CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
Page 2 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
C-1-F05 8 34.00 - 5.00 1360.00 Sft
C-1,C-1-F05 2 34.00 - 5.00 340.00 Sft
C-1-F06 2 36.00 - 5.00 4500.00 Sft
C-1,C-2,C-2-F07 4 52.17 - - 208.66 Sft
Total 17388.66 Sft
Strip Footing
Strip on (Front & Back ) 4 75.50 - 5.00 1510.00 Sft
Strip on (Right & Left) 4 50.50 - 5.00 1010.00 Sft
Total 2520.00 Sft
4000 Psi
Additional for Shuttering and Scafolding on a, b or c for
pillars and columns of any shape
(S.I No. 5 - 26 b+d)
R.C.C in Columns and Strip Footing
Column Footing
C-1-F01 3 5.00 5.00 1.00 75.00 Cft
C-2-F01 4 5.00 5.00 1.00 100.00 Cft
C-1-F02 4 6.00 6.00 1.00 144.00 Cft
C-1-F03 12 7.00 7.00 1.25 735.00 Cft
C-1,C-1-F03 4 7.00 7.00 1.25 245.00 Cft
C-1-F04 40 8.00 8.00 1.50 3840.00 Cft
C-1,C-1-F04 1 8.00 8.00 1.50 96.00 Cft
Page 3 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
C-1-F05 8 8.50 8.50 1.50 867.00 Cft
C-1,C-1-F05 2 8.50 8.50 1.50 216.75 Cft
C-1-F06 2 9.00 9.00 1.75 283.50 Cft
C-1,C-2,C-2-F07 4 147.54 - 2.00 1180.30 Cft
Total 7782.55 Cft
Strip Footing
Strip on (Front & Back ) 2 75.50 2.000 1.00 302.00 Cft
Strip on (Right & Left) 2 50.50 2.000 1.00 202.00 Cft
Total 504.00 Cft
4000 Psi
Additional for Shuttering and Scafolding on a, b or c for
pillars and columns of any shape
(S.I No. 5 - 26 b+i)
R.C.C in Columns upto Plinth beam
C-1-F01 3 1.00 2.00 5.75 34.50 Cft
C-2-F01 4 2.41 - 5.75 55.52 Cft
C-1-F02 4 1.00 2.00 5.75 46.00 Cft
C-1-F03 12 1.00 2.00 5.50 132.00 Cft
C-1,C-1-F03 8 1.00 2.00 5.50 88.00 Cft
C-1-F04 40 1.00 2.00 5.25 420.00 Cft
C-1,C-1-F04 2 1.00 2.00 5.25 21.00 Cft
C-1-F05 8 1.00 2.00 5.25 84.00 Cft
C-1,C-1-F05 4 1.00 2.00 5.25 21.00 Cft
C-1-F06 2 1.00 2.00 5.00 10.00 Cft
C-1,C-2,C-2-F07 4 1.00 2.00 4.75 38.00 Cft
(C-2) 8 2.41 - 4.75 91.73 Cft
Page 4 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
Wall on grid ( Qa) 6 to 17 1 47.75 0.750 3.75 134.30 Cft
Diagonal 4 4.25 0.750 3.75 47.81 Cft
Stair 2 23.88 0.750 3.75 134.30 Cft
4000 Psi
Additional for Shuttering and Scafolding on a, b or c for
pillars and columns of any shape
(S.I No. 5 - 26 b+j)
R.C.C in Plinth band
Plinth band on grid (A ) 5 to 6,11to12 & 17to18 1 49.50 1.00 2.00 99.00 Cft
Plinth band on grid (B) 3 to 5,6 to 11,12 to 17 & 18 to 20 1 69.50 1.00 2.00 139.00 Cft
Plinth band on grid (C) 3 to 22 1 103.75 1.00 2.00 207.50 Cft
Plinth band on grid (Ca) 4 to 22 1 100.75 1.00 2.00 201.50 Cft
Plinth band on grid (D) 1 to7 & 13 to21 1 51.63 1.00 2.00 103.25 Cft
Plinth band on grid (G) 2 to 5 & 18 to 20 1 25.00 1.00 2.00 50.00 Cft
Plinth band on grid (H) 15 to 17 1 8.21 1.00 2.00 16.42 Cft
Plinth band on grid (J) 2 to 5 & 18 to 20 1 25.00 1.00 2.00 50.00 Cft
Plinth band on grid (K) 2 to 5 & 18 to 20 1 23.00 1.00 2.00 46.00 Cft
Plinth band on grid (L) 6 to 8 1 8.21 1.00 2.00 16.42 Cft
Plinth band on grid (M) 2 to 5 & 18 to 20 1 25.00 1.00 2.00 50.00 Cft
Plinth band on grid (Q) 1 to10 & 16 to22 1 71.63 1.00 2.00 143.25 Cft
Plinth band on grid (Qa) 4 to 19 1 93.25 1.00 2.00 186.50 Cft
Plinth band on grid (R) 3 to 20 1 99.50 1.00 2.00 199.00 Cft
Plinth band on grid (S) 3 to 5,6 to 11,12 to 17 & 18 to 20 1 69.50 1.00 2.00 139.00 Cft
Plinth band on grid (T ) 5to6,11to12 & 17to18 1 49.50 1.00 2.00 99.00 Cft
Plinth band on grid Diagonal 8 to 10 1 8.33 1.00 2.00 16.67 Cft
Plinth band on grid Diagonal F to H 1 8.33 1.00 2.00 16.67 Cft
Plinth band on grid Diagonal 4 4.25 1.00 2.00 34.00 Cft
Plinth band on grid (1) G to J & K to M 1 33.00 1.00 2.00 66.00 Cft
Plinth band on grid (2) D to G,J to K & M to Q 1 34.50 1.00 2.00 69.00 Cft
Plinth band on grid (3) B to C, & R to S 1 29.50 1.00 2.00 59.00 Cft
Plinth band on grid (4) C to Ca & Qa to R 1 23.50 1.00 2.00 47.00 Cft
Plinth band on grid (5 ) B to C,D to Q & R to S 1 82.50 1.00 2.00 165.00 Cft
Plinth band on grid (6) B to C,E to P & R to S 1 74.75 1.00 2.00 149.50 Cft
