S/N Item Description per PAC UOM Qty- Revised Unit Price Total Cost % Completed Cost Completed
approval
1 Civil and Mechanical Works CW
1.2 Site Mobilization for Greenfield CW site 1 ₱16,500.00 ₱16,500.00 50% ₱8,250.00
Total ₱16,500.00 50% ₱8,250.00
2 Tower Foundation CW
2.1 Excavation Works - Normal soil without water table-Manual CW cu. M 0 ₱280.00 Done by previuos subcon
3.1 Excavation Works - Normal soil without water table-Manual CW cu. M 4 ₱280.00 ₱1,120.00
3.5 Back filling works & compaction works for DG Pad CW cu. M 4 ₱275.00 ₱1,100.00
Total ₱29,403.00
4 Equipment Pad(4mX2m) CW
4.1 Excavation Works - Normal soil without water table-Manual CW cu. M 4.41 ₱280.00 ₱1,234.80 100% ₱1,234.80
4.2 Lean Concrete CW cu. M 0.33 ₱2,400.00 ₱792.00 100% ₱792.00
4.3 Rebar Works CW kg 242 ₱62.50 ₱15,125.00 80% ₱12,100.00
4.4 Concreting Works for Equipment Pad Foundation CW cu. M 2.96 ₱4,800.00 ₱14,184.00 80% ₱11,347.20
4.5 Back filling works & compaction works for Equipment Pad CW cu. M 4.41 ₱275.00 ₱1,212.75 70% ₱848.93
Total ₱32,548.55 81% ₱26,322.93
5 Other Civil Works CW
5.1 Service Entrance Pedestal Works CW lot 1 ₱13,565.00 ₱13,565.00 90% ₱12,208.50
5.2 Supply, Level & compaction of 100mm thick gravel CW m2 221 ₱850.00 ₱187,850.00 0%
Supply & Install pad lock with 3 keys (Yale) - 2 sets 20mm and 1 set 40mm pad
5.3
lock
CW set 1 ₱1,150.00 ₱1,150.00 0%
5.4 Form Works CW m2 72.07 ₱454.00 ₱32,719.78 80% ₱26,175.82
5.5 Supply level & compaction of imported soil CW cu. M 72 ₱414.40 ₱29,836.80 0%
5.6 Peri meter full CHB fence 2.7m high with top portion having barbed wire CW m 57 ₱3,596.43 ₱204,996.51 50% ₱102,498.26
5.7 Supply & install Steel Gate 3m width with all accessories CW set 1 ₱21,450.00 ₱21,450.00 0%
5.8
GF Tower Erection works (40m < Tower <= 60m 3-Legged SST
CW lot 1 ₱105,000.00 ₱105,000.00
90% ₱94,500.00
Tower) lot 1.00
6.5
Supply & install underground power cable-2-38mm 2THHN & 1-
CW m 12 ₱930.00 ₱11,160.00
85% ₱9,486.00
14 mm2, in 40mm diameter PVC Pipe
6.9
Supply & install all electrical accessories for service Entrance
CW set 1 ₱16,327.30 ₱16,327.30
85% ₱13,878.21
Pedestal set 1.00
6.1 Supply & install KWH meter and panel with security grill CW set 1 ₱16,345.00 ₱16,345.00 85% ₱13,893.25
6.11 Supply & install ACPDB panel with frame stand CW set 1 ₱31,000.00 ₱31,000.00 85% ₱26,350.00
6.12 Supply & install Perimeter Light and all accessories CW set 3 ₱6,505.00 ₱19,515.00 50% ₱9,757.50
Supply & install 500mm x 500mm x 500mm Grounding Test Pit / handhole
6.13
complete with steel plate cover with handle
CW set 2 ₱11,015.55 ₱22,031.10 85% ₱18,726.44
6.14
Supply & install Grounding Bus Bar (32 holes, 340mm x 100mm x
CW set 4 ₱6,175.00 ₱24,700.00
85% ₱20,995.00
6mm)
6.15 TVSS 100 KA, Single Phase,230V CW set 1 ₱24,337.64 ₱24,337.64 85% ₱20,686.99
6.16 Supply & install 16mm diameter x 3 copper clad ground rod CW pcs 5 ₱1,965.55 ₱9,827.75 85% ₱8,353.59
6.17
Supply & install power cables (0B Light) :-2-3.5mm 2 THHN & 1-
CW m 45 ₱523.73 ₱23,567.85
85% ₱20,032.67
3.5mm 2, in 15mm diameter IMC Pipe
6.18 Supply & install 50mm2 bare copper wire in 20mme pvc pipe CW m 12.1 ₱1,258.00 ₱15,221.80 85% ₱12,938.53
Supply and Install. Of 70 sq mm Copper flexi cable(Red and 85% ₱12,831.60
6.19 CW m 12 ₱1,258.00 ₱15,096.00
Black)
Dewatering
CW-
days 1 ₱1,550.00 ₱1,550.00
Additional Height ODU Pad 100% price not stated
Variation CEF 70% price not stated
CW-
Sub Total for Variation Works Total ₱1,550.00
Variation