.7), inject a current on the primary side of each CT (phase
and star point side) with sufficient magnitude to be indicated on the protection relay. Verify
correct indication.
In order to check the entire trip circuit from the BSDGS to the relevant circuit breaker,
initiate trip commands on the protection relay of the EDGS. Verify correct opening of
BSDGS generator circuit breaker.
Check of emergency stop of the diesel generator engine.
NOTE: Only one generator shall be operated when synchronized with the grid!
b) Raise load set point to full load and verify again relays read/indicate currents/voltage
correctly. Record results (checklists).
c) Reduce load set point until BSDGS trips via reverse power. Record results
(checklists).
d) Automatic start of BSDGS with parallel operation (loading and unloading; trip the
BSDGS by one electrical protection function). Record results (chart recorder ->
BSDGS voltage, current and speed). Optimise settings where/if required. Consult
electrical engineering department where/if required. Observe BSDGS sensor
indication (i.e. temperature rise).
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Fossil Power Generation Offenders will be held liable for payment of damages. All rights created by patent grant or
registration of a utility model or design patent are reserved.
Energy Solutions
Inbetriebsetzungs-Anweisung: Seite: 6 of 6
Commissioning Instruction Page
STANDARD
g) With the BSDGS units supplying the MV switchgear only, start and stop the drive or
drive group with the highest kW rating in emergency operation for verification of
Record results (chart recorder -> BSDGS voltage, current and speed). Optimise
settings where/if required. Consult electrical engineering department where/if
required.
6. Documentation
- Commissioning Procedures
- Checklists
- Charts
- List of final settings
7. Appendices
- None -
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Fossil Power Generation Offenders will be held liable for payment of damages. All rights created by patent grant or
registration of a utility model or design patent are reserved.
Energy Solutions
Inbetriebsetzungs-Anweisung Seitenzahl: 1 of 4
Commissioning Instruction No. of Pages
STANDARD
Table of Contents
1 Task
2 Preconditions
3 Precautions
4 Scope
5 Execution
6 Documentation
7 Appendices
1. Task
The measuring circuits for protection, synchronisation, closed-loop control and operational
instrumentation are to be tested.
*) Nicht zutreffendes
streichen Erstellt Erstellt/Geprüft*) Geprüft/Freigeg.*) Geprüft/Freigeg.*)
*) Delete as appropriate Prepared by Prepared/Verified by Verified/Released by Verified/Released by
Dienststelle
Department
Name
Name
Datum
Date
Unterschrift
Signature
Geändert: Geprüft/Freigegeben:
modified by: Reviewed/released by:
Verteiler:
Copies to
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Fossil Power Generation Offenders will be held liable for payment of damages. All rights created by patent grant or
Energy Solutions registration of a utility model or design patent are reserved.
Inbetriebsetzungs-Anweisung: Seite: 2 of 4
Commissioning Instruction Page
STANDARD
2. Preconditions
2.2 Documentation
· The circuit diagrams of the electrical equipment cabinets are available
· Commissioning checklists CL-E21 and CL-E22
2.3 Personnel
· 1 Commissioning engineer: Engineer or technician with experience in commissioning
of types of the electrical equipment systems employed in the plant.
· 1 Helper: skilled worker with adequate on-the-job training.
3. Precautions
· Observe the rules for handling electronic components sensitive to electrostatic
discharge (ESD measures).
· The VDE Regulations for ”Erection and Operation of Electrical Power Installations”
are to be observed (VDE 0100/0101/0105).
· Special safety arrangements shall be made for all areas which are not explicitly
designated as ”electrical operating areas” when performing tests at voltages in
excess of 50 V.
4. Scope
· Testing of the plant side cable connections,
· Checking that the mounting position is correct,
· Checking of the phase and core assignment,
· Checking of correct earthing,
· Checking of the function.
5. Execution
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Fossil Power Generation Offenders will be held liable for payment of damages. All rights created by patent grant or
Energy Solutions registration of a utility model or design patent are reserved.
Inbetriebsetzungs-Anweisung: Seite: 3 of 4
Commissioning Instruction Page
STANDARD
assignment
· Inspection for cleanliness of voltage transformers, high voltage connections and
associated cable connections
· Inspection of isolators, support structures and earthing connections
· Injection of a primary current and measuring of the secondary current in each winding
Record the values in CL-E22 and verify the CT ratio.