Plinth band on grid (9) B to C & R to S 1 25.00 1.00 2.00 50.00 Cft
Plinth band on grid (10) N to Q 1 7.00 1.00 2.00 14.00 Cft
Plinth band on grid (11) B to C 1 12.50 1.00 2.00 25.00 Cft
Plinth band on grid (12) B to C & R to S 1 27.00 1.00 2.00 54.00 Cft
Plinth band on grid (13) D to F 1 7.00 1.00 2.00 14.00 Cft
Plinth band on grid (14) B to C 1 11.50 1.00 2.00 23.00 Cft
Plinth band on grid (17) B to C,E to P 1 60.25 1.00 2.00 120.50 Cft
Plinth band on grid (18 ) B to C,D to Q & R to S 1 82.50 1.00 2.00 165.00 Cft
Plinth band on grid (19) Qa to R 1 11.75 1.00 2.00 23.50 Cft
Plinth band on grid (20) B to C, & R to S 1 29.50 1.00 2.00 59.00 Cft
Plinth band on grid (21) C to G & M to Q 1 34.75 1.00 2.00 69.50 Cft
Plinth band on grid (22) G to M 1 45.00 1.00 2.00 90.00 Cft
Page 5 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
4000 Psi
Additional for Shuttering and Scafolding on a, b or c for
pillars and columns of any shape
(S.I No. 5 - 26 b+i)
R.C.C Columns upto roof level
C1 87 1.000 2.000 14.00 2436.00 Cft
C2 12 2.41 - 14.00 405.55 Cft
Page 6 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
Wall on grid (9) A to C & R to T 1 29.50 0.75 12.50 276.56 Cft
Wall on grid (10) M to Q 1 7.00 0.75 12.50 65.63 Cft
Wall on grid (11) A to C 1 15.50 0.75 12.50 145.31 Cft
Wall on grid (12) A to C & R to T 1 30.00 0.75 12.50 281.25 Cft
Wall on grid (13) D to F 1 7.00 0.75 12.50 65.63 Cft
Wall on grid (14) A to C 1 16.00 0.75 12.50 150.00 Cft
Wall on grid (17) A to C & E to P 1 61.71 0.75 12.50 578.52 Cft
Wall on grid (18 ) A to T 1 109.00 0.75 12.50 1021.88 Cft
Wall on grid (19) Qa to R 1 11.75 0.75 12.50 110.16 Cft
Wall on grid (20) A to C, & R to T 1 29.50 0.75 12.50 276.56 Cft
Wall on grid (21) D to G & M to Q 1 23.00 0.75 12.50 215.63 Cft
Wall on grid (22) G to J & K to M 1 27.00 0.75 12.50 253.13 Cft
Total 12277.27 Cft
Main Entrance Steps 2 18.00 3.00 1.00 108.00 Cft
2 16.00 2.00 0.50 32.00 Cft
2 14.00 1.00 0.50 14.00 Cft
Total 154.00 Cft
Page 7 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
Wall without Grid 6 35.50 0.375 14.00 1118.25 Cft
Wall without Grid 1 26.50 0.375 14.00 139.13 Cft
Brick masonry for counter kitchen Shelve 1 40.00 0.375 3.00 45.00 Cft
Total 1302.38 Cft
3000 Psi
Additional for Shuttering and Scafolding on a, b or c for
beams, lintels and cantilevers of required shape
(S.I No. 5 - 26 A+j)
R.C.C in Lintel
Lintes on Verandah Openings
Openings on grid (D) 7 to 16 1 47.33 0.75 1.00 35.50 Cft
Openings on grid (Qa) 7 to 16 1 47.71 0.75 1.00 35.78 Cft
Openings on grid (6) E to P 1 47.71 0.75 1.00 35.78 Cft
Openings on grid (17) E to P 1 47.71 0.75 1.00 35.78 Cft
Diagonal 4 4.25 0.75 1.00 12.75 Cft
Lintes on Doors 2 7.50 0.75 0.75 8.44 Cft
Lintels on Doors 1 6.50 0.75 0.75 3.66 Cft
Lintels on Doors 1 6.00 0.75 0.75 3.38 Cft
Lintels on Doors 13 5.00 0.75 0.75 36.56 Cft
Lintels on Doors 2 3.50 0.75 0.75 3.94 Cft
Lintels on Windows 8 7.50 0.75 0.75 33.75 Cft
Lintels on Windows 19 6.00 0.75 0.75 64.13 Cft
Lintels on Windows 44 3.00 0.75 0.75 74.25 Cft
Lintels on Doors 11 3.50 0.375 0.50 7.22 Cft
Page 8 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
12 Providing and laying in position ready mixed concrete for
reinforced cement concrete work, using cement content as
per approved design mix, manufactured in fully automatic
batching plant and transported to site of work in transit
mixer for all leads, having continuous agitated mixer,
manufactured as per mix design of specified grade for
reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying , excluding the
cost of centering, shuttering finishing and reinforcement
including cost of admixtures in recommended proportions
as per mix design to accelerate/ retard setting of concrete,
improve workability without impairing strength and
durability as per direction of the Engineer - in - charge.
