NAME OF PROJECT : Construction of Flood Control Structure of Dapdap River (Both Stream) along Bacolod North Road (S00406NR)
Manapla, Negros Occidental (18GK0072)
CONTRACTOR : C'zarles Construction & Supply / GKMM COST : Php 37,235,562.84 SOURCE : Regular Infra CY 2018
Construction & Supplies (JV)
LOCATION : Manapla, Negros Occidental PAVT. PAVT.
LENGTH : WIDTH : THICKNESS :
EFFECTIVITY DURATION EXPIRY
DATE : April 12, 2018 C.D. : 170 C.D. DATE : September 28, 2018
A. TESTS TO BE PERFORMED:
A.1.1(3) Construction of Field Office for the Engineer l.s. 1.00 I.R.
100(1) Clearing & Grubbing ha 0.35 I.R.
103(1)a Structure Excavation (Common Soil) m³ 9,927.00 I.R.
506(1) Stone Masonry m³ 6,525.00 I.R.
a. Portland Cement bags 35,888.00 Q-18;FT-180
b. Fine Aggregates m³ 1,957.50 Q-2;G-26
c. Boulders m³ 6,851.25 UW-23
B.5 Project Billboard / Signboard each 2.00 I.R.
B.7 Occupational Safety & Health Program month 5.67 I.R.
B.9 Mobilization / Demobilization l.s. 1.00 I.R.
We hereby certify that we have conducted an inspection and verification of work accomplished on the above mentioned
project for the period March 22, 2018 - June 13, 2018 ; We further certify that we have found the quality of materials in the
following items of work corresponding to the quantity accomplished conforms with the STANDARD SPECIFICATIONS and Special
provisions of the contract viz.
QUANTITY ACCOMPLISHED
%
ITEM NO. DESCRIPTION PROGRAMMED UNITS
TOTAL ACCOMPLISHMENT
THIS WEEK
TO DATE
B.5 Project Billboard / Signboard 1.00 each 1.00 1.00 0.18
B.7 Occupational Safety & Health Program 3.00 month 2.80 2.80 7.22
403(5) Structural Steel, Furnished, Fabricated & Erected 9,503.65 kgs 9503.65 9503.65 23.60
1014(1)b2 Pre-painted Metal Sheets 627.00 m² 627.00 627.00 3.56
Name of Project and Location : Construction of Multi-Purpose Building (Covered Court), Brgy. Hilub-ang, Calatrava, Negros Occidental (17RB0208)
Implementing Office : DPWH 1st Neg. Occ. Eng'g. District Name of Contractor : Trimluv Builders & Supply
Project Duration : 90 C.D. DPWH Project Inspector :
a. Date Started : March 22, 2018 Project Accomplishment :
b. Target Completion Date : June 19, 2018 Project cost : Php2,817,771.89
SAMPLED
QUANTITY ORIGINAL SOURCE KIND OF SPEC'S TESTED
LAB. No. KIND OF MATERIALS At REMARKS
REPRESENTED OF MATERIALS TESTS ITEM No.
