PROJECT :
CLIENT :
CONTRACTOR :
LOCATION :
AREA DESCRIPTION :
CONTACT PERSON : TITLE:
TESTING INCHARGE NAME:
Test Procedure
Pretest Checklist
Item No.
Activity
Yes
No
REMARKS
1 Check the room to ensure that the size of the room as per final design.
2 Is there any suspended ceiling. Either open few ceiling tile to calculat
e the ceiling leakage. If Main Room leakage to be measured separately then put p
lastic on grills and opening.
3 Are all suspended ceiling tiles in place?
Dampers installed on all external HVAC ducts.
4 Can they be shut for the Room Integrity test?
5 Dampers installed on fresh air inlet ducts.
Can they be shut for the door Room Integrity Test?
6 Check for any leaks. All the leaks must be sealed.
7 5 Minutes HVAC Shut down can be arranged?
8 Maximum Number of door-fan blowers needed?
9 SET UP ROOM FOR DOOR-FAN TEST.
a) Remove temporary air sealing or note who has assured the permanent seal.
b) Close all doors in the protected room boundary.
c) Open all doors within enclosure.
d) Open doors in adjacent rooms and around outside of the enclosure.
e) Shut down the air-conditioning if possible.
f) Close all dampers that would normally be closed during the retention tim
e.
Room Data
1. Area Description:
2. Elevation:
3. Net protected room volume:
= Floor Area X Max. Protected Height
= Total Volume m3
4. Room Operating Temperature: °
C
5. Maximum Protected Height:
a) Above Ceiling: M
b) Main Floor : M
c) Raised Floor: M
6. Minimum agent retention time:
Minutes
7. Agent type:
8. Agent quantity:
kg.
9. Equipment Height: M
10. Sketch of the room:
NAME:
DATE:
DEPT:
SIGN:
NAME:
DATE:
DEPT:
SIGN: