You are on page 1of 11

Item No Quantity Unit Rate Amount

WAREHOUSE FOR MANOJE LAKHIANI


PROVISIONAL BILLS OF QUANTITIES
BILL NO. 1
PRELIMINARIES
BILLS OF QUANTITIES QUERIES

Any queries relating to these bills of quantities are to be


addressed to Krane Construction Ltd.:

Bill No. 1: Preliminaries

CONTRACT CONDITIONS AND PRELIMINARIES


The Conditions of the Contract comprise the "General
Conditions" which form part of the "Short Form of Contract",
First Edition 1999 (Green Book) published by FIDIC
Only those items which are priced in these Preliminaries, Bill
No. 1 of these Bills of Quantities, will be reviewed for
adjustment in the event of a Variation and any such adjustment
in each case shall be in accordance with the merits of each
priced item in relation to the Variation involved. Therefore it is a
condition of this Contract that these aforesaid Preliminaries are
priced according to the merits of each item.

Carried Forward GH¢


Bill No. 1
Preliminaries

Krane Construction Ltd. Page 1


PRICING OF PRELIMINARIES

The prices of these Preliminary items shall be allocated to one


or more of the three categories "F", "T" or "V" as the case may
be below such item, where:

F - An amount which is fixed

V - An amount which is based on the contract amount

T - An amount which is based on contract duration

CONDITION OF CONTRACT

1 Fixed Item 56,000.00

2 Time-related Item 90,000.00

3 Value-related Item 32,000.00

Carried Forward to Summary GH¢ 178,000.00

Bill No. 1
Preliminaries

Krane Construction Ltd. Page 2


BILL NO. 2

EARTHWORKS

SUPPLEMENTARY PREAMBLES

Nature of ground

The nature of the ground is assumed to be loose sandy


material, therefore "earth", but possibly interspersed with "hard
rock" or "soft rock".

Carting away of excavated material

Descriptions of carting away of excavated material shall be


deemed to include loading excavated material onto trucks
directly from the excavations or, alternatively, from stock piles
situated on the building site and taken off-site to a dump site
located by the Contractor.

Filling

Notwithstanding the reference to prescribed multiple handling in


clause 1 page 6 of the Standard System of Measuring Building
Work and the Engineers Earthwork Specification, prices for
filling and backfilling shall include for all selection and any
multiple handling of material

SITE CLEARANCE ETC

Site clearance

1 Clear site of all vegetation and debris 16,114 m2 1.00 16,114.00

2 Rip, scarify and recompact average 150mm thick layer of top


soil 16,114 m2 4.00 64,456.00

EXCAVATION, FILLING, ETC

EXCAVATIONS ETC

Excavation in earth not exceeding 2,000mm deep

3 Reduced levels under floors n.e 200 thick 2,200 m3 29.07 63,954.00

4 Column Pits 219 m3 32.36 7,086.84

Carried Forward GH¢ 151,610.84

Bill No. 2
Earthworks

Krane Construction Ltd. Page 3


Brought Forward 151,610.84

Extra over trench and hole excavations in earth for excavation


in

1 Soft rock (provisional) 16 m3 175.00 2,800.00

2 Hard rock (provisional) 5 m3 190.00 950.00

Extra over all excavations for carting away

3 Surplus material from excavations and/or stock piles on site, to


a dumping site to be located by the contractor 1,500 m3 15.00 22,500.00

Risk of collapse of excavations

4 Sides of Pit excavations exceeding 1,500mm deep 436 m2 18.00 7,848.00

Keeping excavations free of water

5 Keeping excavations free of all water other than subterranean Item 5,000.00 5,000.00
water

FILLING ETC

Earth filling obtained from the excavations and/or prescribed


stock piles on site, compacted to 95% Mod AASHTO density

6 Backfilling to Pits, etc 919 m3 15.00 13,785.00

Imported natural gravel "Laterite" material with a maximum


aggregate of 20mm supplied by the contractor, compacted to
95% Mod AASHTO density

