Sr. No Particulars No
Deducti
Content Unit
Total of
L (Ft) B (Ft) H (Ft) on Each
1 Site Cleaning 1 77.00 30.00 2310.00 Ft²
Site Cleaning 2310.00 Ft² 2310.00
2 Levelling or Surveying
1 71.00 24.00 1704.00 Ft²
Levelling or Surveying 1704.00 Ft² 1704.00
3 Earthwork Excavation
3.1 Footing
F1 24 6.00 6.00 6.00 5184.00 Ft³
5184.00 Ft³ 5184.00
3.2 Retaining Wall
X-direction
Line 1,2&3 3 29.00 2.50 3.00 652.50 Ft³
Y-direction
Line A,B,C,D,E,F&G 7 6.00 2.50 3.00 315.00 Ft³
Line H 1 6.00 2.50 3.00 45.00 Ft³
1012.50 Ft³ 1012.50
Earthwork Excavation Ft³ 6196.50
Page1
DETAIL OF MEASUREMENT
Measurments
Sr. No Particulars No
Deducti
Content Unit
Total of
L (Ft) B (Ft) H (Ft) on Each
Y-direction
Line A,B,C,D,E,F&G 7 11 0.75 3.5 202.125 Ft³
Line H 1 11.25 0.75 3.5 29.53125 Ft³
Total of Brick Work (1:3) (RW) 736.64 Ft³ 736.64
8 Footing
8.1 1:2:4 Concrete Work
F1 24 6.00 6.00 1.00 864.00 Ft³
1:2:4 Concrete Work (Footing) 864.00 Ft³ 864.00
8.2 Formwork
F1 24 6.00 6.00 1.00 576.00 Ft²
Formwork (Footing) 576.00 Ft² 576.00
9 Column
9.1 1:2:4 Concrete Work
Footing to Plinth Beam Level Column
C1 (9''x9'') 3 0.75 0.75 4.50 7.59 Ft³
C2 (12''x12'') 21 1.00 1.00 4.50 94.50 Ft³
1:2:4 Conc; Work (Footing to Plinth Beam 102.09 Ft³ 102.09
9.2 Formwork
Footing to Plinth Beam Level Column
C1 (9''x9'') 3 0.75 0.75 4.50 40.50 Ft²
C2 (12''x12'') 21 1.00 1.00 4.50 378.00 Ft²
Formwork (Footing to Plinth Beam C1) 418.50 Ft² 418.50
10 Beam
10.1 1:2:4 Concrete Work
Plinth Beam
X-direction
Line 1,2&3 PB1 3 64.125 0.75 1.00 144.28 Ft³
Y-direction
Line A,B,C,D,E,F&G PB1 7 11 0.75 1.00 57.75 Ft³
Line H PB1 1 11.25 0.75 1.00 8.44 Ft³
1:2:4 Concrete Work (Plinth Beam) 210.47 Ft³ 210.47
10.2 Formwork
Plinth Beam
X-direction
Line 1,2&3 PB1 3 64.125 0.75 1.00 384.75 Ft³
Y-direction
Line A,B,C,D,E,F&G PB1 7 11 0.75 1.00 154.00 Ft³
Line H PB1 1 11.25 0.75 1.00 22.50 Ft³
Formwork (Plinth Beam) 561.25 Ft² 561.25
10.3 Steel Work
Plinth Beam
X-direction
Line 1,2&3 PB1 16mm 6mm
PB1 (9''x12'') 3 64.125 0.75 1
Top Bar (3-16mmØ) 9 65.38 588.38 Rft
Bottom Bar (3-16mmØ) 9 64.88 583.88 Rft
Stirrups (6mmØ @ 6''c/c) 388 3.00 Rft 1163.25
Line H PB1
PB2 (9''x12'') 1 11.00 0.75 1.00
Top Bar (3-16mmØ) 3 12.25 36.75 Rft
Bottom Bar (3-16mmØ) 3 11.75 35.25 Rft
Stirrups (6mmØ @ 6''c/c) 23 3.00 Rft 69.00
Page3
DETAIL OF MEASUREMENT
Measurments
Sr. No Particulars No
Deducti
Content Unit
Total of
L (Ft) B (Ft) H (Ft) on Each
Page4
BUILDER'S ESTIMATE
Sr. No
Particular Quantity Unit Rate Per Amount
page -7
216878
page -8
Abstract of cost
Item Particulars Qty Unit Rate Per Total Amount
7 Brick Work (1:3) (Retaining Wal 736.64 Cft 2775.06 Cft 2,044,220
10 Steel Work
10.1 Footing, Column & Plinth Beam 3.44 Ton 769000.00 Ton 2,641,538
B Labours
1 Carpenter 79.27 Nos 10000 Nos 792,700.00
