Professional Documents
Culture Documents
DEPARTMENT OF AGRICULTURE
Regional Field Unit No.XII,Satellite Office
Regional Center XII, Carpenter Hill, Koronadal City
Telefax No. (083) 520-0460
I DIVERSION WORKS
L = 6.00 m
H = 2.0 m
II IRRIGATION WORKS
Main Canal A : L = 1700; W x H = 0.8 m x 1.0 m
Main Canal B : L = 925 ; W x H = 1.0 m x 1.0 m
Lateral Canal : L = 4200 m ; W x H = 0.70 m x 0.60 m
CONSTRUCTION PERIOD:
311 CD
PURPOSE:
FOR THE CONSTRUCTION OF POPOYON DIVERSION STRUCTURE & CONCRETING
OF CANAL AT KM.129, BRGY. POPOYON, TULUNAN, NORTH COTABATO
Requested by: Recommending Approval Approved by:
Signature :
Printed Name: Engr. ERWIN A. ARGUELLES JOHN B. PASCUAL, DVM MILAGROS C. CASIS, CE
Designation: Chief, READ OIC RTD for Operations Regional Executive Director
Page 1 of 90
Republic of the Phillippines
Department of Agriculture
Regional Field Office XII
Koronadal City
Mark Up
Estimated Direct
NO. Item No. Description Quantity Unit
Cost OCM Profit
(12%) (8%)
(6)
(i) (1) (2) (3) (4) (5) (7)
II Dam Works
803 (1)a Structure Excavation 436.50 cu.m
Mark Up
86,843.75
Total Mark-Up Total Cost/Unit TOTAL COST
EAO
VAT (5%)
(1%)
(10) (10) (11) (12)
((5)+(6)+(7))*((5)(5%)) (9) (6)+(7)+(8)+(9) (5) + (10) (11) x (3)
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
P -
-
P -
Republic of the Phillippines
Department of Agriculture
Regional Field Office XII
Koronadal City
PROGRAM OF WORKS
Project Name: REHABILTITATION AND CANAL IMPROVEMENT OF NEW TIGBAUAN DIVERSION DAM
Location: Brgy. Kabulakan, Matalam, North Cotabato
Project Cost:
Project Description: Implementation Mode: "BY CONTRACT"
Slope Protection: L = 27.0m Duration of Construction: 165 C.D.
NO. Item No. Description % Wt. Quantity Unit Unit Cost (P) Total Amount (P)
I Mobilization and Demobilzation
Construction of Camps, Other Temporary Facilities and
A.1.1 1.00 L.S
Movement of Equipment
0
Republic of the Phillippines
Department of Agriculture
Regional Field Office XII
Koronadal City
Mark Up
Estimated Direct
NO. Item No. Description Quantity Unit
Cost OCM Profit
(15%) (10%)
(6)
(i) (1) (2) (3) (4) (5) (7)
B.17 Temporary Diversion of Water and Care of Creek 1.00 L.S P 52,758.24 P 7,913.74 P 5,275.82
SPL-4 Concrete Signage w/ DA Logo & Markings 1.00 lot P 30,178.46 P 4,526.77 P 3,017.85
804 (1)a Embankment from Structure Excavation 77.00 cu.m P 510.63 P 76.59 P 51.06
804 (2)a Selected Borrow for Topping Case-1 13.00 cu.m P 774.31 P 116.15 P 77.43
900 (1) a1 Structural Concrete Class A 43.50 cu.m P 7,766.42 P 1,164.96 P 776.64
902 (1)a Reinforcing Steel Bars Grade 40 1,120.50 kgs. P 65.57 P 9.83 P 6.56
702,607.40 -
P 7.88 39.38 165.41 P 15,713.73 11,972.37
E. ABDULA
nal Executive Director
Determining the Number of Calendar Days of the Project:
PERT-CPM
B
ITEM A.1.1
F
ITEM B.17
K P
ITEM SPL-4
G . ITEM 1708(1)