3000 Psi
Additional for Shuttering and Scafolding on a, b or c for
beams, lintels and cantilevers of required shape
(S.I No. 5 - 26 a+j)
R.C.C in Roof Beam
Roof Beam on grid (A ) 5 to 6,11to12 & 17to18 1 49.50 1.00 1.50 74.25 Cft
Roof Beam on grid (B) 3 to 5,6 to 11,12 to 17 & 18 to 20 1 69.50 1.00 1.50 104.25 Cft
Roof Beam on grid (C) 3 to 22 1 103.75 1.00 1.50 155.63 Cft
Roof Beam on grid (Ca) 4 to 22 1 100.75 1.00 1.50 151.13 Cft
Roof Beam on grid (D) 1 to7 & 13 to21 1 51.63 1.00 1.50 77.44 Cft
Roof Beam on grid (G) 2 to 6 & 17 to 20 1 49.00 1.00 1.50 73.50 Cft
Roof Beam on grid (H) 15 to 17 1 8.21 1.00 1.50 12.31 Cft
Roof Beam on grid (J) 2 to 5 & 18 to 20 1 25.00 1.00 1.50 37.50 Cft
Roof Beam on grid (K) 2 to 6 & 17 to 20 1 46.75 1.00 1.50 70.13 Cft
Roof Beam on grid (L) 6 to 8 1 8.21 1.00 1.50 12.31 Cft
Roof Beam on grid (M) 2 to 5 & 18 to 20 1 25.00 1.00 1.50 37.50 Cft
Roof Beam on grid (Q) 1 to10 & 16 to22 1 71.63 1.00 1.50 107.44 Cft
Roof Beam on grid (Qa) 4 to 19 1 93.25 1.00 1.50 139.88 Cft
Roof Beam on grid (R) 3 to 20 1 99.50 1.00 1.50 149.25 Cft
Roof Beam on grid (S) 3 to 5,6 to 11,12 to 17 & 18 to 20 1 69.50 1.00 1.50 104.25 Cft
Roof Beam on grid (T ) 5to6,11to12 & 17to18 1 49.50 1.00 1.50 74.25 Cft
Roof Beam on grid Diagonal 8 to 10 1 8.33 1.00 1.50 12.50 Cft
Roof Beam on grid Diagonal F to H 1 8.33 1.00 1.50 12.50 Cft
Roof Beam on grid Diagonal 4 4.25 1.00 1.50 25.50 Cft
Roof Beam on grid (1) G to J & K to M 1 33.00 1.00 1.50 49.50 Cft
Roof Beam on grid (2) D to G,J to K & M to Q 1 34.50 1.00 1.50 51.75 Cft
Roof Beam on grid (3) B to C, & R to S 1 29.50 1.00 1.50 44.25 Cft
Roof Beam on grid (4) C to Ca & Qa to R 1 23.50 1.00 1.50 35.25 Cft
Roof Beam on grid (5 ) B to S 1 106.00 1.00 1.50 159.00 Cft
Roof Beam on grid (6) B to C,D to Q & R to S 1 82.50 1.00 1.50 123.75 Cft
Roof Beam on grid (7) C to Ca & Qa to R 1 23.50 1.00 1.50 35.25 Cft
Roof Beam on grid (9) B to C & R to S 1 25.00 1.00 1.50 37.50 Cft
Roof Beam on grid (10) N to R 1 18.75 1.00 1.50 28.13 Cft
Roof Beam on grid (11) B to Ca & R to S 1 41.75 1.00 1.50 62.63 Cft
Roof Beam on grid (12) B to C & Qa to S 1 38.75 1.00 1.50 58.13 Cft
Roof Beam on grid (13) C to F 1 18.75 1.00 1.50 28.13 Cft
Roof Beam on grid (14) B to C & R to S 1 25.00 1.00 1.50 37.50 Cft
Roof Beam on grid (16) C to Ca & Qa to R 1 23.50 1.00 1.50 35.25 Cft
Roof Beam on grid (17) B to C,D to Q & R to S 1 82.50 1.00 1.50 123.75 Cft
Roof Beam on grid (18 ) B to S 1 106.00 1.00 1.50 159.00 Cft
Roof Beam on grid (19) Qa to R 1 11.75 1.00 1.50 17.63 Cft
Roof Beam on grid (20) B to C, & R to S 1 29.50 1.00 1.50 44.25 Cft
Roof Beam on grid (21) C to G,J to K & M to Q 1 46.25 1.00 1.50 69.38 Cft
Roof Beam on grid (22) G to J & K to K 1 33.00 1.00 1.50 49.50 Cft
Page 9 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
13 Providing and laying in position ready mixed concrete for
reinforced cement concrete work, using cement content as
per approved design mix, manufactured in fully automatic
batching plant and transported to site of work in transit
mixer for all leads, having continuous agitated mixer,
manufactured as per mix design of specified grade for
reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying , excluding the
cost of centering, shuttering finishing and reinforcement
including cost of admixtures in recommended proportions
as per mix design to accelerate/ retard setting of concrete,
improve workability without impairing strength and
durability as per direction of the Engineer - in - charge.
3000 Psi
Additional for Shuttering and Scafolding on a, b or c for
slabs from 6" upto 9" in thickness
(S.I No. 5 - 26 a+l)
R.C.C in Slab
Total area of Slab 1 10671.20 - 0.50 5335.60 Cft
Slab area of Enterance (Low Level) 1 651.18 - 0.50 325.59 Cft
Chajja on Windows 17 19.00 - 0.50 161.50 Cft
3000 Psi
Additional for Shuttering and Scafolding on a, b or c for
slabs from 6" upto 9" in thickness
(S.I No. 5 - 26 a+l)
R.C.C in Stair Case
Page 10 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
Water Cooler 1 32.50 - 2.00 65.00 Cft
Reception 1 32.50 - 2.00 65.00 Cft
Janitorial 1 32.50 - 2.00 65.00 Cft
Rooms 2 190.735 - 2.00 762.94 Cft
Bath 2 34.500 - 2.00 138.00 Cft
Dress 2 28.750 - 2.00 115.00 Cft
Common Hall 1 421.25 - 2.00 842.50 Cft
Dining Hall 1 622.10 - 2.00 1244.21 Cft
Bearers 1 190.76 - 2.00 381.53 Cft
Dress 1 18.69 - 2.00 37.37 Cft
Bath 1 28.75 - 2.00 57.50 Cft
Cabinet 1 54.38 - 2.00 108.75 Cft
Store 1 371.13 - 2.00 742.25 Cft
Tandoor 1 142.00 - 2.00 284.00 Cft
Kitchen 1 444.59 - 2.00 889.19 Cft
Verandah/ Cooridor 1 4790.85 - 2.00 9581.71 Cft
Stair Case 2 131.19 - 2.00 524.74 Cft
Total Quantity of Earth Filling under Floor Total 19653.69 Cft
With surplus earth from foundation etc.
