ELIAZER CONSTRUCTION PLC

Project : Construction of Public and Communal Toilets and Showers


Client : DEBRE BIRHAN WATER SUPPLY AND SEWARAGE SERVICE

Manpower Schedule
2023
NO. PERSON NAME Required
Month1 Month2 Month3 Month4 Month5
1 Project Manager 1 1 1 1 1 1
2 Site Engineer 1 1 1 1 1 1
3 Superintndant 1 1 1 1 1 1
4 Surveyor 1 1 1 1 1 1
5 Forman 1 1 1 1 1 1
7 Electritian 1 1 1 1
8 Plumber 1 1 1 1
9 Masons and Carpenters 5 2 5 5 5 3
10
ELIAZER CONSTRUCTION PLC
Project : Construction of Public and Communal Toilets and Showers
Client : DEBRE BIRHAN WATER SUPPLY AND SEWARAGE SERVICE

Equipment and Machinary Schedule

2023
NO. TASK NAME Unit Required
Month1 Month2 Month3 Month4 Month5
1 Excavator/Backhoe Loader No 1 1 1 1 1 1

2 Dump Truck No 1 1 1 1 1 1

3 Four Wheel Drive Single Cabin Pickup No 1 1 1 1 1 1

4 Concrete Mixer No 2 1 2 2 2 2

5 Concrete Vibrator No 2 1 2 2 2 2
ELIAZER CONSTRUCTION PLC
Project : Construction of Public and Communal Toilets and Showers
Client : DEBRE BIRHAN WATER SUPPLY AND SEWARAGE SERVICE

Construction Materials Schedule

2023
NO. Description Unit Total Required
Month1 Month2 Month3 Month4 Month5
Construction Materials
1 Cement Qntl 2000 200 300 600 600
2 Sand m3 250 43 65 130 130
3 Gravel 02 m3 450 22 32 65 65
4 Reinforcement bar
8mm kg 2298.8 229.88 574.69 575 575 345
10mm kg 1113.8 111.38 278.44 278 278 167
12mm kg 1717.9 171.79 429.48 429 429 258
14mm kg 2034.2 203.42 508.55 509 509 305
16mm kg 467.70 46.77 116.93 117 117 70