You are on page 1of 4

Today

SO delivery date

Customer Lead Time

Delivery Order
Scheduled date
Security
Sales
Receipt
RFQ PO Order By scheduled date
creation
Security MTO
Delivery LT
Purchase Buy

MO MO deadline
creation

MTO
Security Manufac
Manufacturing LT ture +
Receipt MFG
RFQ Buy
PO Order By scheduled date MO planned date
creation
Security
Delivery LT
Purchase
Today

RFQ
creation PO Order By RO scheduled date
Days to Security Forecasted Qty Order
Delivery LT
Purchase Purchase < Minimum Qty Points
Buy

Order
Security Forecasted Qty
Manufacturing LT Points
MFG < Minimum Qty
Manuf
MO creation acture
= MO deadline Starting v14, the order point (with Minimum Qty = 0) is
= MO planned date the default setup on all products.

PROPOSAL
Today

RFQ
creation PO Order By RO scheduled date
Security Forecasted Qty Order
Days to React Delivery LT
Purchase < Minimum Qty Points
Buy

Order
Security Forecasted Qty
Days to React Manufacturing LT Points
MFG < Minimum Qty
Manuf
MO deadline acture
MO = MO planned date
creation
Starting v14, the order point (with Minimum Qty = 0) is
the default setup on all products.
Day or
first day of the week or
Today = when hitting Replenish first day of the month

Receipt
RFQ PO Order By scheduled date
creation
Security MPS
Delivery LT
Purchase Buy

MO deadline
MO = MO planned date
creation MPS
Security
Manufacturing LT Manufac
MFG
ture
Today

RFQ Creation
= PO Order By
Receipt scheduled date

Forecasted Qty Manual


Delivery LT
increased Buy

Manual
Manufacturing LT Forecasted Qty Manufa
increased cture
MO creation
= MO planned date

You might also like