(S.I No. 3-16- A)
40% of the total surplus earth 7861.48 Cft
Page 11 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
Total 2579.55 Cft 145.65 375,711
Page 12 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
Threshold
D 2 6.00 1.00 - 12.00 Sft
D1 1 5.00 1.00 - 5.00 Sft
D2 1 4.50 1.00 - 4.50 Sft
D3 13 3.50 1.00 - 45.50 Sft
D4 2 2.50 1.00 - 5.00 Sft
D4 11 2.50 0.50 - 13.75 Sft
Page 13 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
22
Providing and laying 3/4"(19mm) thick Granite polished
tiles of any size on floor of approved design in any color,
shade and pattern in ground floor over 3/8" thick base
cement sand mortar 1:3 including setting the tiles with
portland cement slurry over cement sand jointing and
washing the tiles with cement slurry of matching color
including grinding, rubbing, polishing & mortar cost.
(S.I No. 14-9a+24c )
Granite on Shelve top
1 100.00 2.00 200.00 Sft
25
Providing and laying 1/4" to 3/8" (6mm to 9mm) thick
Glazed/ Matt tiles of any colour and size in ground floor
laid over 1" (25mm) thick cement sand mortar base
including jointing and washing the tiles with white cement
slurry of matching color by using color pigment and curing
(S.I No. 14-25 a )
Glazed Tile Flooring in Toilet
Bath 8 34.500 - - 276.00 Sft
Water Cooler 1 32.50 - - 32.50 Sft
Janitorial 1 32.50 - - 32.50 Sft
Bath 2 34.500 - - 69.00 Sft
Bath 1 28.75 - - 28.75 Sft
Tandoor 1 142.00 - - 142.00 Sft
Kitchen 1 444.59 - - 444.59 Sft
Page 14 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
Total 1076.61 Sft 182.25 196,212
Deodar wood
(S.I No. 16-3-a )
Wooden Door Frames
D 2 22.50 0.875 0.25 9.84 Cft
D1 1 19.50 0.875 0.25 4.27 Cft
D2 1 19.00 0.875 0.25 4.16 Cft
D3 13 18.00 0.875 0.25 51.19 Cft
D4 2 17.00 0.875 0.25 7.44 Cft
D4 11 17.00 0.5 0.25 23.38 Cft
Page 15 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
32 Providing and fixing iron grills with square bars of 3/8" size
as per approved design including welding all sides of the
section at the junction and fixing with sunk iron screws,
painting with two coats of red oxide paint and fixing in
masonry/concrete or wood
(S.I No. 28-28 - 1 )
Iron Grills on Windows
W 8 6.00 - 6.00 288.00 Sft
W1 19 4.50 - 6.00 513.00 Sft
W2 44 2.00 - 6.00 528.00 Sft
V 12 2.00 - 2.00 48.00 Sft
Page 16 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
34 Applying architectural coating such as Rockwall, Durock,
Graphaito or equivalent to interior or exterior walls
including supplying all labour, materials, scaffoldings and
removal of debris etc.
(S.I No. 17.71-1 )
Graphic Art on Exterior Wall
50% of Exterior Surface 0.5 12180.66 6090.33 Sft
(S.I.No. 16-66 d )
38 Internal Door Lock
Hyundi Lock
15 - - - 15.00 Each
(S.I.No. 16-66 f )
Page 17 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
40 Hydraulic Door Closer
Hydraulic door closer, New star make
21 21.00 Each
(S.I.No. 28-82-1 )
a Stainless Steel Hand Rail of Stair Case
Hand Rail Self Supported
Stair -1 1 25.00 - - 25.00 Rft
Stair -2 1 25.00 - - 25.00 Rft
(N.S.R)
45 Hand Rail Wall Mounted
b Stair -1 1 25.00 - - 25.00 Rft
Stair -2 1 25.00 - - 25.00 Rft
Page 18 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
46 Providing, fabricating and laying deformed Grade 60 steel
reinforcement (deformed bar) for all kinds of R.C.C work in
foundation, plinth and ground floor including the cost of
straightening, removal of rust, cutting, bending, binding,
wastage and providing such over-laps as are not shown on
the drawings. The cost of binding wire and cement
concrete spacer blocks or chairs for binding and holding
the reinforcement in position is inclusive upto 15 ft. (5m)
height
(S.I.NO 5-65-a)
Reinforcement
Footing 8701 38677.60 - - 38.68 Tonne
Plinth band+Lintel + Roof beam 6455 28696.23 - - 28.70 Tonne
Columns 4077 27188.07 - - 27.19 Tonne
Slabs 6114 16639.27 - - 16.64 Tonne
Stair 217 591.89 0.59 Tonne
Page 19 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
Page 20 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
Page 21 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
Wall on grid (1) G to J & K to M 1 27.00 0.75 12.50 253.13 Cft
Wall on grid (2) D to G,J to K & M to Q 1 34.50 0.75 12.50 323.44 Cft
Wall on grid (3) A to C, & R to T 1 29.50 0.75 12.50 276.56 Cft
Wall on grid (4) C to Ca & Qa to R 1 23.50 0.75 12.50 220.31 Cft
Wall on grid (5 ) A to C,D to G,J to K,M to Q & R to T 1 61.50 0.75 12.50 576.56 Cft