A H J L Q
N R
MOVING IN ITEM 803(1)a ITEM 900 (1)a1 ITEM 900 (2)a ITEM ITEM 804(2)a
7 C.D. 5 C.D. ITEM 802(2) MOVING OUT
8 C.D. 20 C.D 40 C.D 804(1) 3 C.D 5 C.D.
7 C.D
I M O
ITEM
902(1)a1
30 C.D ITEM 1718 ITEM 713 a
E
ITEM
B.7(2)
D
ITEM B.5
C
ITEM
SPL-1
PREPARED BY: REVIEWED BY: CHECKED BY: RECOMMENDING APPROVAL: APPROVED BY:
ENGR. REYMART A. NUÑEZ ENGR. ISRAEL M. JUANDAY JOCELYN F. TORRES, Ph.D., ABE ZALDY M. BOLORON, MPA SAILILA E. ABDULA
Engineer II EPDS Section Head RAED Chief OIC-RTD for Operations OIC-Regional Executive Director
Republic of the Phillippines
Department of Agriculture
Regional Field Office XII
Koronadal City
PROGRAM OF WORKS
POSTHARVEST FACILITY
PROJECT DESCRIPTION: DIMENSION:
Length ( L) = 36 m, Width ( W) = 20 meters, Height ( H) = 1
Construction of 20m x 36m - Rice Processing Facility Warehouse with Office and Equipment / Utility ( N.G.L to Roof Apex Line)
Room
NO. Item No. Description % Wt. Quantity Unit Unit Cost (P) Total Amount
I Mobilization and Demobilzation
Construction of Camps, Other Temporary Facilities and
A.1.1 2.42% 1.00 L.S P 76,037.50 P
Movement of Equipment
B.7 (2) Occupational Safety and Health Standards Program 1.77% 1.00 L.S P 55,671.00 P
B.17 Temporary Diversion of Water and Care of Creek 2.20% 1.00 L.S P 69,245.19 P
SOURCE OF FUND
Breakdown of Estimated Sub-Project Cost Total Co
DA FUND LGU Equity(cash)
A. Direct Cost
P 2
Republic of the Phillippines
Department of Agriculture
Regional Field Office XII
Koronadal City
PhP18,000,000.00
RICE PROGRAM CY - 2023
197 CALENDAR DAYS
BY CONTRACT
DIMENSION:
Length ( L) = 36 m, Width ( W) = 20 meters, Height ( H) = 12.10 meters
( N.G.L to Roof Apex Line)
15
P 76,037.50
P 55,671.00
P 11,422.38
P 69,245.19
P -
P 170,290.89
P 39,609.22
P 422,276.18
P 15,713.73
P 51,605.11
P 13,211.62
P 443,413.76
P 96,425.78
P 15,583.36
P 66,654.03
P 702,607.40
P 25,306.51
P 4,631.42
P 515,028.14
P 56,911.61
P 98,694.63
P 189,171.80
P 41,256.39
P 48,096.04
P 2,018,958.26
P 3,143,841.84
Total Cost
P 2,417,751.09
#REF!
PROJECT PROGRAM OF WORKS
POSTHARVEST FACILITY
PROJECT DESCRIPTION: DIMENSION:
Length ( L) = 36 m, Width ( W) = 20 meters, Heig
Construction of 20m x 36m - Rice Processing Facility Warehouse with ( N.G.L to Roof Apex Line)
Office and Equipment / Utility Room
1014(1)b1
Prepainted metal Sheet (Corrugated, Long Span,
above 0.427 mm thk
1047(2)a Structural Steel (Trusses)
1047(2)b Structural Steel (Purlins)
1047(6) Metal Structure Accessories (Steel Plates)
1047(7)b Metal Structure Accessories (Sagrods)
1047(4) Metal Structure Accessories (Crossbracing)
1047(3)c Metal Structure Accessories (Turnbuckle)
1013(2)a1
Fabricated Metal Roofing Accessory (Ridge/Hip
Rolls, Ga. 26)
1013(2)a2
Fabricated Metal Roofing Accessory (Flashing, Ga.
26)
1013(2)b1
Fabricated Metal Roofing Accessory (Gauge
24,Gutter)
Sub-total of C.6
Sub-total of C.7
Sub-total of Part D
ENGR. JUN B.
RAED DEPUTY CHIEF /
REVIEWED BY: RECOMMENDING APPROVAL:
APPROVED BY:
T COST PhP18,000,000.00
L.s
L.s
Ea.