7 Under floors, steps, pavings, etc up to 800 thick above grounds 5,749 m3 91.00 523,159.00

Compaction of surfaces

8 Compaction of ground surface under floors etc including


scarifying for a depth of 150mm, breaking down oversize
material, adding suitable material where necessary and
compacting to 93% Mod AASHTO density 9,126 m2 2.00 18,252.00

Carried Forward GH¢ 745,904.84

Bill No. 2
Earthworks

Krane Construction Ltd. Page 4


Brought Forward GH¢ 745,904.84

SOIL POISONING

Soil insecticide in accordance with SANS 5859

1 To bottoms and sides of Pits etc 436 m2 2.00 872.00

2 Under floors etc, including forming and poisoning shallow


furrows against foundation walls etc, filling in furrows and
ramming 9,126 m2 2.00 18,252.00

Carried Forward to Summary GH¢ 765,028.84


Bill No. 2
Earthworks

Krane Construction Ltd. Page 5


BILL NO. 3

CONCRETE, FORMWORK
AND REINFORCEMENT

SUPPLEMENTARY PREAMBLES

Before commencement of the Works, the Contractor shall


engage suitably qualified staff, to the Engineer's approval, for
carrying out tests required by this Specification.

The Contractor shall submit for the approval of the Engineer the
name and project reference of the certified testing laboratory
the Contractor proposes to employ to carry out the tests.
Unless noted otherwise they shall maintain on site the following
pieces of apparatus which shall be kept in good condition
throughout the Contract and shall remain the property of the
Contractor:
(a) Apparatus for assessing workability in accordance with BS.
(b) Apparatus for making, curing, and weighing the concrete
test cubes required by this Specification, all in accordance with
BS.

Formwork

Descriptions of formwork shall be deemed to include use and


waste only (except where described as "left in" or "permanent"),
for fitting together in the required forms, wedging, plumbing and
fixing to true angles and surfaces as necessary to ensure easy
release during stripping and for reconditioning as necessary
before re-use. The vertical strutting shall be carried down to
such construction as is sufficiently strong to afford the required
support without damage and shall remain in position until the
newly constructed work is able to support itself.

Carried Forward GH¢ -


Bill No. 3
Concrete, Formwork & Reinforcement

Krane Construction Ltd. Page 6


Brought Forward GH¢ -

UNREINFORCED CONCRETE CAST AGAINST


EXCAVATED SURFACES

15MPa/20mm concrete

1 Surface blinding under footings and bases n.e 50mm thick 10 m3 376.22 3,762.20

REINFORCED CONCRETE CAST AGAINST


EXCAVATED SURFACES

25MPa/20mm concrete

2 Bases 65 m3 514.80 33,462.00

4 800 x 600mm column stubbs 18 m3 514.80 9,266.40

5 Edge beams n.e 200 x 600mm deep 50 m3 514.80 25,740.00

REINFORCED CONCRETE

25MPa/19mm concrete

6 Surface beds cast in panels 200mm thick 1,916 m3 514.80 986,356.80

7 Aprons to surrounds 2000mm wide n.e 200mm thick 167 m3 514.80 85,971.60

8 Concrete cover slab on existing open drain 200mm thick 133 m 826.00 109,858.00

TEST CUBES

9 Making and testing 150 x 150 x 150mm concrete strength test


cubes 50 No 60.00 3,000.00

CONCRETE SUNDRIES

Finishing top surfaces of concrete smooth with a power trowel

10 Surface beds, slabs, etc 9,126 m2 3.00 27,378.00

Carried Forward GH¢ 1,284,795.00

Bill No. 3
Concrete, Formwork & Reinforcement

Krane Construction Ltd. Page 7


Brought Forward GH¢ 1,284,795.00

35MPa non-shrink grout

1 Bedding approximately 25mm thick under 600 x 800mm base


plate including chamfered edges all round 55 No 8.00 440.00

ROUGH FORMWORK (DEGREE OF ACCURACY III)