Wall on grid (6) A to C,E to P & R toT 1 77.71 0.75 12.50 728.52 Cft
Wall on grid (9) A to C & R to T 1 29.50 0.75 12.50 276.56 Cft
Wall on grid (10) M to Q 1 7.00 0.75 12.50 65.63 Cft
Wall on grid (11) A to C & R to T 1 30.00 0.75 12.50 281.25 Cft
Wall on grid (12) A to C & R to T 1 30.00 0.75 12.50 281.25 Cft
Wall on grid (13) D to F 1 7.00 0.75 12.50 65.63 Cft
Wall on grid (14) A to C & R to T 1 29.50 0.75 12.50 276.56 Cft
Wall on grid (17) A to C & E to P & R to T 1 76.21 0.75 12.50 714.46 Cft
Wall on grid (18 ) A to T 1 109.00 0.75 12.50 1021.88 Cft
Wall on grid (19) C to Ca & Qa to R 1 23.75 0.75 12.50 222.66 Cft
Wall on grid (20) A to C, & R to T 1 29.50 0.75 12.50 276.56 Cft
Wall on grid (21) D to G,J to K & M to Q 1 34.50 0.75 12.50 323.44 Cft
Wall on grid (22) G to J & K to M 1 27.00 0.75 12.50 253.13 Cft
Total 12570.00 Cft
Main Entrance Steps 2 18.00 3.00 1.00 108.00 Cft
2 16.00 2.00 0.50 32.00 Cft
2 14.00 1.00 0.50 14.00 Cft
Total 154.00 Cft
Verandah Openings
Openings on grid (D) 7 to 16 1 47.33 0.75 7.00 248.50 Cft
Openings on grid (Qa) 7 to 16 1 47.71 0.75 7.00 250.47 Cft
Openings on grid (6) E to P 1 47.71 0.75 7.00 250.47 Cft
Openings on grid (17) E to P 1 47.71 0.75 7.00 250.47 Cft
Diagonal 4 4.25 0.75 7.00 89.25 Cft
Lintes on Verandah Openings
Openings on grid (D) 7 to 16 1 47.33 0.75 1.00 35.50 Cft
Openings on grid (Qa) 7 to 16 1 47.71 0.75 1.00 35.78 Cft
Openings on grid (6) E to P 1 47.71 0.75 1.00 35.78 Cft
Openings on grid (17) E to P 1 47.71 0.75 1.00 35.78 Cft
Diagonal 4 4.25 0.75 1.00 12.75 Cft
Page 22 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
Brick masonry for counter kitchen Shelve 1 40.00 0.375 3.00 45.00 Cft
Total 3399.75 Cft
Page 23 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
Additional for Shuttering and Scafolding on a, b or c for
beams, lintels and cantilevers of required shape
For first floor
(S.I No. 5 - 26 a+j+n)
R.C.C in Roof Beam
Roof Beam on grid (A ) 5 to 6,11to12 & 17to18 1 49.50 1.00 1.50 74.25 Cft
Roof Beam on grid (B) 3 to 5,6 to 11,12 to 17 & 18 to 20 1 69.50 1.00 1.50 104.25 Cft
Roof Beam on grid (C) 3 to 22 1 103.75 1.00 1.50 155.63 Cft
Roof Beam on grid (Ca) 4 to 22 1 100.75 1.00 1.50 151.13 Cft
Roof Beam on grid (D) 1 to7 & 13 to21 1 51.63 1.00 1.50 77.44 Cft
Roof Beam on grid (G) 2 to 6 & 17 to 20 1 49.00 1.00 1.50 73.50 Cft
Roof Beam on grid (H) 15 to 17 1 8.21 1.00 1.50 12.31 Cft
Roof Beam on grid (J) 2 to 5 & 18 to 20 1 25.00 1.00 1.50 37.50 Cft
Roof Beam on grid (K) 2 to 6 & 17 to 20 1 46.75 1.00 1.50 70.13 Cft
Roof Beam on grid (L) 6 to 8 1 8.21 1.00 1.50 12.31 Cft
Roof Beam on grid (M) 2 to 5 & 18 to 20 1 25.00 1.00 1.50 37.50 Cft
Roof Beam on grid (Q) 1 to10 & 16 to22 1 71.63 1.00 1.50 107.44 Cft
Roof Beam on grid (Qa) 4 to 19 1 93.25 1.00 1.50 139.88 Cft
Roof Beam on grid (R) 3 to 20 1 99.50 1.00 1.50 149.25 Cft
Roof Beam on grid (S) 3 to 5,6 to 11,12 to 17 & 18 to 20 1 69.50 1.00 1.50 104.25 Cft
Roof Beam on grid (T ) 5to6,11to12 & 17to18 1 49.50 1.00 1.50 74.25 Cft
Roof Beam on grid Diagonal 8 to 10 1 8.33 1.00 1.50 12.50 Cft
Roof Beam on grid Diagonal F to H 1 8.33 1.00 1.50 12.50 Cft
Roof Beam on grid Diagonal 4 4.25 1.00 1.50 25.50 Cft
Roof Beam on grid (1) G to J & K to M 1 33.00 1.00 1.50 49.50 Cft
Roof Beam on grid (2) D to G,J to K & M to Q 1 34.50 1.00 1.50 51.75 Cft
Roof Beam on grid (3) B to C, & R to S 1 29.50 1.00 1.50 150.00 Cft
Roof Beam on grid (4) C to Ca & Qa to R 1 23.50 1.00 1.50 50.00 Cft
Roof Beam on grid (5 ) B to S 1 106.00 1.00 1.50 50.00 Cft
Roof Beam on grid (6) B to C,D to Q & R to S 1 82.50 1.00 1.50 123.75 Cft
Roof Beam on grid (7) C to Ca & Qa to R 1 23.50 1.00 1.50 35.25 Cft
Roof Beam on grid (9) B to C & R to S 1 25.00 1.00 1.50 37.50 Cft
Roof Beam on grid (10) N to R 1 18.75 1.00 1.50 20.00 Cft
Roof Beam on grid (11) B to Ca & R to S 1 41.75 1.00 1.50 62.63 Cft
Roof Beam on grid (12) B to C & Qa to S 1 38.75 1.00 1.50 58.13 Cft
Roof Beam on grid (13) C to F 1 18.75 1.00 1.50 28.13 Cft
Roof Beam on grid (14) B to C & R to S 1 25.00 1.00 1.50 37.50 Cft
Roof Beam on grid (16) C to Ca & Qa to R 1 23.50 1.00 1.50 35.25 Cft
Roof Beam on grid (17) B to C,D to Q & R to S 1 82.50 1.00 1.50 123.75 Cft
Roof Beam on grid (18 ) B to S 1 106.00 1.00 1.50 159.00 Cft
Roof Beam on grid (19) Qa to R 1 11.75 1.00 1.50 17.63 Cft
Roof Beam on grid (20) B to C, & R to S 1 29.50 1.00 1.50 44.25 Cft
Roof Beam on grid (21) C to G,J to K & M to Q 1 46.25 1.00 1.50 350.00 Cft
