Professional Documents
Culture Documents
CONDITION OF CONTRACT
Bill No. 1
Preliminaries
EARTHWORKS
SUPPLEMENTARY PREAMBLES
Nature of ground
Filling
Site clearance
EXCAVATIONS ETC
3 Reduced levels under floors n.e 200 thick 2,200 m3 29.07 63,954.00
Bill No. 2
Earthworks
5 Keeping excavations free of all water other than subterranean Item 5,000.00 5,000.00
water
FILLING ETC
7 Under floors, steps, pavings, etc up to 800 thick above grounds 5,749 m3 91.00 523,159.00
Compaction of surfaces
Bill No. 2
Earthworks
SOIL POISONING
CONCRETE, FORMWORK
AND REINFORCEMENT
SUPPLEMENTARY PREAMBLES
The Contractor shall submit for the approval of the Engineer the
name and project reference of the certified testing laboratory
the Contractor proposes to employ to carry out the tests.
Unless noted otherwise they shall maintain on site the following
pieces of apparatus which shall be kept in good condition
throughout the Contract and shall remain the property of the
Contractor:
(a) Apparatus for assessing workability in accordance with BS.
(b) Apparatus for making, curing, and weighing the concrete
test cubes required by this Specification, all in accordance with
BS.
Formwork
15MPa/20mm concrete
1 Surface blinding under footings and bases n.e 50mm thick 10 m3 376.22 3,762.20
25MPa/20mm concrete
REINFORCED CONCRETE
25MPa/19mm concrete
7 Aprons to surrounds 2000mm wide n.e 200mm thick 167 m3 514.80 85,971.60
8 Concrete cover slab on existing open drain 200mm thick 133 m 826.00 109,858.00
TEST CUBES
CONCRETE SUNDRIES
Bill No. 3
Concrete, Formwork & Reinforcement
REINFORCEMENT
Fabric reinforcement
WATERPROOFING
9 Under surface beds (Material to be supplied by client -fix only) 9,126 m2 0.50 4,563.00
10 10mm Wide x 20mm deep saw cut joints in top of concrete 456 m 28.65 13,064.40
slabs
SUPERSTRUCTURE
30MPa/20mm concrete
REINFORCEMENT
MASONRY
BLOCKWORK
BLOCKWORK SUNDRIES
DAMPPROOFING OF WALLS
PLASTERING
Bill No
1 Preliminaries 2 178,000.00
2 Earthworks 5 765,028.84
4 Superstructure 9 199,698.90
5 Plastering 24 76,440.00