2 Mason 68.91 Nos 10000 Nos 689,109.38
3 Workers 327.04 Nos 7500 Nos 2,452,818.75
4 Machine Driver 5.88 Nos 8500 Nos 50,003.91
5 Steel Work 3.44 Ton 95000 Ton 326,327.88
6 Earth Filling Work (50%) 3098.25 Ft³ 70 Ft³ 216,877.50
Total Labours Charges 4,527,837
page - 11
10363071
4527837
14890908
page - 12
SUB STRUCTURE WORK ( FOUNDATION)
SUMMUARY
B Formwork
C1(9''x9'') 1 0.75 0.75 10.00 30.00 Ft²
C2(12''x12'') 2 1.00 1.00 10.00 80.00 Ft²
Formwork 110.00 Ft² 110.00
C Steel Work
C1(9''x9'') 3 0.75 0.75 10.00
Main Bar(16mm x 4 nos) 12 12.13 145.60 Rft
Tie Bar(6mm@6''c/c) 63 2.50 157.50 Rft
B Formwork
C1(9''x9'') 3 0.75 0.75 9.00 81.00 Ft²
C2(12''x12'') 21 1.00 1.00 9.00 756.00 Ft²
Formwork 837.00 Ft² 837.00
C Steel Work
C1(9''x9'') 3 0.75 0.75 9.00
Main Bar(16mm x 4 nos) 12 9.48 113.76 Rft
Tie Bar(6mm@6''c/c) 57 2.50 142.50 Rft
14
(Super Sturcture)
DETAIL OF MEASUREMENT
Measurments
Sr. No
Total of
Particulars No Ded; Content Unit
L (Ft) B (Ft) H (Ft) Each
A 1:2:4 Concrete Work
C1(9''x9'') 40 0.75 0.75 9.00 202.50 Ft³
1:2:4 Conc; Work 202.50 Ft³ 202.50
B Formwork
C1(9''x9'') 40 0.75 0.75 9.00 1080.00 Ft²
Formwork 1080.00 Ft² 1080.00
C Steel Work
C1(9''x9'') 40 0.75 0.75 9.00
Main Bar(16mm x 4 nos) 160 9.48 1516.80 Rft
Tie Bar(6mm@6''c/c) 760 2.50 1900.00 Rft
Steel work 16mmØ Ton 0.76
6mmØ Ton 0.14
2 Beam
2.1 Floor Beam
A 1:2:4 Concrete Work
X-direction
Line 1,2&3 PB1
FB2 (9''x12'') 3 64.13 0.75 0.67 96.24 Ft³
Y-direction
Line A,B,C,D,E,F&G PB1
FB3 (9''x12'') 7 11.00 0.75 0.67 38.52 Ft³
Line H PB1
FB2 (9''x12'') 1 11.25 0.75 0.67 5.63 Ft³
1:2:4 Concrete Work (Floor Beam) 140.38 Ft³ 140.38
B Formwork
X-direction
Line 1,2&3 PB1
FB2 (9''x12'') 3 64.13 0.75 0.67 256.63 Ft²
Y-direction
Line A,B,C,D,E,F&G PB1
FB3 (9''x12'') 7 11.00 0.75 0.67 102.72 Ft²
Line H PB1
FB2 (9''x12'') 3 11.25 0.75 0.67 45.02 Ft²
Formwork (Floor Beam) 404.37 Ft² 404.37
C Steel Work
X-direction
Line 1,2&3 PB1 16mm 6mm
FB2 (9''x12'') 3 64.13 0.75 0.67
Top Bar (3-16mmØ) 9 64.71 582.38 Rft
Bottom Bar (3-16mmØ) 9 64.88 583.88 Rft
15
(Super Sturcture)
DETAIL OF MEASUREMENT
Measurments
Sr. No
Total of
Particulars No Ded; Content Unit
L (Ft) B (Ft) H (Ft) Each
Stirrups (6mmØ @ 6''c/c) 388 2.33 Rft 905.01
Y-direction
Line A,B,C,D,E,F&G PB1
FB3 (9''x12'') 7 11.00 0.75 0.92
Top Bar (3-16mmØ) 21 14.22 298.56 Rft
Bottom Bar (3-16mmØ) 21 13.88 291.55 Rft
Stirrups (6mmØ @ 6''c/c) 161 2.83 Rft 456.27
Line H PB1
FB2 (9''x12'') 1 11.25 0.75 0.67
Top Bar (3-16mmØ) 3 11.83 35.50 Rft
Bottom Bar (3-16mmØ) 3 12.00 36.00 Rft
Stirrups (6mmØ @ 6''c/c) 24 2.33 Rft 54.85
Y-direction
Line A,B,C,D,E,F&G PB1
FB3 (9''x12'') 7 11.00 0.75 0.67 38.52 Ft³
Line H PB1
FB2 (9''x12'') 1 11.25 0.75 0.67 5.63 Ft³
1:2:4 Concrete Work (Floor Beam) 140.38 Ft³ 140.38