Roof Beam on grid (22) G to J & K to K 1 33.00 1.00 1.50 450.00 Cft
Page 24 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
3000 Psi
Additional for Shuttering and Scafolding on a, b or c for
slabs from 6" upto 9" in thickness
(S.I No. 5 - 26 a+l)
R.C.C in Slab
Total area of Slab 1 10671.20 - 0.50 5335.60 Cft
Chajja on Windows 18 19.00 - 0.50 171.00 Cft
3000 Psi
Additional for Shuttering and Scafolding on a, b or c for
slabs from 6" upto 9" in thickness
(S.I No. 5 - 26 a+l)
R.C.C in Stair Case
Page 25 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
9 Cement plaster using Coarse Sand on soffits of ceiling,
cantilever slabs, sides and soffits of beams, in basement
and ground floor including making edges, corners and
curing.
1/2 inch (13mm) thick cement sand plaster (1:4 Ratio)
11
Providing and laying super white 12"x12" marble tiles
floor fine dressed on surface without winding in ground
floor and laid over 1" (25mm) thick cement sand mortar
1:2 setting tiles with portland cement slurry over cement
mortar, jointing and washing the tiles with white cement
slurry including curing, rubbing and polishing including
the cost of cement mortar.
1/2" (13 mm) thick marble tiles floor
Extra over item 14-9 to 14-22-1 for the description of
work given below:
Extra for first floor
(S.I No. 14-9a+24c )
Marble Tiles Flooring
Rooms 12 166.750 - - 2001.00 Sft
Dress 12 28.750 - - 345.00 Sft
Rooms 6 190.735 - - 1144.41 Sft
Dress 6 28.750 - - 172.50 Sft
Store 1 66.13 - - 66.13 Sft
Page 26 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
Threshold
D3 18 3.5 1.00 - 63.00 Sft
13
Providing and laying 3/4"(19mm) thick Granite polished
tiles of any size on floor of approved design in any color,
shade and pattern in ground floor over 3/8" thick base
cement sand mortar 1:3 including setting the tiles with
portland cement slurry over cement sand jointing and
washing the tiles with cement slurry of matching color
including grinding, rubbing, polishing & mortar cost.
(S.I No. 14-9a+24c )
Granite on Shelve top
1 100.00 2.00 200.00 Sft
14
Providing and laying super white 12"x12" marble tiles
floor fine dressed on surface without winding in ground
floor and laid over 1" (25mm) thick cement sand mortar
1:2 setting tiles with portland cement slurry over cement
mortar, jointing and washing the tiles with white cement
slurry including curing, rubbing and polishing including
the cost of cement mortar.
1" (25 mm) thick marble tiles floor
Extra over item 14-09 to 14-22 for the description of
work given below.
a) Extra for stair/steps.
Extra for first floor
(S.I No. 14-9c+14-24a+c )
Marble on Stair Case
Treads 58.0 5.00 1.00 - 290.00 Sft
Risers 62.0 5.00 0.50 - 155.00 Sft
Half Landing 4 9.58 - - 38.32 Sft
Page 27 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
Total 507.49 Sft 498.95 253,210
Page 28 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
19 Providing and fixing First class wood frames of required
size for doors, windows, ventilators, clerestory windows,
shelves, partitions, trellis (Jafri) work.
Deodar wood
Extra for respective payable item of ground floor
For first floor
(S.I No. 16-3-a+87a )
Wooden Door Frames
D3 18 18.00 0.875 0.25 70.88 Cft
Page 29 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
23 Providing and fixing iron grills with square bars of 3/8"
size as per approved design including welding all sides
of the section at the junction and fixing with sunk iron
screws, painting with two coats of red oxide paint and
fixing in masonry/concrete or wood
Extra for respective payable item of ground floor
For first floor
(S.I No. 28-28 - 1+67a )
Iron Grills on Windows
W 6 6.00 - 6.00 216.00 Sft
W1 22 4.50 - 6.00 594.00 Sft
W2 72 2.00 - 6.00 864.00 Sft
V 20 2.00 - 2.00 80.00 Sft
Page 30 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
27 Painting with ICI/Berger or equivalent super gloss
synthetic enamel paint in two or more coats as per
manufacturer's instructions on steel and iron work over
and including the cost of priming coat, surface
preparation, removing rust, scales and dust with wire
brush in ground floor or basement. (@ atleast 1.25Litre
per 10 Sq.m)
Extra for respective payable item of ground floor
For first floor
(S.I No. 17-7-1 +47a)
Painting on Iron work
2 1842 3683.40 Sft
18 18.00 Each
Page 31 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
b) Brass finger plate 150 mm x 57 mm (6² x 2-1/4²) with
brass screws.