(1) (2) (11) (12)
(3) (4) (5) (6) BY DATE BY DATE
17RB0208 - 1 Portland Cement Quality Test Jobsite FT 901(1)c1 Chua / Dela Cruz 3/22/2018 Chua / Dela Cruz 3/23/2018 Contractor's Lab Satisfactory
17RB0208 - 2 Coarse Aggregate Quality Test Malogo River G 901(1)c1 Chua / Dela Cruz 3/22/2018 Chua / Dela Cruz 3/23/2018 Contractor's Lab Recommended for Use
17RB0208 - 3 Fine Aggregate Quality Test Malogo River G 901(1)c1 Chua / Dela Cruz 3/22/2018 Chua / Dela Cruz 3/23/2018 Contractor's Lab Recommended for Use
17RB0208 - 4 Coarse Aggregate Quality Test Malogo River AL 901(1)c1 Chua / Dela Cruz 3/22/2018 Chua / Dela Cruz 3/24/2018 DPWH Lab Satisfactory
17RB0208 - 5 Coarse Aggregate Quality Test Malogo River SGA 901(1)c1 Chua / Dela Cruz 3/22/2018 Chua / Dela Cruz 3/24/2018 Contractor's Lab Satisfactory
17RB0208 - 6 Fine Aggregate Quality Test Malogo River SGA 901(1)c1 Chua / Dela Cruz 3/22/2018 Chua / Dela Cruz 3/24/2018 Contractor's Lab Satisfactory
17RB0208 - 7 Reinforcing Steel Bars 2,426.93 kgs UW 901(1)c1 Chua / Dela Cruz 3/23/2018 Chua / Dela Cruz 3/25/2018 Contractor's Lab Recommended for Use
17RB0208 - 8 Concrete Cylinder Trial Mix Jobsite COMP 901(1)c1 Chua / Dela Cruz 3/24/2018 Chua / Dela Cruz 3/31/2018 DPWH Lab Satisfactory
17RB0208 - 9 Coarse Aggregate 54.70 m³ Malogo River G 901(1)c1 Chua / Dela Cruz 4/1/2018 Chua / Dela Cruz 4/3/2018 Contractor's Lab Recommended for Use
17RB0208 - 10 Fine Aggregate 27.35 m³ Malogo River G 901(1)c1 Chua / Dela Cruz 4/1/2018 Chua / Dela Cruz 4/3/2018 Contractor's Lab Recommended for Use
17RB0208 - 11 Portland Cement 520 Bags Jobsite FT 901(1)c1 Chua / Dela Cruz 4/1/2018 Chua / Dela Cruz 4/3/2018 Contractor's Lab Satisfactory
Note: 1. Indicate the Name of batching plant as source of ready-mix concrete and hot -bituminuos mix to column (4).
2. Indicate the name of testing laboratories on the sample tested to column (11).
ESMAEL L. CHUA III RAUL DELA TORRE MARCELINO C. ESTALES ARNEL P. TORREFRANCA
Materials Engineer - Trimluv Builders & Supply Materials Engineer - DPWH Project Engineer - DPWH Chief Quality Assurance Section, DPWH
SUMMARY REPORT OF FIELD TEST
FOR THE MONTH OF MAY 2018
Name of Project and Location : Construction of Multi-Purpose Building (Covered Court), Brgy. Hilub-ang, Calatrava, Negros Occidental (17RB0208)
Implementing Office : DPWH 1st Neg. Occ. Eng'g. District Name of Contractor : Trimluv Builders & Supply
Project Duration : 90 C.D. DPWH Project Inspector :
a. Date Started : March 22, 2018 Project Accomplishment :
b. Target Completion Date : June 19, 2018 Project cost : Php2,817,771.89
SAMPLED
QUANTITY ORIGINAL SOURCE KIND OF SPEC'S TESTED
LAB. No. KIND OF MATERIALS At REMARKS
REPRESENTED OF MATERIALS TESTS ITEM No.
