Professional Documents
Culture Documents
CONTRACTOR PAGE
PS0 1 of 3
COMMENTS SHEET
Document Title
ORF PV FARM PROJECT COST ESTIMATION
Company Document Number and Revision
220802DJRGU0116 - EX-DE - 00
Contractor Document Number and Revision
Transmittal IN Number
IN-2208-00-PS0-ENI-U0069
Transmittal OUT Number
OUT-2208-ENI-PS0-00231
Transmittal OUT Date
26/01/2023
Approval Status Code
B - APPROVED WITH COMMENTS
Company Document Approver
Approver Engineering - Suryodipuro Andika Diwaji
Note: "COMPANY's approval of this document has to be deemed just as an authorization to proceed with the project
execution.
CONTRACTOR is aware that COMPANY's approval is not relieving CONTRACTOR from any of its responsibilities in the
performances required by the CONTRACT"
(*)
A APPROVED
B APPROVED WITH COMMENTS
C NOT APPROVED
D DEEMED APPROVED
Comments:
Civil Operation Make sure the cost of Civil works (excavation, cut & Has been added
backfill, concrete work, drainage, fencing, etc.) is included
in the "Project Installation" and "Preparation Work" costs.
- Cost of material
Basis of estimation calculation for material price refer to - Cost of fabrication
- Cost of mobilization
existing contract price and market survey with related - Cost of installation
work.
PROJECT FILE
Facility Improvement Project 220802DJRGU0116_EXDE00_8.zip
CONTRACTOR PAGE
PS0 2 of 3
Comment; We need clear explain in regard methodology Moreover, a 30% margin has
been incorporated as a
of cost estimation for this project; cost estimation is precautionary measure in the
event that the capital cost
calculated based on 2 categories; direct costs and in proves insufficient due to
unforeseen expenses.
direct costs and year of estimation.
Instrument &
Control
1. Please ensure that the cost of vendor support for 1. Noted
existing system modification (ICSS, MCC, etc.) are
considered here.
6. Works related to foundation and its related civil & 6. Has been added
structure works for PV power house and PV panels have
not been identified. Please confirm.
CONTRACTOR PAGE
PS0 3 of 3
Piping 1. Please add cost estimate for civil works, building, Noted
mechanical handling tools/equipment, etc.
PROJECT
ENGINEER 1 & 2
Please to have complete cost estimation on nest revision Noted
Contract No.
5000018744
Facility Sub Facility Name Scale Sheet of Sheets
Onshore Receiving Facility n.a. 1 of 8
Document Verification
Company
Checked Checked by Unit Signature Date
REVISION LIST
00 Issued for Review
01 Final Issue
HOLD LIST
Table of Content
1.0 INTRODUCTION .................................................................................................... 5
1.1 Project Background .................................................................................................... 5
1.2 Scope and purpose ...................................................................................................... 6
1.0 INTRODUCTION
1.1 Project Background
Eni Muara Bakau B.V. (Operator 55.0%) in joint venture with Neptune Energy (33.7%) and PT.
Saka Indonesia (11.3%) is developing the Jangkrik Complex Project (JKK) inclusive of Jangkrik
Main (JKK Main) and Jangkrik North East (JKNE Fields). The JKK Complex is located in the
Muara Bakau PSC permit area approximately 70 km off the coast of Makassar Strait, offshore
East Kalimantan. Water depths in Jangkrik Complex are ranging from 200 to 500m.
The subsea development consists of seven (7) wells at JKK Main field and four (4) wells at
JKNE field tied back to a spread moored FPU with full treatment facilities. Seven (7) subsea
wells of JKK Main field will be drilled from three (3) drilling centres named Drill Centre Cluster
1, Drill Centre Cluster 2 and Drill Centre Cluster 3. Production of these drilling centres will be
gathered by 3 manifolds named Manifold 1, Manifold 2 and Manifold 3. Two (2) of JKNE field
wells will be satellite wells, connected to an intermediate manifold named Manifold NE2. The
remaining two (2) wells will be drilled from a drilling centre named Drill Centre Cluster NE1,
where a manifold named Manifold NE1 will gather the production of these two wells.
The multiplexed electro hydraulic control system comprises main umbilical starting from the
FPU and terminating at respective Umbilical Termination Assembly (UTA). The UTAs are
connected to a Subsea Distribution Units (SDUs) by means of electro hydraulic flying leads.
The electro hydraulic flying leads will also connect the UTAs/SDUs to the subsea control
module (SCM) on the subsea wellheads/manifolds to control and monitor the subsea
wellheads/manifolds. The treated gas and condensate from FPU are then exported via 24inch
treated gas export pipeline and 4inch condensate export pipeline to shore at Sapi Landfall. An
onshore receiving facility (ORF) fiscal metering system for gas and condensates is located
approximately 4kms downstream of Sapi Landfall. Gas and condensates pipelines are then
tied-in to the existing East Kalimantan Pipeline Network. Final destination of Jangkrik treated
gas is to the Bontang LNG Plant and local market; and the final destination of Jangkrik
condensate is to the Senipah Plant.
