MACHINERY/EQUIPMENT SCHEDULE (KAROORA MASHINARII HOJIICHAF BARBACHISAAN)

PROJECT:BOE UNTA-ROBALE URRAP ROAD FINISHING WORK PROJECT Project Amount (Birr) 10,522,046.44
CLIENT:OROMIA ROAD AND LOGISTICS BUREAU(ANA SORA WOREDA ROADS AND LOGISTICS BUREAU
Project Duration 120 Cal. Days
Site Location: Guji Zone, Ana Sora Wereda Commencement Date 18/3/2024
Contractor: Debenu Road & Bridge Construction Small Enterprise Completion Date 30/8/2024
Source of Required Year 2024 G.C
S/N Type of Machinery/ Equipments
Equipement No. Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1 Concrete Mixer 350 lit Rental 4 1 1 1 1
2 Vibrator Rental 4 1 1 1 1
3 Mixer Rental 1 1 1 1
4 Vibrator Rental 4 1 1 1 1
5 Dump Truck Rental 2 1 1 1 1
6 Loader Rental 1 1 1 1 1 1
7 Plate Compactor Rental 1 1 1 1 1 1
8 Greador Rental 4 1 1 1
9 Roller 10 Ton Rental 6 2 2 2
10 Water Truck 1200lt Rental 6 2 2 2
11 Excavator Rental 6 2 2 2
12 Small tools Own 60 10 10 10 10 10
13 Hammers Own 7 1 1 1 1 1
14 Wrench Own 20 5 5 5
15 Bar Cutter Own 4 1 1
16 Shovels Own 4 1 1 1 1 1
17 50m steel meter Own 4 1 1 1 1 1
18 Garden Pick Own 3 1 1 1
19 Saw Own 4 1 1 1 1 1
20 Pipe Own 2 2 2 2
21 Cutter Own 3 1 1 1

Note:- We describe that how we get the required equipments and machinery by method of Rental and Owner,