(1) (2) (11) (12)
(3) (4) (5) (6) BY DATE BY DATE
17RB0208 - 12 Fine Aggregate 14.40 m³ Malogo River G 1021(1)a Chua / Dela Cruz 4/25/2018 Chua / Dela Cruz 4/26/2018 Contractor's Lab Recommended for Use
17RB0208 - 13 Portland Cement 260 Bags Jobsite FT 1021(1)a Chua / Dela Cruz 4/25/2018 Chua / Dela Cruz 4/26/2018 Contractor's Lab Satisfactory
17RB0208 - 14 Concrete Cylinder Footing Jobsite COMP 901(1)c1 Chua / Dela Cruz 4/17/2018 Chua / Dela Cruz 5/2/2018 DPWH Lab Satisfactory
17RB0208 - 15 Concrete Cylinder Footing Jobsite COMP 901(1)c1 Chua / Dela Cruz 4/18/2018 Chua / Dela Cruz 5/2/2018 DPWH Lab Satisfactory
17RB0208 - 16 Concrete Cylinder Column Jobsite COMP 901(1)c1 Chua / Dela Cruz 4/20/2018 Chua / Dela Cruz 5/4/2018 DPWH Lab Satisfactory
17RB0208 - 17 Concrete Cylinder Column Jobsite COMP 901(1)c1 Chua / Dela Cruz 4/27/2018 Chua / Dela Cruz 5/11/2018 DPWH Lab Satisfactory
17RB0208 - 18 Concrete Cylinder Floor Slab Jobsite COMP 901(1)c1 Chua / Dela Cruz 5/3/2018 Chua / Dela Cruz 5/17/2018 DPWH Lab Satisfactory
17RB0208 - 19 Concrete Cylinder Floor Slab Jobsite COMP 901(1)c1 Chua / Dela Cruz 5/4/2018 Chua / Dela Cruz 5/18/2018 DPWH Lab Satisfactory
17RB0208 - 20 Concrete Cylinder Floor Slab Jobsite COMP 901(1)c1 Chua / Dela Cruz 5/4/2018 Chua / Dela Cruz 5/19/2018 DPWH Lab Satisfactory
Note: 1. Indicate the Name of batching plant as source of ready-mix concrete and hot -bituminuos mix to column (4).
2. Indicate the name of testing laboratories on the sample tested to column (11).
ESMAEL L. CHUA III RAUL DELA TORRE MARCELINO C. ESTALES ARNEL P. TORREFRANCA
Materials Engineer - Trimluv Builders & Supply Materials Engineer - DPWH Project Engineer - DPWH Chief Quality Assurance Section, DPWH
SUMMARY REPORT OF FIELD TEST
FOR THE MONTH OF JUNE 2018
Name of Project and Location : Construction of Multi-Purpose Building (Covered Court), Brgy. Hilub-ang, Calatrava, Negros Occidental (17RB0208)
Implementing Office : DPWH 1st Neg. Occ. Eng'g. District Name of Contractor : Trimluv Builders & Supply
Project Duration : 90 C.D. DPWH Project Inspector :
a. Date Started : March 22, 2018 Project Accomplishment :
b. Target Completion Date : June 19, 2018 Project cost : Php2,817,771.89
SAMPLED
QUANTITY ORIGINAL SOURCE KIND OF SPEC'S TESTED
LAB. No. KIND OF MATERIALS At REMARKS
REPRESENTED OF MATERIALS TESTS ITEM No.
(1) (2) (11) (12)
(3) (4) (5) (6) BY DATE BY DATE
NO TEST PERFORMED
Note: 1. Indicate the Name of batching plant as source of ready-mix concrete and hot -bituminuos mix to column (4).
2. Indicate the name of testing laboratories on the sample tested to column (11).
ESMAEL L. CHUA III RAUL DELA TORRE MARCELINO C. ESTALES ARNEL P. TORREFRANCA
Materials Engineer - Trimluv Builders & Supply Materials Engineer - DPWH Project Engineer - DPWH Chief Quality Assurance Section, DPWH
C'Zarles Construction & Supply / GKMM Construction & Supplies (JV)
STATUS OF TEST
Project : Construction of Flood Control Structure of Dapdap River (Both Stream) along Bacolod North Road (S00406NR), Manapla, Negros Occidental (18GK0072)
Location : Manapla, Negros Occidental For the Period Ending: April 22, 2018
A.1.1(3) Construction of Field Office for the Engineer 1.00 l.s. I.R. None I.R.
100(1) Clearing & Grubbing 0.35 ha I.R. None I.R.
103(1)a Structure Excavation (Common Soil) 9,927.00 m³ I.R. None I.R.
506(1) Stone Masonry 6,525.00 m³ I.R. None I.R.
a. Portland Cement 35,888.00 bags Q-18;FT-180 Q-1;FT-10 Q-17;FT-170
b. Fine Aggregates 1,957.50 m³ Q-2;G-26 Q-1;G-1 Q-1;G-25
c. Boulders 6,851.25 m³ UW-23 UW-1 UW-22
B.5 Project Billboard / Signboard 2.00 each I.R. I.R. None
B.7 Occupational Safety & Health Program 5.67 month I.R. None I.R.
