Professional Documents
Culture Documents
Revision History
Rev. Date Revision Details Prepared Checked Reviewed Approved
4 INSTALLATION PROCEDURES
5 SAFETY
Appendix 1 QUALITY CONTROL CHECK LIST AND CHECK SHEET
Appendix 2 INSPECTION & TEST PLAN
1. PURPOSE
The purpose of this method statement is to have a systematized work procedures that complies with the General
Standards and Rules and Regulations being implemented on project site to ensure the Quality of work that will be
made and Safeness of all persons that will be involved in doing such activities.
This method statement is prepared for the provision of Chilled Water Pump and Condenser Water Pump
of ................................Project to be undertaken by Italthai Engineering Co. Ltd.
2. SCOPE OF WORK
Title : Page 3 of 15
Document No. : Effective Date : Revision :
This method statement defies the delivery / handling, installation and Testing of Chilled Water Pump and
Condenser Water Pump for.........................Project. This ensures all the materials that will be used are in
compliance with the contract specifications and requirements approved by the Consultant.
3. MATERIALS
3.1 Chilled Water Pump and Condenser Water Pump shall conform to standard stated in the specification
and material submission for approved (See Appendix F for Water pump equipment schedule).
a) Chilled Water Pump and Condenser Water Pump shall be specified as shown on the approved shop
drawings and/or material approved.
b) Type of Chilled Water Pump and Condenser Water Pump shall be specified as shown on the approved
shop drawings and/or material approved. General classification type shall be as the following.
c) All Chilled Water Pump and Condenser Water Pump shall be factory made by one manufacturer if
necessary they may be ordered in semi-knock-down condition and the assembly may be done on site.
4. INSTALLATION PROCEDURES
Workmanship shall conform to standard states in specification. Method of work is as
follow installation chiller water pump and condenser water pump of air conditioning
work.
Title : Page 5 of 15
Document No. : Effective Date : Revision :
required. Incorrect alignment may cause rapid coupling and bearing failure.
- If a flow-measuring station (venture, orifice plate, or balancing valve) is located in the
pump discharge, allow 10 diameters of straight pipe between the pump discharge and
the flow station for measurement accuracy.
- If fine mesh screen is used in the strainer at initial start-up to remove residual
debris, replace it with normal size screen after commissioning to protect the pump
and minimize the suction pressure drop.
- Various accessories need to be studied as altimeters to conventional fittings, a
suction diffuser in the pump inlet is an alternate to an eccentric reducer and it
contains a strainer. Separate strainers can be specified with screen size. A
multipurpose valve in the pump discharge is an altimeter way to combine the
functions of shutoff, check, and balancing valves.
- Check direction of rotation pump is suction and discharge correct or not.
- The site engineer shall verify that all conduits equipment and material are conformed to the
specification before work commences.
- The site engineer or supervisor shall verify the construction drawing is good for construction.
- The site engineer shall ensure that type of equipment to be installed is in accordance with the
specification.
- In function inspected of equipment visual check by site engineer; QC engineer and MTL
representative.
- The type of equipment to be installed shall be in accordance with the design
5. SAFETY
Regularly checking in the inclusive working area shall be performed before working.
In the case of light failures during night shift work, barricades shall be equipped with suitable
light reflectors.
Sufficient lightings shall be setup when working at night shift and night shift workers must wear
reflectors.
Provide fire blankets and fire extinguishers in the welding area or the places that fire may
occur.
Provide safe and suitable access for mobile crane, dump-trucks, concrete mixer trucks, and
other heavy type vehicles.
Provide suitable ground and pads when setting up outriggers of the mobile crane that is
capable of supporting the crane load.
All lifting and rigging equipment shall be inspected and shall obtain valid certificate By ITE
inspector and witnessed by Sea Consult Engineering Co Ltd.
Title : Page 10 of 15
Document No. : Effective Date : Revision :
Lifting equipment, as well as its accessories such as slings, hoists, shackles, chain blocks, and
crane hook, shall be inspected before use.
Machines, equipment, and tools shall be certified by the qualified person and must be
inspected at the Jobsite to ensure that they are working properly and efficiently.
Periodic preventive maintenance shall be made to all machines and equipment.
Operators and drivers shall obtain a valid license or permit from certifying or affiliated
agencies. Only authorized drivers or operators will be allowed to operate machines or
equipment.
Flagman and Signalman/Bankman shall be trained and be certified to be authorized to manage
traffic flows and provide coordination/communication with truck drivers, mobile-crane, and
tower crane operators.
Housekeeping protocol in the construction site shall be consistently observed and be imposed
appropriately.
Disposal area shall be provided and proper disposals of construction waste shall be
consistently done following the housekeeping protocol and environmental conservation.
Dump-trucks transporting construction materials shall be covered with covering sheets to
prevent spills of materials such as loss soil, dust, muds, etc., in the public roads.
ATTACHMENT
I. Quality Control Checklist and Check Sheet
Title : Page 11 of 15
Document No. : Effective Date : Revision :
Title : Page 12 of 15
Document No. : Effective Date : Revision :
Title : Page 13 of 15
Document No. : Effective Date : Revision :
Title : Page 14 of 15
Document No. : Effective Date : Revision :
ATTACHMENT