You are on page 1of 1

MAN POWER SCHEDULE (KAROORAA HUMNA NAMA HOJIICHAF BARBACHISAAN)

PROJECT:BOE UNTA-ROBALE URRAP ROAD FINISHING WORK PROJECT Project Cost (Birr) 10,522,046.44
CLIENT:OROMIA ROAD AND LOGISTICS BUREAU(ANA SORA WOREDA ROADS AND LOGISTICS BUREAU Project Duration 120 Cal. Days
Site Location: Guji Zone, Ana Sora Wereda Commencement Date 18/3/2024
Contractor: Debenu Road & Bridge Construction Small Enterprise Completion Date 30/8/2024
Type of Requiered Project Year 2024 G.C
S/N Man Power Type Assigned Person
Employement No. Mar Apr May Jun Jul Aug Sep Oct Nov Dec
A. Permanent Personnel Member
1 Project Manager Ararse Mintasa Permanent 1 1 1 1 1 1
2 Site Engineer Adugna Wako Permanent 1 1 1 1 1 1
3 Surveyour Haleka Robe Permanent 1 1 1 1 1 1
4 Forman Abinet Geleta Permanent 1 1 1 1 1 1
5 Accountant Hawa Adem Permanent 1 1 1 1 1 1
6 Administrator/Management Kemal Nesh Dagne Permanent 1 1 1 1 1 1
B. Temporary Manpower
1 Daily Laborer Temporary 60 20 10 10 10 10
2 Mason Temporary 8 4 4 4 4
3 Assistant mason Temporary 4 2 2 2 2
4 Bar-bender Temporary 8 2 2 2 2
5 Assistant bar-bender Temporary 6 2 2 2 2
6 Carpenter Temporary 8 2 2 2 2
7 Assistant carpenter Temporary 4 1 1 1 1
8 Gang leader Temporary 8 2 2 2
9 Daily laborer Temporary 4 2 2 2
10 Mixer operator Temporary 4 2 2 2
11 Dump Truck Driver Temporary 4 2 2
12 Loader Operator Temporary 4 2 2
13 Vibrator Operator Temporary 2 1 1 1
14 Excavator Operator Temporary 6 2 2 2
15 Greador Operator Temporary 3 1 1 1
16 Water Truck Driver Temporary 6 2 2 2
17 Roller Operator Temporary 3 2 2 2
18 Metal Welder Temporary 4 2 2 2
19 Ass. metal welder Temporary 10 2 2 2 2 2
20 Store Keeper Temporary 2 2 2 2 2 2

Note:- We describe that our employement method of the proposed personnel and man power which is Temporary and Permanent as mention in the above table.