· Meeting of both requirements is verified by opening the earthing link and checking
the isolation of the circuit to earth (by Ohmmeter, Megger or voltage source)
Subsequently the earth connection is to be restored.
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Fossil Power Generation Offenders will be held liable for payment of damages. All rights created by patent grant or
Energy Solutions registration of a utility model or design patent are reserved.
Inbetriebsetzungs-Anweisung: Seite: 4 of 4
Commissioning Instruction Page
STANDARD
6. Documentation
A check list CL-E21 or CL-E22, as the case may be, is to be completed for each set of
instrumentation transformers. In the case of cascade-type voltage transformers a
separate check list is required for the top element.
7. Appendices
- None -
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Fossil Power Generation Offenders will be held liable for payment of damages. All rights created by patent grant or
Energy Solutions registration of a utility model or design patent are reserved.
Inbetriebsetzungs-Anweisung Seitenzahl: 1 of 3
Commissioning Instruction No. of Pages
STANDARD
Table of Contents
1 Task
2 Preconditions
3 Precautions
4 Scope
5 Execution
6 Documentation
7 Appendices
1. Task
The function of the measuring and metering equipment is to be tested.
Messungv *) Nicht
zutreffendes streichen Erstellt Erstellt/Geprüft*) Geprüft/Freigeg.*) Geprüft/Freigeg.*)
*) Delete as appropriate Prepared by Prepared/Verified by Verified/Released by Verified/Released by
Dienststelle
Department
Name
Name
Datum
Date
Unterschrift
Signature
Geändert: Geprüft/Freigegeben:
modified by: Reviewed/released by:
Verteiler:
Copies to
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Fossil Power Generation Offenders will be held liable for payment of damages. All rights created by patent grant or
registration of a utility model or design patent are reserved.
Energy Solutions
Inbetriebsetzungs-Anweisung: Seite: 2 of 3
Commissioning Instruction Page
STANDARD
2. Preconditions
2.2 Documentation
· The circuit diagrams of the electrical equipment cabinets are available.
· The I&C equipment, the alarm printer and the control console are ready for service.
· The relevant logic diagrams and circuit diagrams are available for the I&C equipment.
. The product manuals are available for the types of equipment employed in the plant
· Commissioning checklist CL-E20
2.3 Personnel
· 1 Commissioning engineer: Engineer or technician with experience in commissioning
of the type of electrical equipment systems employed in the plant.
· 1 Helper: skilled worker with adequate on-the-job training.
3. Precautions
· Observe the rules for handling electronic components sensitive to electrostatic
discharge (ESD measures).
· The VDE Regulations for ”Erection and Operation of Electrical Power Installations” are
to be observed (VDE 0100/0101/0105).
· Special safety arrangements shall be made for all areas which are not explicitly
designated as ”electrical operating areas” when performing tests at voltages in
excess of 50 V
4. Scope
· Checking of the technical data,
· Testing of the functions,
· Testing of the remote indications,
· Testing of the fault alarm signals.
5. Execution
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Fossil Power Generation Offenders will be held liable for payment of damages. All rights created by patent grant or
registration of a utility model or design patent are reserved.
Energy Solutions
Inbetriebsetzungs-Anweisung: Seite: 3 of 3
Commissioning Instruction Page
STANDARD
· Test the output signals of the measuring equipment and the indications at the cabinet,
in the I&C equipment and at the control console.
· Restore the equipment to its original condition.
5.3 Testing of the active and reactive power measuring equipment and meters
· Feed in a three-phase current and a three-phase voltage.
Important: Disconnect the voltage transformer, voltage should not be fed into the primary
circuit of voltage transformers!
· Employ a zero phase angle: The active power meter should be operating and the
reactive power meter should be at a standstill.
· Test the output signals of the measuring equipment and the indications at the cabinet,
in the I&C equipment and at the control console.
· Employ a phase angle of 90°: The active power meter should be at a standstill and the
reactive power meter should be running.
· Test the output signals of the measuring equipment and the indications at the
cabinet, in the I&C equipment and at the control console.
6. Documentation
The activities performed and any modifications made are to be documented in the circuit
documentation.
An individual check list CL-E20 is to be completed for each device.
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Fossil Power Generation Offenders will be held liable for payment of damages. All rights created by patent grant or
registration of a utility model or design patent are reserved.
Energy Solutions
Inbetriebsetzungs-Anweisung: Seite: 4 of 3
Commissioning Instruction Page
STANDARD
7. Appendices
- None -
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Fossil Power Generation Offenders will be held liable for payment of damages. All rights created by patent grant or
registration of a utility model or design patent are reserved.
Energy Solutions
Inbetriebsetzungs-Anweisung Seitenzahl: 1 of 10
Commissioning Instruction No. of Pages
Table of Contents
1 Task
2 Preconditions
3 Precautions
4 Scope
5 Execution
6 Documentation
7 Appendices
1. Task
The purpose of the secondary tests is to ensure the functional integrity and the correct
operation of the protection system according to the design.
*) Nicht zutreffendes
streichen Erstellt Erstellt/Geprüft*) Geprüft/Freigeg.*) Geprüft/Freigeg.*)
*) Delete as appropriate Prepared by Prepared/Verified by Verified/Released by Verified/Released by
Dienststelle
Department
Name
Name
Datum
Date
Unterschrift
Signature
Geändert: Geprüft/Freigegeben:
modified by: Reviewed/released by:
Verteiler:
Copies to
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Offenders will be held liable for payment of damages. All rights created by patent grant or
Fossil Power Generation registration of a utility model or design patent are reserved.
Inbetriebsetzungs-Anweisung: Seite: 2 of10
Commissioning Instruction Page
STANDARD
2. Preconditions
2.2 Documentation
· Circuit documentation of the generator protection equipment.
· Logic diagrams of the relevant fault alarms.
· Product manuals of all relevant protection devices.
· Protection relay setting study of engineering department
2.3 Personnel
· 1 Commissioning engineer: Engineer or technician with experience in commissioning
of the types of protection devices employed in the plant.
· 1 Helper: Technician or skilled worker with adequate on-the-job training.
3. Precautions
· The VDE Regulations for „Erection and Operation of Electrical Power Installations
with rated voltage up to 1000 V“ (VDE 0100/0105) shall be observed.
· The rules for handling electronic components sensitive to electrostatic discharge
(ESD measures) shall be observed.
· Designation and locking of external plant sections, which are used for protection
purposes, must be checked prior to commencing work.
· If applicable, the voltage transformers must be short-circuited and earthed on the
primary side, the secondary-side MCB is to be opened
4. Scope
· Setting and testing of the relays,
· Checking of the interface signals,
· Checking of the tripping channels.
· Current Transformer and Voltage Transformer circuit testing (Not part of this CI)
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Offenders will be held liable for payment of damages. All rights created by patent grant or
Fossil Power Generation registration of a utility model or design patent are reserved.
Inbetriebsetzungs-Anweisung: Seite: 3 of10
Commissioning Instruction Page
STANDARD
5. Execution
NOTE: Some of the protection functions might not be applicable for individual projects.
These deactivated functions will not be tested by secondary injection.
5.1.1 General
· Before commencing the tests the technical data of the relays should be noted as per
the relevant device cover sheet.
· All tests performed are to be documented in the corresponding check lists or by using
print outs of the protection software.
· The tests are to be carried out at the specified settings (if possible).
· Testing is to be carried out in an overlapped manner up to and including the trip
channels; if other commissioning activities are hindered by testing of the tripping
channels, the corresponding tripping channels have to be blocked.
· The relays should be injected at the input terminals of the cabinet, the response
values are to be documented in the corresponding check lists or by using print outs of
the protection software.
· The current circuits can withstand a continuous current of up to 4 x In and the voltage
circuits up to 2 x Un. Unnecessary use of the full overload capability should be
avoided.
· On completion of the tests all simulated signals must be removed and the equipment
must be restored to its original condition.
· Connect the secondary test set to the input terminals of the starpoint current
transformers.
· Inject a test current into phase L1.
· Steadily increase the test current until the relay picks up, document the tripping
current.