Jangkrik Onshore Receiving Unit (ORF) introducing a renewable energy source (solar PV plant).
The electrical system on ORF is powered by two Gas Engine Generators (GEG) that supply
power to the electrical facilities of the plant during normal operating condition. Currently, one
GEG is running, while the other one in standby, according to sparing philosophy of 2 X 100%.
To reduce CO2 emission and as an energy efficiency effort, it is proposed to reduce or replace
the use of existing GEG with the new Solar PV farm for power generation source at ORF.
2.0 REFERENCE
No. Description Doc Number Rev
A. Project Documentation
B. ENI Documentation
[B1] RCM Approach 28014.ENG.MNU.STD 01
C Quotation Documentation
[C1] BOQ and Price_ 15 June 2023_034641_014743 - -
NO DESCRIPTION TOTAL
Civil Scope
PV Foundation
Soil Excavated 113,715 m3 IDR 109.700 IDR 12.474.536
Backfill Soil 77,250 m3 IDR 45.000 IDR 3.476.250
Dismantle Concrete 12,200 m3 IDR 241.400 IDR 2.945.080
fc = 15 MPa for lean concrete 5,415 m3 IDR 1.687.600 IDR 9.138.354
fc = 30 MPa for structural concrete 39,555 m3 IDR 3.517.400 IDR 139.130.757
Non-shrink grout fc = 35 Mpa 0,413 m3 IDR 7.661.500 IDR 3.164.200
Oily plywood panel 147,546 m2 IDR 309.200 IDR 45.621.223
D10 Fy = 420 MPa 0,684 ton IDR 21.200.000 IDR 14.500.800
D16 Fy = 420 MPa 4,761 ton IDR 21.200.000 IDR 100.933.200
Quantity
Mineral wool insulation Thickness 50mm density 100 kg/m³ 158,422 m2 IDR 104.167 IDR 16.502.344
Serrated bar grating Serrated 30x100 mm pitch 32x5 341,31 m2 IDR 1.018.519 IDR 347.630.556
Checkered plate Thickness 6 mm 11,021 m2 IDR 1.151.042 IDR 12.685.634
Vinyl floor 0.5mm Wood series 172x1210x5 67,918 m2 IDR 420.200 IDR 28.539.144
Removable Handrail Height 1200mm 10,488 m IDR 595.400 IDR 6.244.555
Fixed Handrail Height 1200mm 28,24 m IDR 595.400 IDR 16.814.096
Roof Sheet Galvalum 0,6 mm 69,108 m2 IDR 76.100 IDR 5.259.119
Equipment Door 1300 (W) x 2500 (H) 3 ea IDR 3.705.200 IDR 11.115.600
A325 Or Jis B1051 Equivalent (Hot Dip
14mm dia hole for M12 bolt and nuts for stairs 82 ea IDR 6.100 IDR 500.200
Galvanized
A325 Or Jis B1051 Equivalent (Hot Dip
Hex Bolt M12 for Ramp 24 ea IDR 6.100 IDR 146.400
Galvanized
PV Plant Slope Reinforcement
Section 1A-1B
Soil Boring, hole diameter 300mm 264 m IDR 125.000 IDR 33.000.000
fc = 15 MPa for lean concrete 1,29 m3 IDR 1.687.600 IDR 2.177.004
fc = 30 Mpa for structural concrete 28,981 m3 IDR 3.517.400 IDR 101.937.769
Oily plywood panel 41,76 m2 IDR 309.200 IDR 12.912.192
D10 Fy = 420 MPa 0,844 ton IDR 21.200.000 IDR 17.892.800
D16 Fy = 420 MPa 2,626 ton IDR 21.200.000 IDR 55.671.200
Gabion 659,52 m3 IDR 1.019.700 IDR 672.512.544
Section 2
Soil Boring, hole diameter 300mm 492 m IDR 125.000 IDR 61.500.000
fc = 15 MPa for lean concrete 2,46 m3 IDR 1.687.600 IDR 4.151.496
fc = 30 Mpa for structural concrete 54,457 m3 IDR 3.517.400 IDR 191.547.052
Oily plywood panel 79,2 m2 IDR 309.200 IDR 24.488.640