B.9 Mobilization / Demobilization 1.00 l.s. I.R. None I.R.
STATUS OF TEST
Project : Construction of Flood Control Structure of Dapdap River (Both Stream) along Bacolod North Road (S00406NR), Manapla, Negros Occidental (18GK0072)
Location : Manapla, Negros Occidental For the Period Ending: May 22, 2018
A.1.1(3) Construction of Field Office for the Engineer 1.00 l.s. I.R. None I.R.
100(1) Clearing & Grubbing 0.35 ha I.R. None I.R.
103(1)a Structure Excavation (Common Soil) 9,927.00 m³ I.R. None I.R.
506(1) Stone Masonry 6,525.00 m³ I.R. None I.R.
a. Portland Cement 35,888.00 bags Q-18;FT-180 Q-2;FT-40 Q-16;FT-140
b. Fine Aggregates 1,957.50 m³ Q-2;G-26 Q-1;G-7 Q-1;G-19
c. Boulders 6,851.25 m³ UW-23 UW-6 UW-17
B.5 Project Billboard / Signboard 2.00 each I.R. I.R. None
B.7 Occupational Safety & Health Program 5.67 month I.R. None I.R.
B.9 Mobilization / Demobilization 1.00 l.s. I.R. None I.R.
STATUS OF TEST
Project : Construction of Flood Control Structure of Dapdap River (Both Stream) along Bacolod North Road (S00406NR), Manapla, Negros Occidental (18GK0072)
Location : Manapla, Negros Occidental For the Period Ending: June 22, 2018
A.1.1(3) Construction of Field Office for the Engineer 1.00 l.s. I.R. I.R. None
100(1) Clearing & Grubbing 0.35 ha I.R. None I.R.
103(1)a Structure Excavation (Common Soil) 9,927.00 m³ I.R. None I.R.
506(1) Stone Masonry 6,525.00 m³ I.R. None I.R.
a. Portland Cement 35,888.00 bags Q-18;FT-180 Q-6;FT-70 Q-12;FT-110
b. Fine Aggregates 1,957.50 m³ Q-2;G-26 Q-1;G-13 Q-1;G-13
c. Boulders 6,851.25 m³ UW-23 UW-9 UW-14
B.5 Project Billboard / Signboard 2.00 each I.R. I.R. None
B.7 Occupational Safety & Health Program 5.67 month I.R. None I.R.
B.9 Mobilization / Demobilization 1.00 l.s. I.R. None I.R.
STATUS OF TEST
Project : Construction of Flood Control Structure of Dapdap River (Both Stream) along Bacolod North Road (S00406NR), Manapla, Negros Occidental (18GK0072)
Location : Manapla, Negros Occidental For the Period Ending: July 22, 2018
A.1.1(3) Construction of Field Office for the Engineer 1.00 l.s. I.R. I.R. None
100(1) Clearing & Grubbing 0.35 ha I.R. I.R. None
103(1)a Structure Excavation (Common Soil) 9,927.00 m³ I.R. None I.R.
506(1) Stone Masonry 6,525.00 m³ I.R. None I.R.
a. Portland Cement 35,888.00 bags Q-18;FT-180 Q-10;FT-110 Q-8;FT-70
b. Fine Aggregates 1,957.50 m³ Q-2;G-26 Q-1;G-15 Q-1;G-11
c. Boulders 6,851.25 m³ UW-23 UW-13 UW-10
B.5 Project Billboard / Signboard 2.00 each I.R. I.R. None
B.7 Occupational Safety & Health Program 5.67 month I.R. I.R. None
B.9 Mobilization / Demobilization 1.00 l.s. I.R. None I.R.