· Measure the tripping time for an injected current of In.
· Repeat the procedure for phases L2 and L3 as well as for the three phases of the
generator line-side current transformers.
· Record the results.
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Offenders will be held liable for payment of damages. All rights created by patent grant or
Fossil Power Generation registration of a utility model or design patent are reserved.
Inbetriebsetzungs-Anweisung: Seite: 4 of10
Commissioning Instruction Page
STANDARD
· Connect the secondary test set to the input terminals of the current transformers
· Inject a test current into phase L1.
· Steadily increase the test current until the relay picks up, document the tripping
current.
· Measure the tripping time for an injected current of In.
· Record the results.
· Connect the secondary test set to the input terminals of the HV current transformers.
· Inject a test current into phase L1.
· Steadily increase the test current until the relay responds, document the tripping
current.
· Measure the tripping time for an injected current of In.
· Repeat for all phases and for all sets of current transformers.
· Record the results.
· Connect the secondary test set to the input terminals of the current transformers
· Inject a three phase current with swapped phases (alternatively a single phase test
can be performed )
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Offenders will be held liable for payment of damages. All rights created by patent grant or
Fossil Power Generation registration of a utility model or design patent are reserved.
Inbetriebsetzungs-Anweisung: Seite: 5 of10
Commissioning Instruction Page
STANDARD
Before commencing each test the thermal preloading of the relay must be cancelled
(refer to protection relay manual).
· Inject 2 test currents in the range between the maximum permissible continuous
unbalanced load (I2> warn setting ) and the independent trip stage (I2>> trip setting ).
· Document the measured values and compare to the calculated values; calculation
according to protection relay manual.
· When testing one phase at a time it is necessary to divide the injected current by
three in order to calculate the tripping time.
· Repeat for all phases (single phase test only)
· Record the results.
- Impedance protection
· Connect the three-phase secondary test set to the input terminals for the 3 current
and 3 voltages at the cabinet.
· Without any voltage being applied, steadily increase the test current for phase L1,
noting the value at which the relay picks up. Repeat for the other phases.
- Underexcitation protection
· Test the tripping delay with and without the emergency stop signal. Where necessary,
simulate the emergency stop signal in the protection cabinet.
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Offenders will be held liable for payment of damages. All rights created by patent grant or
Fossil Power Generation registration of a utility model or design patent are reserved.
Inbetriebsetzungs-Anweisung: Seite: 6 of10
Commissioning Instruction Page
STANDARD
DANGER: When the 20Hz generator is energised, voltage on the generator will appear!
The external 20 Hz bias voltage of the stator winding must be isolated before
commencing work on the generator at standstill.
The 100-% stator earth fault protection can be checked with the machine at standstill,
because the measuring principle for the earth resistance calculation is independent of
whether the machine is at standstill, rotating or excited. A prerequisite is, however, that
the 20 Hz generator 7XT33 must be supplied with a DC voltage or an external voltage
source
· Under fault-free conditions (RE infinite) the measured current must be negative due to
the capacitive current. If it is not, the connection at the current input must be rotated.
The phase angle „ φSEF=“ should be about –90° due to the existing stator
capacitances. If it is not, the value to complement it to –90° must be determined and
set as PHI I SEF = –90° – φSEF. For a display value of e.g. „ φSEF =“ –75° PHI I SEF = –
15° is set. This will change the measured value to approx. –90°. The value displayed
for R SEF must be in fault-free condition the maximum possible value of 9999 . The
maximum value for the primary earth resistance R SEFp depends on the selected
conversion.
· A short-circuit (RE = 0 ) is created in the generator starpoint, and the measured fault
resistance (address „R SEF=“) read out from the operational measured values. This
resistance is set at SEF Rps.
· Insert now on the primary side a resistance which corresponds to the tripping value
(e.g. 2 k). Check the measured fault resistance („R SEF=“). If this resistance differs
very much from the value expected, modify SEF Rps accordingly and, if necessary,
make a fine adjustment with the correction angle (PHI I SEF). Read out finally the fault
resistance, and set this value as the tripping threshold at R<< SEF TRIP.