Add extra for respective payable item of ground floor.
(S.I.No. 28-82-1+67a )
a Stainless Steel Hand Rail of Stair Case
Hand Rail Self Supported
Stair -1 1 25.00 - - 25.00 Rft
Stair -2 1 25.00 - - 25.00 Rft
Page 32 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
Stair 217 591.89 0.59 Tonne
Page 33 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
41 Providing and fixing of 3/4" (19mm) thick 12" x 24"
travetine sand stone in beach color (Loralai stone) on
exterior wall and cladding including with cement sand
mortar 1:3 complete in all respect.
(S.I No. 15-56-1 )
Face Stone on Exterior Wall
50% of Exterior Surface 0.5 12592.39 6296.20 Sft
Page 34 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
Page 35 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
3 Providing and laying in position ready mixed concrete for
reinforced cement concrete work, using cement content
as per approved design mix, manufactured in fully
automatic batching plant and transported to site of work
in transit mixer for all leads, having continuous agitated
mixer, manufactured as per mix design of specified grade
for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying , excluding the
cost of centering, shuttering finishing and reinforcement
including cost of admixtures in recommended proportions
as per mix design to accelerate/ retard setting of
concrete, improve workability without impairing strength
and durability as per direction of the Engineer - in -
charge.
3000 Psi
Additional for Shuttering and Scafolding on a, b or c for
beams, lintels and cantilevers of required shape
For first floor
Extra for every additional floor over first floor.
(S.I No. 5 - 26 a+j+n)
R.C.C 1:2:4 in Lintel
Lintels on Doors 2 5.00 0.75 0.75 5.63 Cft
Lintels on Windows 6 7.50 0.75 0.75 25.31 Cft
Page 36 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
5 Providing and laying in position ready mixed concrete for
reinforced cement concrete work, using cement content
as per approved design mix, manufactured in fully
automatic batching plant and transported to site of work
in transit mixer for all leads, having continuous agitated
mixer, manufactured as per mix design of specified grade
for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying , excluding the
cost of centering, shuttering finishing and reinforcement
including cost of admixtures in recommended proportions
as per mix design to accelerate/ retard setting of
concrete, improve workability without impairing strength
and durability as per direction of the Engineer - in -
charge.
3000 Psi
Additional for Shuttering and Scafolding on a, b or c for
slabs from 6" upto 9" in thickness
(S.I No. 5 - 26 a+l)
R.C.C 1:2:4 in Slab 6" Thick
2 290.50 - 0.500 290.50 Cft
6
Providing and fixing single leaf steel door with frame fully
panelled with M.S sheet 16 gauge (1.59mm) painted with
two coats of red oxide paint with brass fitting of approved
make including cost of fabrication, iron lugs, cutting holes
and making good the damages to walls.
Extra for first floor
Extra for every additional floor above first floor
(S.I No. 28-6-1+67a +b)
Steel Door
2 3.50 7.00 49.00 Sft
Page 37 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
2 60.00 - 10.00 1200.00 Sft
Page 38 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
14
Extra for first floor on Item No.5-65(a)
(S.I.NO 5-65-a+f)
Reinforcement
Lintels 32 144.40 0.14 Tonne
Columns 203 1351.53 - - 1.35 Tonne
Slabs 291 790.62 - - 0.79 Tonne
Page 39 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
SEWERAGE AND WATER SUPPLY
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
Page 40 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
SEWERAGE AND WATER SUPPLY
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
6
Providing and fixing looking mirror of Belgium/ Malaysian/
Indonesian glass with chromium plated screws.
(S.I No. 23-15-1)
29 2.00 2.00 116.00 Sft
WATER SUPPLY
10 Providing and fixing superior quality gun-metal peet/gate
valve (Class150) of approved make.
(S.I No. 23-39)
i) 15 mm(1/2") dia. 42 42.00 No.s 265.50 11151.00
ii) 20 mm (.75²) i/d. 30 30.00 No.s 331.50 9945.00
iii) 25 mm(1") dia. 10 10.00 No.s 479.25 4792.50
Page 41 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
SEWERAGE AND WATER SUPPLY
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
13 Providing manhole type 'A' size 24" x 18" (inside
dimensions) as per approved design and specifications
complete for 4" to 12" dia pipes upto 4 ft. (1.2 m) depth with
16" dia.Concrete Cover fixed in 4" thick RCC 1:2:4 slab
(with 5 lbs per Cu.ft. or 80 kg/Cu.m of steel), burnt brick
masonry walls 9" (225 mm) thick set in 1:3 cement sand
mortar, 6" thick 1:3:6 cement concrete in foundation, 4" av.
thickness 1:2:4 cement concrete in benching and 1/2"
(13mm) thick cement sand plaster in 1:3 to all inside wall
surfaces, channels and benching including making
requisite number of main and branch channels but
excluding the cost of excavation, back filling and disposal
of excavated stuff.
Page 42 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
SEWERAGE AND WATER SUPPLY
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
16 Excavation in open cutting for sewers and manholes as
shown in drawings, dressing to correct sections and
dimensions according to templates and levels and
removing surface water in all types of soil except rock
(i) The rate includes back filling after laying of sewer, which
is payable separately.
(ii) The rate for close/open shuttering & timbering will be as
per item No. 3-43 & 3-44 where actually used at site.