B Formwork
X-direction
Line 1,2&3 PB1
FB2 (9''x12'') 3 64.13 0.75 0.67 256.63 Ft²
Y-direction
Line A,B,C,D,E,F&G PB1
FB3 (9''x12'') 7 11.00 0.75 0.67 102.72 Ft²
Line H PB1
FB2 (9''x12'') 3 11.25 0.75 0.67 45.02 Ft²
Formwork (Floor Beam) 404.37 Ft² 404.37
D Steel Work
X-direction
Line 1,2&3 PB1 16mm 6mm
16
(Super Sturcture)
DETAIL OF MEASUREMENT
Measurments
Sr. No
Total of
Particulars No Ded; Content Unit
L (Ft) B (Ft) H (Ft) Each
FB2 (9''x12'') 3 64.13 0.75 0.67
Top Bar (3-16mmØ) 9 64.71 582.38 Rft
Bottom Bar (3-16mmØ) 9 64.88 583.88 Rft
Stirrups (6mmØ @ 6''c/c) 388 2.33 Rft 905.01
Y-direction
Line A,B,C,D,E,F&G PB1
FB3 (9''x12'') 7 11.00 0.75 0.92
Top Bar (3-16mmØ) 21 14.22 298.56 Rft
Bottom Bar (3-16mmØ) 21 13.88 291.55 Rft
Stirrups (6mmØ @ 6''c/c) 161 2.83 Rft 456.27
Line H PB1
FB2 (9''x12'') 1 11.25 0.75 0.67
Top Bar (3-16mmØ) 3 11.83 35.50 Rft
Bottom Bar (3-16mmØ) 3 12.00 36.00 Rft
Stirrups (6mmØ @ 6''c/c) 24 2.33 Rft 54.85
Y-direction
Line A,B,C,D,E,F&G PB1
FB3 (9''x12'') 7 11.00 0.75 0.67 38.52 Ft³
Line H PB1
FB2 (9''x12'') 1 11.25 0.75 0.67 5.63 Ft³
1:2:4 Concrete Work 140.38 Ft³ 140.38
B Formwork
X-direction
Line 1,2&3 PB1
FB2 (9''x12'') 3 64.13 0.75 0.67 256.63 Ft²
Y-direction
Line A,B,C,D,E,F&G PB1
FB3 (9''x12'') 7 11.00 0.75 0.67 102.72 Ft²
Line H PB1
FB2 (9''x12'') 3 11.25 0.75 0.67 45.02 Ft²
Formwork (Floor Beam) 404.37 Ft² 404.37
C Steel Work
17
(Super Sturcture)
DETAIL OF MEASUREMENT
Measurments
Sr. No
Total of
Particulars No Ded; Content Unit
L (Ft) B (Ft) H (Ft) Each
X-direction
Line 1,2&3 PB1 16mm 6mm
FB2 (9''x12'') 3 64.13 0.75 0.67
Top Bar (3-16mmØ) 9 64.71 582.38 Rft
Bottom Bar (3-16mmØ) 9 64.88 583.88 Rft
Stirrups (6mmØ @ 6''c/c) 388 2.33 Rft 905.01
Y-direction
Line A,B,C,D,E,F&G PB1
FB3 (9''x12'') 7 11.00 0.75 0.92
Top Bar (3-16mmØ) 21 14.22 298.56 Rft
Bottom Bar (3-16mmØ) 21 13.88 291.55 Rft
Stirrups (6mmØ @ 6''c/c) 161 2.83 Rft 456.27
Line H PB1
FB2 (9''x12'') 1 11.25 0.75 0.67
Top Bar (3-16mmØ) 3 11.83 35.50 Rft
Bottom Bar (3-16mmØ) 3 12.00 36.00 Rft
Stirrups (6mmØ @ 6''c/c) 24 2.33 Rft 54.85
1:2:4 Concrete Work (1st Floor Slab) 27.97 662.00 Ft³ 634.03
B Formwork
1 71.00 28.00 0.33 1988.00 Ft²
Deduction
Stair 1 7.00 12.00 0.33 84 Ft²
Formwork (1st Floor Slab) 84.00 1988.00 Ft² 1904.00
4 Stair Case
4.1 Ground To 1st Floor Level Stair
18
(Super Sturcture)
DETAIL OF MEASUREMENT
Measurments
Sr. No
Total of
Particulars No Ded; Content Unit
L (Ft) B (Ft) H (Ft) Each
A 1:2:4 Concrete Work
Landing Slab 3 7.00 5.00 0.33 34.97 Ft³
Landing Beam 3 7.00 0.75 0.75 11.81 Ft³
Waist 6 8.67 3.50 0.50 91.04 Ft³
Step 48 3.50 0.28 46.67 Ft³
1:2:4 Concrete Work (Ground to 1st Fl Level Stair) 184.48 Ft³ 184.48
B Formwork
Landing Slab 3 7.00 5.00 0.33 105.00 Ft²
Landing Beam 3 7.00 0.75 0.75 31.50 Ft²