L.s
L.s
-
SOURCE OF FUND
Total Cost
LGU Equity(cash)
PROGRAM OF WORKS
Item No. Scope of work % Wt. Quantity Unit Adjusted Unit Cost Total
804 (1)a Embankment from Structure Excavation Err:509 77.00 cu.m 670.20 P 51,605.11
804 (2)a Selected Borrow for Topping Case-1 Err:509 13.00 cu.m 1,016.28 P 13,211.62
902 (1)a Reinforcing Steel Bars, Grade 40 Err:509 7,105.30 kgs. 86.71 P 616,112.62
SPL-3 HDPE Pipe (6" dia.) Err:509 2.00 cu.m 24,231.24 P 48,462.48
501 (1) Pipe Culvert (610 mm dia.) Err:509 33.00 cu.m 5,199.65 P 171,588.34
713 Wooden Flashboard Err:509 52.00 bd.ft 3,665.64 P 190,613.11
1708 (1) Levelling Course Err:509 44.00 cu.m 2,617.02 P 115,148.68
Construction of Camps, Other Temporary Facilities and Movement of
A.1.1 Err:509 1.00 L.S 76,037.50 P 76,037.50
Equipment
B.17 Temporary Diversion of Water and Care of Creek Err:509 1.00 L.S 69,772.77 P 69,772.77
B.5 Concrete Signage w/ DA Logo and Markings Err:509 1.00 lot 11,422.38 P 11,422.38
TOTAL PROJECT COST Err:509 Err:509
SOURCE OF FUND
Breakdown of Estimated Sub-Project Cost Total Cost
DA FUND LGU Equity(cash)
A. Direct Cost
Material P 2,311,353.65 P 2,311,353.65
Equipment & Fuel P 711,922.41 P 711,922.41
Labor P 786,247.57 P 786,247.57
Mineral & Quarry Toll Fee, Mineral Tax
Sub-Total Cost A P 3,809,523.63 P - P 3,809,523.63
B. Indirect Cost
1. OCM (15% of the EDC) P 571,428.54 P 571,428.54
2. Contractor's Profit(10% of the EDC) P 380,952.36 P 380,952.36
3. VAT (5% of EDC+OCM+Profit) P 238,095.23 P 238,095.23
Sub-Total Cost B P 1,190,476.13 P 1,190,476.13
TOTAL PROJECT COST P 4,999,999.76 P - P 4,999,999.76
Say >>>>>> P 5,000,000.00
NATHANIEL I. NEBRES REYMART A. NUÑEZ ENGR. ISRAEL M. JUANDAY JOCELYN F. TORRES, Ph.D., ABE
Engineer I Engineer I EPDS Section Head Chief, RAED
Page 28 of 90
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
B. Equipment
F. Materials
A. Labor
B. Equipment
C. Materials:
Selected borrow with 25% shrinkage cu.m. 1.00 300.00 P 300.00
A. Labor
B. Equipment
a. Backhoe (0.75 - 1.00 cu.m) 1 0.07 P 2,000.00 P 133.33.
b. Compactor 1 0.07 ₱ 1,720.00 P 114.67.
Minor Tools (10% of labor) P 2.39
P 250.39
Name and Specifications Unit Quantity Unit Cost Amount
C. Materials
a.) Selected Borrow Materials cu.m 1 500.00 P 500.00
No. of
Designation No. of Hours Hourly Rate Amount
Person
A. Labor
Installation/Removal of Formworks
a. Skilled Laborer 3 0.63 P 52.50 P 98.44
b. Laborer 10 0.63 P 47.50 P 296.88
B. Equipment
C Materials
No. of
Designation No. of Hours Hourly Rate Amount
Person
A. Labor
Installation/Removal of Formworks
a. Skilled Laborer 3 0.63 P 52.50 P 98.44
b. Laborer 10 0.63 P 47.50 P 296.88
B. Equipment
C Materials
A. Labor
B. Equipment
Minor Tools (10% of labor) P 15.65
No. of
Designation No. of Hours Hourly Rate Amount
Person
A. Labor
Installation/Removal of Formworks
a. Skilled Laborer 3 0.63 P 67.00 P 125.63
b. Laborer 6 0.63 P 51.72 P 193.95
B. Equipment
C Materials
No. of
Designation No. of Hours Hourly Rate Amount
Person
A. Labor
Installation/Removal of Formworks
a. Skilled Laborer 3 0.63 P 67.00 P 125.63
b. Laborer 6 0.63 P 51.72 P 193.95
B. Equipment
C Materials
A. Labor
B. Equipment
C Materials
No. of No. of
Designation Hourly Rate Amount
Person Hours
A. Labor
F. Materials
A. Labor
B. Equipment
C. Materials
No. of No. of
Designation Hourly Rate Amount
Person Hours
A. Labor
C. Materials:
a. Wooden Flashboard (Good Lumber) bd.ft. 45 P 50.00 P 2,250.00
A. Labor
B. Equipment
a. Backhoe 1 0.5000
C Materials
0.125
Hourly Rate Amount
P 84.86. P 84.86.
P 67.00. P 134.00.
P 51.72. P 310.32.
Labor Rates
P/day
P 1,000.00
1,800.00 P 1,800.00.
600.00 P 600.00.
P 2,400.00.
P 3,929.18.
of D P 589.38.
of D P 392.92.
of (D + E + F) P 245.57.
(G + H + I + J) P 5,157.05. 5,157.05
RSB 10mm (horizontal)
694.8
2570.67778 3.7
257.067778
0.00
RSB 12mm (horizontal)
Check length 3
spa. 0.3
10.0
RSB length 1.6
m/lentgh 6
Sub Total L 2.7
kgs/length
A. Equipment
C Materials
Note:
*Delivery cost are included in the unit cost.
B.