TOTAL 3,142,999
S
G-TOTAL 0.00 3,142,999
Page 43 of 55
COMMUNICATION & WORKS DEPARTMENT
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
GAS WORKS
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S/No. DESCRIPTION QUANTITY UNIT
(Pak Rs) (Pak Rs)
G-TOTAL 1,205,923
Page 44 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BASED ON COMPOSITE SCHEDULE OF RATES - 2018
Electric Work Ground , First Floor. Abstract Sheet
Schedule
Sr. No. Description Quantity Unit Rate Total
item no
Light circuit concealed / open wiring with length upto
75 ft. (25m) from distribution board to point/switch
with 3x2.5 Sq.mm PVC insulated single core copper
conductor Pak , Pakistan Cables, Pioneer, Newage
1
or approved equivalent cables for offices/multi
storeyed buildings. (Concealed wiring with 3/4" 20
(mm )dia. PVC pipe conduit and accessories such
as bends, elbows, junction boxes etc.)
30-1 (a) Ground Floor 24 Point 4,433.25 106398.00
30-1 a +30-
First Floor 26 Point 4,876.58 126790.95
127 a
Page 45 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BASED ON COMPOSITE SCHEDULE OF RATES - 2018
Electric Work Ground , First Floor. Abstract Sheet
Schedule
Sr. No. Description Quantity Unit Rate Total
item no
Wiring of Power Plug 5 Amps. socket outlet with 4
sq.mm PVC insulated single core copper conductor
cable including 3/4" (20mm) dia. PVC conduit,
6
8.7sq.mm (10SWG) copper wire as earth continuity
conductor and wiring accessories such as bends,
elbows, junction boxes etc.
30-9 (a) Ground Floor 120 R.ft. 101.95 12234.00
30-9 a +30-
First Floor 120 R.ft. 112.15 13457.40
127 a
Page 46 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BASED ON COMPOSITE SCHEDULE OF RATES - 2018
Electric Work Ground , First Floor. Abstract Sheet
Schedule
Sr. No. Description Quantity Unit Rate Total
item no
30-15 +30-
First Floor 4 No. 1,200.43 4801.72
127 a
Page 47 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BASED ON COMPOSITE SCHEDULE OF RATES - 2018
Electric Work Ground , First Floor. Abstract Sheet
Schedule
Sr. No. Description Quantity Unit Rate Total
item no
Supply and install 25 sq.mm, 3.5 core, PVC insulated
and sheathed multicore, 600/1000V cable with
20 30-41 copper conductor directly clipped on surface of wall, 240 R.ft. 666.20 159888.00
column, beam, ceiling, etc. for power wiring.
Page 48 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BASED ON COMPOSITE SCHEDULE OF RATES - 2018
Electric Work Ground , First Floor. Abstract Sheet
Schedule
Sr. No. Description Quantity Unit Rate Total
item no
Supply and install pair of earth electrode each
comprising 24"x12" ( 600mm x 3mm) thick copper
plate buried 13 ft (4M) deep underground in upright
position in a pit and surrounded by mixture of salt
28 30-91 and charcoal (1:3), 12" (300mm) min dia around the 2 Job 60,471.15 120942.30
plate. The job also includes providing and fixing all
accessories such as nuts, bolts, washers, 2x3/0
SWG (2x70mm) copper conductor earthing lead.
Page 49 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BASED ON COMPOSITE SCHEDULE OF RATES - 2018
Electric Work Ground , First Floor. Abstract Sheet
Schedule
Sr. No. Description Quantity Unit Rate Total
item no
Extra for installing each number circuit breaker 6
35 30-116 (b) Ampere on same distribution board and bus bar (For 4 Job 2,748.00 10992.00
outgoing)
Page 50 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BASED ON COMPOSITE SCHEDULE OF RATES - 2018
Electric Work Ground , First Floor. Abstract Sheet
Schedule
Sr. No. Description Quantity Unit Rate Total
item no
TOTAL 5973617.17
Page 51 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
UNDER GROUND WATER TANK (CAPACITY 5000 GALLONS)
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QTY UNIT
(Pak Rs) (Pak Rs)
(S.I.NO 5-65-a)
Columns + walls + slabs 498 1985 1.98 Tonne
6
Providing and fixing iron bars of required dia at required
spacing with horizontal flat iron as per approved design
including making holes fixing with sunk iron screws,
painting with two coats of red oxide paint.
38 mm x 4.8 (1.5² x 1/6²) flat iron ladder.
(S.I No. 28-29 )
Page 52 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
UNDER GROUND WATER TANK (CAPACITY 5000 GALLONS)
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QTY UNIT
(Pak Rs) (Pak Rs)
1.00 9.00 1.50 13.50 Sft
7
Providing and fixing 22" dia. manhole cover in 3" (75 mm)
thick RCC 1:2:4, with steel at 5 lbs per cu.ft of concrete
with tee shaped C.I. frame of 20" clear inner dia. frame
weighing 37.5 kg. including cost of fixing material.
(S.I No. 25-14-1)
1.00 1.00 Each
TOTAL 457,864
175 % Premium above steel items 445,835
90 % Premium above Concrete items 137,061
G-TOTAL 1,040,760
Page 53 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
OVER HEAD WATER TANK (CAPACITY 2000 GALLONS)
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
Page 54 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
OVER HEAD WATER TANK (CAPACITY 2000 GALLONS)
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
Extra over respective payable items of ground floor
For first floor
b) For every additional floor above first floor.
(S.I No. 15-3 iii +46.a+b)
L/W 4 13.25 6.00 318.00 Sft
S/W 4 9.13 6.00 219.00 Sft
1 13.25 14.09 186.70 Sft
6
Providing and fixing iron bars of required dia at required
spacing with horizontal flat iron as per approved design
including making holes fixing with sunk iron screws,
painting with two coats of red oxide paint.
d) 38 mm x 4.8 (1.5² x 1/6²) flat iron ladder.
(S.I No. 28-29 )
1 6.00 1.50 9.00 Sft
Page 55 of 55