Waist 6 8.67 3.50 0.50 182.07 Ft²
Step 48 3.50 0.28 46.67 Ft²
Step Cover 12 8.67 1.50 156.06 Ft²
Formwork (Ground to 1st Fl Level Stair) 521.30 Ft² 521.30
C Steel Work
Waist 6 8.67 4.34 0.50 12mm 10mm
Main bar (12mm @ 6''c/c)
Bottom Steel 48 16 776.24 Rft
Top Steel (L/3) 48 6 290.72 Rft
Top Steel (L/3) 48 9 430.80 Rft
19
(Super Sturcture)
Builder's Estimate
Sr. No Particular Quantity Unit Rate Per Amount Total Amount
Labour
Mason 15.12 Nos 10000 Nos 151184.86458
Workers 45.36 Nos 7500 Nos 340165.94531
Machine Driver 3.78 Nos 8500 Nos 32126.783724
523477.59362 523477.59
B Formwork (Timber Shuttering)
1 Column, Beam, Slab & Stair
3776.77 Ft²
Material (2 times used)
Timber Scantling 5.67 Tons 760000 Tons 4305513.42
5 ply wood (8'x4')(+10%) 64.91 Shts 25000 Shts 1622829.21
Nails 31.47 Viss 1250 Viss 39341.31
Red Oxide 11.97 Gals 10560 Gals 126428.00
Turpentine 2.42 Gals 6750 Gals 16358.12
6110470.06 6110470.06
Labour
Carpenter 151.07 Nos 10000 Nos 1510706.46
Workers 75.54 Nos 7500 Nos 566514.92
2077221.39 2077221.39
C Steel Work
1 Column, Beam, Slab & Stair
6.15 Tons
16mmØ 2.01 Tons 670000 Tons 1349999.62
12mmØ 0.45 Tons 670000 Tons 304415.38
10mmØ 3.34 Tons 670000 Tons 2240269.03
6mmØ 0.34 Tons 670000 Tons 228071.82
Bending wire 35.16 Viss 720 Viss 25316.71
4148072.56 4148072.56
21
(Super Sturcture)
Abstract of cost
C Steel Work
1 Column, Beam, Slab & Stair 6.15 Ton 769114.29 Ton 4,732,642
14,801,549
22
14,801,549
23
(Super Sturcture)
BILL OF QUANTITY
Sr.
Particular Quantity Unit Rate Per Amount
No
A Materials
B Labours
24
#REF!
Err:509
14,801,548.7
25
SUPER STRUCTURE WORK
SUMMUARY
Y-direction
Line A,B,C,E,F& G 7 11.00 10.00 770.00 Ft²
Line H 1 11.25 10.00 112.50 Ft²
Y-direction
10 24.00 9.00 2160.00 Ft²
1.3 Second Floor
X-direction
Line 1,2,3,4&5 5 71.00 9.00 3195.00 Ft²
Y-direction
10 24.00 9.00 2160.00 Ft²
Deduction
Door & Window
TD1 Door Size Ft²
TD2 Ft²
TD3 Ft²
TD4 Ft²
TW1 Ft²
TW2 Ft²
TW3 Ft²
TW4 Ft²
TW5 Ft²
0.00 13012.50 Ft² 13012.50
Total of 4-1/2'' Brick Work (Walling) Ft² 13012.50
27
(Finishing work)
DETAIL OF MEASUREMENT
Sr. No
Measurments Total of
Particulars No Deduction Content Unit
L (Ft) B (Ft) H (Ft) Each
4 Scaffolding Work
Front & Back 2 77.00 41.00 6314.00 Ft²
Left & Right 2 34.00 41.00 2788.00 Ft²
Total of Scaffolding Work 9102.00 Ft² 9102.00
28
(Finishing work)
Builder's Estimate
39,529,099
29
11009969.2 #REF!
#REF!
5530312.5
3621781.23
9911051.06
2695035.159
5049584.08
1355818.75
18682604.34
355546.875
20846495 39529098.8472114
30
(Finishing work)
Abstract of cost
39,529,099
31
39,529,099
32
(Finishing work)
BILL OF QUANTITY
Sr.
Particular Quantity Unit Rate Per Amount
No
A Materials
B Labours
33
18,682,604
20846494.51
39,529,098.8
34
FINISHING WORK (Finishing)
SUMMUARY