· Next, insert a fault resistance for the alarm stage (e.g. 5k on the primary side, and
read out the fault resistance („R SEF=“) from the operational measured values. This
value is set as R< SEF ALARM.
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Offenders will be held liable for payment of damages. All rights created by patent grant or
Fossil Power Generation registration of a utility model or design patent are reserved.
Inbetriebsetzungs-Anweisung: Seite: 7 of10
Commissioning Instruction Page
STANDARD
· Switch off the voltage supply for the 20 Hz generator, or block the binary input. The
indication „SEF100 Failure“ will appear. This ensures that a failure of the 20 Hz
generator is reliably detected. If this indication occurs already with the 20 Hz generator
in operation, the monitoring threshold should be reduced. This can be the case if the
loading resistances are very small (< 1 ).
· Now the earth resistance is reduced to about 90 % of the resistance for the alarm
stage. After the delay time T SEF ALARM (10.00 s on delivery), the stator earth fault
protection issues an alarm.
· Further reduce the earth resistance to 90 % of what the trip stage pickup value would
be for the protection device. The protection issues a pickup indication and after T SEF
TRIP a trip indication.
· Unblock Relay
· Apply a 100 V AC auxiliary voltage to the input to the square wave generator located in
the panel.
· Apply a dead earth fault between one slip ring and earth. The device now measures as
earth impedance only the reactance of the coupling unit and the brush resistance (as
the case may be in series with a protection resistor for the coupling capacitors and a
current-limiting resistor with inductive/capacitive coupling). These values can be read
out with the phase angle of this complex resistance under the earth fault measured
values:
· Rtot = x.xx k
· Xtot = y.yy k
· φZtot = z.z °
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Offenders will be held liable for payment of damages. All rights created by patent grant or
Fossil Power Generation registration of a utility model or design patent are reserved.
Inbetriebsetzungs-Anweisung: Seite: 8 of10
Commissioning Instruction Page
STANDARD
· Rtot corresponds to the series resistance (brushes plus protection and limiting resistor)
and Xtot to the coupling reactance. If both for Rtot as well as for Xtot values are
indicated as 0, then the connections of URE or IRE have wrong polarity. Change the
polarity of one of the connections and repeat the measurement.
· Now using a resistor of the size of the warning resistance (RE< WARN,) an earth fault
is simulated as above. The earth resistance calculated by the unit can be read out
under the Operational Measured Values as Rearth. If substantial deviation occurs
between the actual and the indicated earth resistances, the matching improvement can
be attempted by correcting the preset angle error for IRE PHI I RE. This angle error
correction is only effective for the rotor earth fault protection function. An earth fault is
now simulated as above using a resistor approximately 90% of the trip resistance
(RE<< TRIP). The rotor earth fault protection initiates a pickup signal and after T-TRIP-
RE<< a trip indication.
- Overvoltage protection
- Overexcitation protection
- Frequency protection
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Offenders will be held liable for payment of damages. All rights created by patent grant or
Fossil Power Generation registration of a utility model or design patent are reserved.
Inbetriebsetzungs-Anweisung: Seite: 9 of10
Commissioning Instruction Page
STANDARD
· Connect a DC current source (max. 10A) to the input terminals of the earth measuring
circuit.
· Insert an ammeter in the measuring circuit.
· Inject a test current until the relay picks up.
· Measure the voltage across the measuring shunt.
· Measure the voltage at the input to the protection relay.
· Repeat the measurements with the polarity of the test current reversed.
· Record the results.
- Inadvertent energisation
- Out-of-step protection
· Connect the three-phase secondary test set to the input terminals for the 3 current
and 3 voltages at the cabinet.
· Adjust the voltages symmetrically to the level of the rated voltage, currents
o
symmetrically to 2 x In. The angle between currents and voltages: Φp = 0 .
· Slowly reduce the voltages symmetrically down to 0 V. Reverse polarity of
Voltages by adding 180° to the phase angle. Then increase voltages again. This
simulates one passing through the power swing polygon (characteristic 1) of the out-
of-step protection. When the polygon is left, pick-up of the out-of-step
protection occurs:
- Annunciation “O/S char. 1”.
- Annunciation “O/S det.ch. 1” .