Rough formwork to sides

2 Rectangular columns 99 m2 38.33 3,794.67

3 Edge Beam 468 m2 38.33 17,938.44

4 Edges,of bes not exceeding 300mm high or 390 m 8.10 3,159.00

REINFORCEMENT

High tensile steel reinforcement to structural concrete work

5 20mm diameter bars 5 t 4,800.00 22,080.00

6 16mm diameter bars 3 t 4,800.00 15,840.00

7 10mm diameter bars 1 t 4,800.00 6,720.00

Fabric reinforcement

8 Type A393 fabric reinforcement in concrete surface beds,


slabs, in both ways 9,126 m2 46.17 421,347.42

WATERPROOFING

DAMPPROOFING OF WALLS AND FLOORS

One layer of 250 micron "Consol Plastics


waterproof sheeting sealed at laps

9 Under surface beds (Material to be supplied by client -fix only) 9,126 m2 0.50 4,563.00

MOVEMENT JOINTS ETC

Isolation joint consisting of a 140 x 10mm thick Polystyrene


board covered with a 10 x 10mm thick poured Flexseal
Elastometric joint sealant

10 10mm Wide x 20mm deep saw cut joints in top of concrete 456 m 28.65 13,064.40
slabs

Bill No. 3 Carried Forward to Summary GH¢ 1,793,741.93


Subsructure Concrete, Formwork & Reinforcement

Krane Construction Ltd. Page 8


BILL NO. 4

SUPERSTRUCTURE

REINFORCED CONCRETE CAST AGAINST FORMWORK

30MPa/20mm concrete

1 Column stiffeners withen perimeter of blockwall 20 m3 561.00 11,220.00

2 Tie Beam on top of perimeter blockwork 25 m3 561.00 14,025.00

ROUGH FORMWORK (DEGREE OF ACCURACY III)

Rough formwork to sides

3 Rectangular columns 385 m2 38.33 14,757.05

4 Tie Beam on top of perimeter blockwork 245 m2 38.33 9,390.85

REINFORCEMENT

High tensile steel reinforcement to structural concrete work

5 14mm diameter bars in columns and Tie Beam 4 t 4,800.00 20,640.00

5 10mm diameter bars in columns and Tie Beam 1 t 4,800.00 7,056.00

MASONRY

BLOCKWORK

Blockwork of blocks with compressive strength of not less than


5 MPa, in class II mortar

6 150mm Walls 1,433 m2 80.00 114,640.00

BLOCKWORK SUNDRIES

3 150mm Wide reinforcement built in horizontally 390 m 6.00 2,340.00

Joint forming material in movement joints

4 12mm Bitumen impregnated fibre board built in vertically


through block walls 32 m2 60.00 1,920.00

Wall bonding ties

5 70mm Wide "Mentis Mentex 130" expanded metal wall bonding


tie 700mm girth built horizontally into blockwork at one end and
welded to structural steel (43no.) 43 No 10.00 430.00

DAMPPROOFING OF WALLS

One layer of 375 micron "Consol Plastics Brikgrip DPC"


embossed damp proof course

In walls 82 m2 40.00 3,280.00

Bill No. 4 Carried Forward to Summary GH¢ 199,698.90


Superstructure

Krane Construction Ltd. Page 9


BILL NO. 5

PLASTERING

One coat cement plaster on blockwork

1 On walls 2,730 m2 28.00 76,440.00

Carried Forward to Summary GH¢ 76,440.00


Bill No. 5
Plastering

Krane Construction Ltd. Page 10


FINAL SUMMARY Page No Amount

Bill No

1 Preliminaries 2 178,000.00

2 Earthworks 5 765,028.84

3 Concrete, Formwork & Reinforcement 8 1,793,741.93

4 Superstructure 9 199,698.90

5 Plastering 24 76,440.00

SUB TOTAL GH¢ 3,012,909.67

ADD: CONTINGENCIES 5% GH¢ 150,645.48

ADD: VALUE ADDED TAX (17.50%) TO BE DISCUSSED GH¢ 553,622.15

TOTAL ESTIMATE INCLUDING VAT GH¢ 3,717,177.31

Krane Construction Ltd. Page 11