D10 Fy = 420 MPa 1,586 ton IDR 21.200.000 IDR 33.623.200
D16 Fy = 420 MPa 4,914 ton IDR 21.200.000 IDR 104.176.800
Section 3
Soil Boring, hole diameter 300mm 408 m IDR 125.000 IDR 51.000.000
fc = 15 MPa for lean concrete 2,07 m3 IDR 1.687.600 IDR 3.493.332
fc = 30 Mpa for structural concrete 45,4 m3 IDR 3.517.400 IDR 159.689.960
Oily plywood panel 66,72 m2 IDR 309.200 IDR 20.629.824
D10 Fy = 420 MPa 1,324 ton IDR 21.200.000 IDR 28.068.800
D16 Fy = 420 MPa 4,087 ton IDR 21.200.000 IDR 86.644.400
Gabion 288 m3 IDR 1.019.700 IDR 293.673.600
CIVIL TOTAL PRICE IDR 6.510.744.548
Electrical Material
4C +E x 185 mm2 13 roll(50m) IDR 78.999.000 IDR 1.026.987.000
4C +E x 150 mm2 2 roll(50m) IDR 63.999.000 IDR 127.998.000
4C +E x 70 mm2 3 roll(50m) IDR 30.999.000 IDR 92.997.000
4C +E x 50 mm2 2 roll(50m) IDR 21.999.000 IDR 43.998.000
4C +E x 16 mm2 1 roll(50m) IDR 8.299.000 IDR 8.299.000
0.6/1Kv Power Cable (Ep2), Xlpe Insulated
4C +E x 10 mm2 3 roll(50m) IDR 5.199.000 IDR 15.597.000
/Swa/ Black
3C x 2,5 mm2 1 roll(50m) IDR 2.499.000 IDR 2.499.000
2C +E x 2,5 mm2 3 roll(50m) IDR 2.499.000 IDR 7.497.000
2C x 120 mm2 2 roll(100m) IDR 119.999.000 IDR 239.998.000
2C x 95 mm2 1 roll(100m) IDR 96.999.000 IDR 96.999.000
2C x 70 mm2 7 roll(100m) IDR 70.999.000 IDR 496.993.000
2C +E x 2,5 mm2 6 roll(100m) IDR 2.834.999 IDR 17.009.994
0.6/1Kv Power Cable (Ep4), Mgt-Xlpe
2C x 35 mm2 80 m IDR 410.000 IDR 32.800.000
Insulated /Swa/Orange
2C x 4 mm2 88 m IDR 50.250 IDR 4.422.000
12C x 1,5 mm2 4 roll(50m) IDR 4.799.000 IDR 19.196.000
0.6/1Kv Control Cable (Ec1) Class 2 , Xlpe
2C x 1,5 mm2 5 roll(50m) IDR 2.799.000 IDR 13.995.000
Insulated /Swa/Black
10C x 2,5 mm2 4 roll(50m) IDR 7.500.000 IDR 30.000.000
Quantity
PVC Tee Conduit Dia 2" 4 1 pack (15pcs) IDR 229.000 IDR 916.000
Pvc Conduit And Accessories
PVC Elbow Conduit Dia 2", 1 pack
2 pack(18pcs) IDR 331.890 IDR 663.780
(18pcs)
PVC Conduit Clamp C/W Screw and
212 EA IDR 2.100 IDR 445.200
Washer
Sealing Compound, Non-Hardening And
(1 LB/0.5 KG) 17 EA IDR 50.000 IDR 850.000
Temp. With Stand Material
Quantity
450mm (W) 150mm (H) 450mm (R) 6 EA IDR 2.746.000 IDR 16.476.000
150 (W) 150mm (H) 150mm (R) 4 EA IDR 1.020.000 IDR 4.080.000
90 Degree Cable Ladder Elbow
300 (W) 100mm (H) 300mm (R) 3 EA IDR 1.383.000 IDR 4.149.000
450mm (W) 100mm (H) 450mm (R) 2 EA IDR 2.280.000 IDR 4.560.000
90 Degree Cable Ladder Elbow Inside
450mm (W) 150mm (H) 450mm (R) 3 EA IDR 3.133.000 IDR 9.399.000
Vertical Riser
90 Degree Cable Ladder Elbow Outside
450mm (W) 150mm (H) 450mm (R) 2 EA IDR 3.133.000 IDR 6.266.000
Vertical Riser
300mm (W1) 100mm (D) 300mm (R) 3 EA IDR 2.144.000 IDR 6.432.000
"T" BRANCH ELBOW
450mm (W1) 150mm (D) 450mm (R) 4 EA IDR 4.339.000 IDR 17.356.000
Nylon Insulation Pad 2mm THK. SIZE 75 x 40 1 (1mx10m) IDR 1.500.000 IDR 1.500.000
60W Street Lighting , 230 Vac, 1 Ph,50 Hz,
14 EA IDR 2.431.000 IDR 34.034.000
Min. 7800 Lumens
132W Street Light, 230 Vac, 1 Ph, 50 Hz,