· If one out-of-step cycle has been set for n1, trip will occur:
- Annunciation “O/S Trip ch.1” .
- Trip relay.
· If more than one out-of-step cycle has been parameterized, the procedure must
be followed as often until trip occurs.
o o o
· Repeat test for different phase angles (Φp = 30 ,60 ,90 )
· Record the results in Commissioning Checklist and R/X diagram
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Offenders will be held liable for payment of damages. All rights created by patent grant or
Fossil Power Generation registration of a utility model or design patent are reserved.
Inbetriebsetzungs-Anweisung: Seite: 10 of10
Commissioning Instruction Page
STANDARD
- Undervoltage protection
6. Documentation
The corresponding check lists are to be filled in for each relay and also for the entire
protection system.
7. Appendices
None.
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Offenders will be held liable for payment of damages. All rights created by patent grant or
Fossil Power Generation registration of a utility model or design patent are reserved.
Inbetriebsetzungs-Anweisung Seitenzahl: 1 of 6
Commissioning Instruction No. of Pages
STANDARD
Table of Contents
1 Task
2 Preconditions
3 Precautions
4 Scope
5 Execution
6 Documentation
7 Appendices
1. Task
Commissioning of EDGS unit itself and EDGS unit in an overall plant configuration.
*) Nicht zutreffendes
streichen Erstellt Erstellt/Geprüft*) Geprüft/Freigeg.*) Geprüft/Freigeg.*)
*) Delete as appropriate Prepared by Prepared/Verified by Verified/Released by Verified/Released by
Dienststelle
Department
Name
Name
Datum
Date
Unterschrift
Signature
Geändert: Geprüft/Freigegeben:
modified by: Reviewed/released by:
Verteiler:
Copies to
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Fossil Power Generation Offenders will be held liable for payment of damages. All rights created by patent grant or
Energy Solutions registration of a utility model or design patent are reserved.
Inbetriebsetzungs-Anweisung: Seite: 2 of 6
Commissioning Instruction Page
STANDARD
2. Preconditions
2.2 Documentation
- Circuit diagrams of emergency diesel generator set.
- Logic diagram of emergency diesel generator control.
- Product manuals of all affected equipment.
- Circuit diagrams of related switchgears.
- Commissioning checklists of related equipment/cables.
- Workshop test certificates/results.
- Settings for control and protection devices (manufacturer instruction/engineering
department).
2.3 Personnel
- 1 Commissioning engineer: qualified electrical engineer with experience in
commissioning of generator sets.
- 1 Helper: skilled worker who has received suitable training.
3. Precautions
- Observe standards for "Erection and operation of power installations" (VDE
0100/101/105 and IEC 364 respectively).
- Before operating a synchronizing CB a local inspection shall be done.
4. Scope
- Visual checks
- EDGS tests
- Control centre
- Generator/Generator circuit breaker
- Cables
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Fossil Power Generation Offenders will be held liable for payment of damages. All rights created by patent grant or
Energy Solutions registration of a utility model or design patent are reserved.
Inbetriebsetzungs-Anweisung: Seite: 3 of 6
Commissioning Instruction Page
STANDARD
- Interface
- Sensors
- CT circuits
- Interlock
- Check of electrical protection circuits
- Synchronising equipment
- Initial start up
- Load tests/operation modes
5. Execution
NOTE: Since the EDGS is a pre-assembled and tested component, workshop tests will
not be repeated on site. A list with workshop tests is available in the product manual.
IT IS MANDATORY TO OBSEREVE THE MANUFACTURER INSTRUCTION.
NOTE:
Diesel engine supervisor shall be called to site when the tests have 5.1, 5.2.1 to
5.2.10 (including) have been performed successfully. Inform engineering
department of the anticipated date when above works are completed.
Tests 5.2.11 to 5.2.12.c) shall be performed in cooperation with the diesel engine
supervisor.
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Fossil Power Generation Offenders will be held liable for payment of damages. All rights created by patent grant or
Energy Solutions registration of a utility model or design patent are reserved.
Inbetriebsetzungs-Anweisung: Seite: 4 of 6
Commissioning Instruction Page
STANDARD
5.2.2 Generator
An insulation test for the stator and rotor windings of the generator shall be done, if no
manufacturer test certificate is available.