55,671.00
Reservoir
Outlet
TOTAL
338
= 141.96
0.7
0.6
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Equipment
Backhoe 1 16 2,000.00 P 32,000.00
Water pump with accessories
10mm diameter 1 80 200.00 P 16,000.00
Minor Tools 15% of Labor P 620.64
B. Labor
No. of No. of
Designation Hourly Rate Amount
Person Hours
A. Labor
B. Materials
Trashrack (2.00m x 1.00m) 1 Ass. 6,000.00 6,000.00
3/8'' x 2''Flar Bar Welded on
3/8'' x 2'' Angle Bar, Painted with Red Lead
Oxide Primer
Hinge (4'' x 4'') 1 pc 100.00 100.00
A. Labor
B. Equipment
C. Materials
A. Labor
B. Equipment
C Materials
1.00
5,160.33
RSB 10mm (horizontal) RSB 12mm (horizontal)
694.8
2570.67778 3.7 kgs/length
257.067778
A. Labor
B. Equipment
P -
P -
C. Materials:
a. Steel Trash Rack w/ complete accessories assy 1 P 50,000.00 P 50,000.00
A. Labor
a. Construction Foreman 1 4
b. Skilled Laborer 1 4
c. Laborer 4 4
B. Equipment
C. Materials
Sub-Total for C
D. Total Direct Cost
E. Overhead, Contingencies & Miscellaneous (OCM) 15%
F. Contractor's Profit (CP) 10%
G. Value Added Tax (VAT) 5%
I. Total Cost
IS (DUPA)
84.86 P 339.44
67.00 P 268.00 Labor Rates
51.72 P 827.52 P/day
P 143.50
P 143.50
15.00 P 1,935.00
310.00 P 4,960.00
800.00 P 800.00
1100.00 P 1,650.00
55.00 P 1,925.00
90.00 P 90.00
50.00 P 1,000.00
800.00 P 800.00
100.00 P 500.00
12,000.00 P 12,000.00
70.00 P 2,940.00
P 28,600.00
A+B+C P 30,178.46
of D P 4,526.77
of D P 3,017.85
of (D+E+F) P 1,886.15
D+E+F+G P 39,609.22
Labor Rates
P/hr
80.00
68.75
81.25
50.00
37.50
43.75
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
B. Equipment
C. Materials
1.) Back-up Computation for item 405 (3) - Concrete Class "B" (w/ forms)
2. ) Back-up Computation for item 405 (3) - Concrete Class "B" (w/o forms)
B.) Canal B
C1 0.50 4 2.00
C2 1.95 4 7.80
C3 3.20 4 12.80
C4 3.95 4 15.80
C5 4.00 4 16.00
C6 4.10 4 16.40
C7 3.85 4 15.40
C8 4.45 4 17.80
C9 3.50 4 14.00
C10 1.90 4 7.60
Total no.
say
9.47 kgs/ 6m length 198.87
add 15 % splicing 29.83
Total 228.70 kgs
A.) Canal B
A.) Canal B
1.) Back-up Computation for item 405 (3) - Concrete Class "B" (w/ forms)
2.) Back-up Computation for item 405 (3) - Concrete Class "B" (w/o forms)
8.) Back-up Computation for item 500 (2) - RCP (610 mm)
VOLUME
0.01
0.10
0.18
0.23
0.23
0.24
0.22
0.26
0.20
0.10
0.47
2.25 cu.m
214.5
Volume 165.08
24.52 cu.m 199.94
Volume
1.161 cu.m
49.42 cu.m
Volume 138
3.0 cu.m 116.64
140.16
Volume
18.36 cu.m
21.36 cu.m
cture
no. of pcs
1pc/6m length
0.33
1.30
2.13
2.63
2.67
2.73
2.57
2.97
2.33
1.27
20.93
21.00
cture
no. of pcs
1pc/6m length
0.50
1.95
3.20
3.95
4.00
4.10
3.85
4.45
3.50
1.90
B
no. of pcs (1pc/6m
length)
2.61
34.01
35.00
cture
no. of pcs
1pc/6m length
73.50
73.50
824
204.00
238.00
589.00
147
Volume 128.64
18.36 cu.m 132.24
18.36 cu.m
Volume
36.72 cu.m
Total Volume
2.5 cu.m
514
474.78
39.22 cu.m 529.80
4.08 cu.m
7.20 cu.m
RKS
Volume
30.6 cu.m
Volume
3 cu.m
Volume
1.26 cu.m
34.86 cu.m
Volume
21.42 cu.m
Volume
2.1 cu.m
23.52 cu.m
6.00 cu.m
Volume
55.02 cu.m
55.02 cu.m
22.08 cu.m
14.2 cu.m
of RCP needed
l.m.
7.00 l.m
Garcia, ABE
ction Head
C.) Concrete Canal (from sta. 0+597 to exisiting canal)
kgs
kgs
to exisiting canal)
5.1
Computation
a.) Clearing and Grubbing