Emergency light 9 EA IDR 13.000.000 IDR 117.000.000
Min. 12349 Lumens
109W Led Floodlight, 230 Vac, 1 Ph, 50 Hz,
18 EA IDR 8.545.890 IDR 153.826.020
Min. 16000 Lumens
113W Led Flooflight, 230 Vac, 1 Ph, 50 Hz,
Emergency light 11 EA IDR 27.374.616 IDR 301.120.776
Min. 15000 Lumens
2 X 18W, 230Vac, 1Ph, 50Hz, Min 2100
Complete with lampshade 9 unit IDR 387.390 IDR 3.486.510
Lumens
2 X 18W, 230Vac, 1Ph, 50Hz, Min 2100
Emergency light 5 EA IDR 730.000 IDR 3.650.000
Lumens
11W Exit Light, 230Vac, 1Ph, 50Hz Emergency light 6 EA IDR 1.804.000 IDR 10.824.000
Socket Outleet 16A, 230Vac, 1Ph, 2P+E,
5 EA IDR 271.500 IDR 1.357.500
50Hz
SOCKET OUTLEET 32A, 400VAC, 3PH,
2 EA IDR 271.500 IDR 543.000
3P+N+E, 50HZ
Welding Socket 63 A, 230Vac, 3Ph, 4P+E,
3 EA IDR 798.090 IDR 2.394.270
50Hz
Lighting Switch Single/ Switch / One Gang 6 EA IDR 125.000 IDR 750.000
Lighting Junction Box Suitable For Safe Area
33 EA IDR 1.241.000 IDR 40.953.000
(Industrial Type).
Indoor Lighting Junction Box (Industrial Type). 8 EA IDR 1.241.000 IDR 9.928.000
Mechanical
Air Conditioner Outdoor Unit Location (Accu) 14 kW (2) IDR 50.246.400 IDR 100.492.800
2 ea
Exhaust Fan 2 ea IDR 4.400.000 IDR 8.800.000
Fire Damper 300mm x 300mm 1 ea IDR 38.172.010 IDR 38.172.010
Fire Damper 200mm x 200mm 6 ea IDR 29.704.158 IDR 178.224.948
Non Return Damper 2 ea IDR 18.339.936 IDR 36.679.872
Manual Volume Damper 300mm x 300mm 1 ea IDR 3.862.692 IDR 3.862.692
Quantity
Temperature & Humidity Indicator Transmitter Safe Are IDR 7.753.940 IDR 15.507.880
2 ea
Temperature & Humidity Indicator Transmitter Ex-rated IDR 41.202.048 IDR 41.202.048
1 ea
Differential Pressure Transmitter 2 ea IDR 11.000.000 IDR 22.000.000
Differential Pressure Switches 1 ea IDR 15.507.764 IDR 15.507.764
Control Panel 1 ea IDR 50.246.400 IDR 50.246.400
Instrument Cable 2x1.5 mm2 (Cu/XLPE/SWA/PVC) 129,6 m IDR 58.000 IDR 7.516.800
Plate 2mm SS 316L Finish 2B 78,9 m2 IDR 4.480.000 IDR 353.472.000
L 50x50x5 SS 316L Finish 2B 121 m IDR 120.000 IDR 14.520.000
Insulation Mineral Wool 50mm 78,9 m2 IDR 208.334 IDR 16.437.553
A4 - M10 x 40 c/w spring and plate nuts SS 316L Finish 2B 413 ea IDR 46.800 IDR 19.328.400
Duct Penetration Sleeve Carbon Steel 4,8 m2 IDR 5.000.000 IDR 24.000.000
Insulation Mineral Wool 75mm 4,8 m2 IDR 458.334 IDR 2.200.003
M12 x 40 c/w spring and plate nuts SS 316L Finish 2B 2 ea IDR 61.840 IDR 123.680
Grounding Cable 1C x 35 mm2 12 m IDR 150.000 IDR 1.800.000
Cable lug 35 mm2 108 ea IDR 390.000 IDR 42.120.000
Adhesive 1 lot IDR 1.000.000 IDR 1.000.000
MECHANICAL TOTAL PRICE IDR 1.283.013.406
FABRICATION
A. Personnel Day Rate
Volume Duration
No. Description Qty Unit Qty Unit Unit Price Total Price
(A) (B) (C) (D) (E) (A)*(C)*(E)
SUB TOTAL PRICE PERSONAL & EQUIPMENT DAY RATE (A+B) IDR5.100.187.230
MOBILIZATION
Qty Duration Unit Price Total Price
No. Description Unit Unit
(A) (B) (C) (A)*(B)*(C)
SUB TOTAL PRICE PERSONAL & EQUIPMENT DAY RATE (A+B) IDR13.494.653.240