5.25 Commissioning of signal interface to I&C and commands from and to EDGS
control centre
The signal interface to the I&C system shall be tested according to the relevant
drawings/logic diagrams.
All commands from and all feedbacks to the EDGS control centre shall be checked (test
position of circuit breakers).
After test of the CT circuits (5.2.7), inject a current on the primary side of each CT (phase
and star point side) with sufficient magnitude to be indicated on the protection relay. Verify
correct indication.
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Fossil Power Generation Offenders will be held liable for payment of damages. All rights created by patent grant or
Energy Solutions registration of a utility model or design patent are reserved.
Inbetriebsetzungs-Anweisung: Seite: 5 of 6
Commissioning Instruction Page
STANDARD
In order to check the entire trip circuit from the EDGS to the relevant circuit breaker,
initiate trip commands on the protection relay of the EDGS. Verify correct opening of
EDGS generator circuit breaker.
Check of emergency stop of the diesel generator engine.
Excite the generator and check for correct phase sequence and voltage level. Local and
remote indications to be checked.
b) Raise load set point to full load and verify again relays read/indicate currents/voltage
correctly. Record results (checklists).
c) Reduce load set point until EDGS trips via reverse power. Record results (checklists).
d) Automatic start of EDGS with parallel operation (loading and unloading; trip the EDGS
by one electrical protection function). Record results (chart recorder -> EDGS voltage,
current and speed). Optimise settings where/if required. Consult electrical engineering
department where/if required. Observe EDGS sensor indication (i.e. temperature rise).
e) Start up EDGS. With the EDGS supplying the emergency switchgear only, start and
stop the drive or drive group with the highest kW rating in emergency operation for
verification of
• speed controller (check behaviour and compare with under-/overfrequency
detection settings)
• differential protection setting (in-rush detection and stabilising function)
• voltage controller (check behaviour and compare with under-/overvoltage
detection settings on protection relay and switchgear)
Record results (chart recorder -> EDGS voltage, current and speed). Optimise settings
where/if required. Consult electrical engineering department where/if required.
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Fossil Power Generation Offenders will be held liable for payment of damages. All rights created by patent grant or
Energy Solutions registration of a utility model or design patent are reserved.
Inbetriebsetzungs-Anweisung: Seite: 6 of 6
Commissioning Instruction Page
STANDARD
f) Perform mains failure function test to verify that the EDGS and the EDGS automatic
programme is functioning according to design. Verify that the emergency busbar voltage
is not less than rated voltage (e.g. 400V). Record results (chart recorder -> EDGS voltage,
current and speed). Optimise settings where/if required. Consult electrical engineering
department where/if required.
6. Documentation
- Commissioning Programme
- Checklists
- Charts
- List of final settings
7. Appendices
- None -
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Fossil Power Generation Offenders will be held liable for payment of damages. All rights created by patent grant or
Energy Solutions registration of a utility model or design patent are reserved.
Inbetriebsetzungs-Anweisung Seitenzahl: 1 of 3
Commissioning Instruction No. of Pages
STANDARD
Table of Contents
1 Task
2 Preconditions
3 Precautions
4 Scope
5 Execution
6 Documentation
7 Appendices
1. Task
These instructions comprise a description of the test to be carried out on commissioning
of the dry-type low-voltage transformers (GEAFOL transformers).
*) Nicht zutreffendes
streichen Erstellt Erstellt/Geprüft*) Geprüft/Freigeg.*) Geprüft/Freigeg.*)
*) Delete as appropriate Prepared by Prepared/Verified by Verified/Released by Verified/Released by
Dienststelle
Department
Name
Name
Datum
Date
Unterschrift
Signature
Geändert: Geprüft/Freigegeben:
modified by: Reviewed/released by:
Verteiler:
Copies to
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Fossil Power Generation Offenders will be held liable for payment of damages. All rights created by patent grant or
Energy Solutions registration of a utility model or design patent are reserved.
Inbetriebsetzungs-Anweisung: Seite: 2 of 3
Commissioning Instruction Page
STANDARD
2. Preconditions
2.2 Documentation
· Protection grading diagram (short-circuit calculations),
· Product manual of the transformer,
· Circuit diagrams and layout drawings of the corresponding switchgear.