STATUS OF TEST
Project : Construction of Flood Control Structure of Dapdap River (Both Stream) along Bacolod North Road (S00406NR), Manapla, Negros Occidental (18GK0072)
Location : Manapla, Negros Occidental For the Period Ending: August 22, 2018
A.1.1(3) Construction of Field Office for the Engineer 1.00 l.s. I.R. I.R. None
100(1) Clearing & Grubbing 0.35 ha I.R. I.R. None
103(1)a Structure Excavation (Common Soil) 9,927.00 m³ I.R. I.R. None
506(1) Stone Masonry 6,525.00 m³ I.R. I.R. None
a. Portland Cement 35,888.00 bags Q-18;FT-180 Q-13;FT-140 Q-5;FT-40
b. Fine Aggregates 1,957.50 m³ Q-2;G-26 Q-1;G-19 Q-1;G-7
c. Boulders 6,851.25 m³ UW-23 UW-17 UW-6
B.5 Project Billboard / Signboard 2.00 each I.R. I.R. None
B.7 Occupational Safety & Health Program 5.67 month I.R. I.R. None
B.9 Mobilization / Demobilization 1.00 l.s. I.R. None I.R.
INSPECTION REPORT
Name of Project : Construction of Flood Control Structure of Dapdap River (Both Stream) along Bacolod North Road (S00406NR)
Manapla, Negros Occidental (18GK0072)
QUANTITY
ITEM NO. DESCRIPTION REMARKS
Planned Actual
A.1.1(3) Construction of Field Office for the Engineer 1.00 l.s. 1.00 l.s. The indicated item of works
have been accomplished in
100(1) Clearing & Grubbing 0.35 ha 0.35 ha
accordance with the plans,
B.5 Project Billboard / Signboard 2.00 each 2.00 each specifications and program of
B.7 Occupational Safety & Health Program 5.67 month 5.67 month works.
Inspected by:
MARCELINO C. ESTALES
Project Engineer - DPWH
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
QUALITY ASSURANCE SECTION
Negros Occidental 1st District Engineering Office
Matab-ang, Talisay City, Negros Occidental
INSPECTION REPORT
Name of Project : Construction of Flood Control Structure of Dapdap River (Both Stream) along Bacolod North Road (S00406NR)
Manapla, Negros Occidental (18GK0072)
QUANTITY
ITEM NO. DESCRIPTION REMARKS
Planned Actual
A.1.1(3) Construction of Field Office for the Engineer 1.00 l.s. 1.00 l.s. The indicated item of works
have been accomplished in
100(1) Clearing & Grubbing 0.35 ha 0.35 ha
accordance with the plans,
103(1)a Structure Excavation (Common Soil) 9,927.00 m³ 9,927.00 m³ specifications and program of
B.5 Project Billboard / Signboard 2.00 each 2.00 each works.
B.7 Occupational Safety & Health Program 5.67 month 5.67 month
Inspected by:
MARCELINO C. ESTALES
Project Engineer - DPWH
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
QUALITY ASSURANCE SECTION
Negros Occidental 1st District Engineering Office
Matab-ang, Talisay City, Negros Occidental
BILL NO. :
DATE :
TRIMLUV BUILDERS & SUPPLY
(Name of Contractor/Supplier)
TALISAY CITY, NEG. OCC.
(Address)
XXXXXXXXXXXXXXXXXXXXX
ARNEL P. TORREFRANCA
ENGINEER III
ffice
al
TOTAL AMOUNT
500.00
2,880.00
3,380.00
ered and/or supplies and
EL P. TORREFRANCA
ENGINEER III
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
QUALITY ASSURANCE SECTION
Negros Occidental 1st District Engineering Office
Matab-ang, Talisay City, Negros Occidental
PROJECT : Improvement of Multipurpose Building (Covered Court) Brgy. Makiling, Sagay City, Negros Occidental (17RB0027)
We hereby certify that we have conducted an inspection and verification on work accomplished on the
aforementioned project for the period March 23 - 31, 2018 ; We further certify that we have found out that the quality of
materials in the following items of work corresponding to the quantity accomplished conforms with the approved POW
Standard Specifications and Special provisions of the contract, viz.:
QUANTITY ACCOMPLISHED %
ITEM DESCRIPTION PROGRAMMED UNITS
THIS WEEK TOTAL TO DATE ACCOMPLISHMENT
PREPARED BY : CONCURRED BY :