· Commissioning checklist CL-E06.7
2.3 Personnel
· 1 Commissioning engineer: engineer or technician with experience in commissioning
of low-voltage transformers and authorised to carry out switching in medium-voltage
and low-voltage switchgears.
· 1 Helper: skilled worker with adequate on-the-job training.
3. Precautions
· The safety regulations for working at electrical installations shall be observed.
· Before testing voltages are applied a check shall be carried out to ensure that
no unauthorised persons are working at the corresponding loads
(where necessary barriers should be provided)
4. Scope
· Visual inspection
· Insulation resistance test
· Functional test
· Initial switching-on
5. Execution
The following instructions are valid generally. There may be deviations in detail depending
on the type of transformer employed.
Only those points relevant to dry-type transformers in the check list CL-E06.7 should be
carried out.
Note: Refer to manufacturer instruction.
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Fossil Power Generation Offenders will be held liable for payment of damages. All rights created by patent grant or
Energy Solutions registration of a utility model or design patent are reserved.
Inbetriebsetzungs-Anweisung: Seite: 3 of 3
Commissioning Instruction Page
STANDARD
6. Documentation
The results of the individual tests and the data and measured values are to be
documented in the commissioning check list CL-E06.7.
Where appropriate, a list of activities performed, which are not listed in the check list, shall
be appended.
If applicable, corrections and amendments shall be entered in the circuit diagrams and the
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Fossil Power Generation Offenders will be held liable for payment of damages. All rights created by patent grant or
Energy Solutions registration of a utility model or design patent are reserved.
Inbetriebsetzungs-Anweisung: Seite: 4 of 3
Commissioning Instruction Page
STANDARD
7. Appendices
- None -
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Fossil Power Generation Offenders will be held liable for payment of damages. All rights created by patent grant or
Energy Solutions registration of a utility model or design patent are reserved.
Inbetriebsetzungs-Anweisung Seitenzahl: 1 of 2
Commissioning Instruction No. of Pages
STANDARD
Table of Contents
1 Task
2 Preconditions
3 Precautions
4 Scope
5 Execution
6 Documentation
7 Appendices
1. Task
To ensure that transformers have been properly installed and the respective safety and
monitoring devices are in perfect working order.
*) Nicht zutreffendes
streichen Erstellt Erstellt/Geprüft*) Geprüft/Freigeg.*) Geprüft/Freigeg.*)
*) Delete as appropriate Prepared by Prepared/Verified by Verified/Released by Verified/Released by
Dienststelle
Department
Name
Name
Datum
Date
Unterschrift
Signature
Geändert: Geprüft/Freigegeben:
modified by: Reviewed/released by:
Verteiler:
Copies to
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Fossil Power Generation Offenders will be held liable for payment of damages. All rights created by patent grant or
registration of a utility model or design patent are reserved.
Energy Solutions
Inbetriebsetzungs-Anweisung: Seite: 2 of 2
Commissioning Instruction Page
STANDARD
System/Titel:
System/Title CI-E17 Power Transformers
2. Preconditions
2.2 Documentation
· The manufacturer instructions are available for component.
· The circuit diagrams are available.
· Commissioning checklist.
2.3 Personnel
· 1 Commissioning engineer: Engineer or technician with experience in
commissioning of electrical equipment.
3. Precautions
· The VDE Regulations for ”Erection and
Operation of Electrical Power Installations with rated voltage up to 1000 V” (VDE
0100/0105) shall be observed.
· Refer to manufacturer instruction.
4. Scope
· Check of safety and monitoring devices
5. Execution
· All tests shall be performed according to the manufacturer instructions.
6. Documentation
The activities performed shall be documented in the manufacture commissioning checklist
7. Appendices
- None -
Siemens Sector Energy Transmittal, reproduction, dissemination and/or editing of this document as well as utilization Electrical Commissioning
of its content and communication thereof to others without express authorization are prohibited.
Fossil Power Generation Offenders will be held liable for payment of damages. All rights created by patent grant or
registration of a utility model or design patent are reserved.
Energy Solutions
t to the handling restrictions set forth on the title page.