You are on page 1of 55

CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.

BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL


ABSTRAT OF COST
PSDP#
BASED ON COMPOSITE SCHEDULE OF RATES 2018
No. DESCRIPTION AMOUNT Rs.

1 CIVIL WORK GROUND FLOOR (C. Area=10000.20Sft) 76,733,777


2 CIVIL WORK FIRST FLOOR (C. Area = 10000.20Sft) 53,443,783
3 CIVIL WORK MUMTY 2,158,798
4 SEWERAGE AND WATER SUPPLY 3,142,999
5 ELECTRICAL WORKS 5,973,617
6 GAS WORKS 1,205,923
7 U.G.W.TANK 1,040,760
8 O.H.W.TANK (02Nos) 1,064,890

TOTAL 144,764,546

Add Contingency 1% 2,895,290.93


Add Consultancy Charges for Top Supervision 3 % 4,342,936.39
G-TOTAL 152,002,774
TOTAL (In Millions) 152.00

Page 1 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)

GROUND FLOOR (Covered Area=10671.20Sft)


BUILDING CIVIL WORKS
1 Excavation in foundation of buildings and bridges including
layout, dressing, refilling around structures with excavated
earth, watering & ramming lead upto 100 ft. (30m) & lift
upto 5 ft. (1.5m)
(S.I No. 3-21 A iii)
Excavation for Foundation
Column Footing
C-1-F01 3 5.00 5.00 5.00 375.00 Cft
C-2-F01 4 5.00 5.00 5.00 500.00 Cft
C-1-F02 4 6.00 6.00 5.00 720.00 Cft
C-1-F03 12 7.00 7.00 5.00 2940.00 Cft
C-1,C-1-F03 4 7.00 7.00 5.00 980.00 Cft
C-1-F04 40 8.00 8.00 5.00 12800.00 Cft
C-1,C-1-F04 1 8.00 8.00 5.00 320.00 Cft
C-1-F05 8 8.50 8.50 5.00 2890.00 Cft
C-1,C-1-F05 2 8.50 8.50 5.00 722.50 Cft
C-1-F06 2 9.00 9.00 5.00 90.00 Cft
C-1,C-2,C-2-F07 4 147.54 - 5.00 2950.76 Cft
Total 25288.26 Cft
Strip Footing
Strip on (Front & Back ) 2 75.50 2.000 5.00 1510.00 Cft
Strip on (Right & Left) 2 50.50 2.000 5.00 1010.00 Cft
Main Enterance Steps 1 18.00 3.000 1.00 54.00 Cft
Side Enterance Steps 4 12.88 3.000 1.00 154.50 Cft
Total 2728.50 Cft

Total 29417.60 Cft 7.90 232,399

2 Spraying approved anti-termite chemical mixed with water


in the ratio of 1:40
(S.I No. 3- 69-1)
Anti-Termite Spry
Column Footing
C-1-F01 3 5.00 5.00 - 150.00 Sft
C-2-F01 4 5.00 5.00 - 150.00 Sft
C-1-F02 4 6.00 6.00 - 144.00 Sft
C-1-F03 12 7.00 7.00 - 588.00 Sft
C-1,C-1-F03 4 7.00 7.00 - 2500.00 Sft
C-1-F04 40 8.00 8.00 - 2560.00 Sft
C-1,C-1-F04 1 8.00 8.00 - 64.00 Sft
C-1-F05 8 8.50 8.50 - 578.00 Sft
C-1,C-1-F05 2 8.50 8.50 - 144.50 Sft
C-1-F06 2 9.00 9.00 - 18.00 Sft
C-1,C-2,C-2-F07 4 147.54 - - 590.15 Sft
Total 7486.65 Sft
Strip Footing
Strip on (Front & Back ) 2 75.50 2.000 - 302.00 Sft
Strip on (Right & Left) 2 50.50 2.000 - 202.00 Sft
Main Enterance Steps 1 18.00 3.000 - 54.00 Sft
Side Enterance Steps 4 12.88 3.000 - 154.50 Sft
Total 712.50 Sft
Column Footing
C-1-F01 3 20.00 - 5.00 1300.00 Sft
C-2-F01 4 20.00 - 5.00 400.00 Sft
C-1-F02 4 24.00 - 5.00 480.00 Sft
C-1-F03 12 28.00 - 5.00 1680.00 Sft
C-1,C-1-F03 4 28.00 - 5.00 560.00 Sft
C-1-F04 40 32.00 - 5.00 6400.00 Sft
C-1,C-1-F04 1 32.00 - 5.00 160.00 Sft

Page 2 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
C-1-F05 8 34.00 - 5.00 1360.00 Sft
C-1,C-1-F05 2 34.00 - 5.00 340.00 Sft
C-1-F06 2 36.00 - 5.00 4500.00 Sft
C-1,C-2,C-2-F07 4 52.17 - - 208.66 Sft
Total 17388.66 Sft
Strip Footing
Strip on (Front & Back ) 4 75.50 - 5.00 1510.00 Sft
Strip on (Right & Left) 4 50.50 - 5.00 1010.00 Sft
Total 2520.00 Sft

29513.21 Sft 9.75 287,754

3 Providing and laying cement concrete using approved


coarse sand and crushed aggregate 3/4" (19mm) & down
gauge in foundation including leveling, compacting and
curing.
(S.I No. 5 - 8 e)
P.C.C 1:4:8 in Foundation
Column Footing
C-1-F01 3 5.00 5.00 0.25 18.75 Cft
C-2-F01 4 5.00 5.00 0.25 150.00 Cft
C-1-F02 4 6.00 6.00 0.25 36.00 Cft
C-1-F03 12 7.00 7.00 0.25 147.00 Cft
C-1,C-1-F03 4 7.00 7.00 0.25 100.00 Cft
C-1-F04 40 8.00 8.00 0.25 100.00 Cft
C-1,C-1-F04 1 8.00 8.00 0.25 16.00 Cft
C-1-F05 8 8.50 8.50 0.25 144.50 Cft
C-1,C-1-F05 2 8.50 8.50 0.25 36.13 Cft
C-1-F06 2 9.00 9.00 0.25 4.50 Cft
C-1,C-2,C-2-F07 4 147.54 - 0.25 147.54 Cft
Main Enterance Steps 1 18.00 3.000 0.25 13.50 Cft
Side Enterance Steps 4 12.88 3.000 0.25 38.63 Cft

Total 1000.16 Cft 200.85 200,883

4 Providing and laying in position ready mixed concrete for


reinforced cement concrete work, using cement content as
per approved design mix, manufactured in fully automatic
batching plant and transported to site of work in transit
mixer for all leads, having continuous agitated mixer,
manufactured as per mix design of specified grade for
reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying , excluding the
cost of centering, shuttering finishing and reinforcement
including cost of admixtures in recommended proportions
as per mix design to accelerate/ retard setting of concrete,
improve workability without impairing strength and
durability as per direction of the Engineer - in - charge.

4000 Psi
Additional for Shuttering and Scafolding on a, b or c for
pillars and columns of any shape
(S.I No. 5 - 26 b+d)
R.C.C in Columns and Strip Footing
Column Footing
C-1-F01 3 5.00 5.00 1.00 75.00 Cft
C-2-F01 4 5.00 5.00 1.00 100.00 Cft
C-1-F02 4 6.00 6.00 1.00 144.00 Cft
C-1-F03 12 7.00 7.00 1.25 735.00 Cft
C-1,C-1-F03 4 7.00 7.00 1.25 245.00 Cft
C-1-F04 40 8.00 8.00 1.50 3840.00 Cft
C-1,C-1-F04 1 8.00 8.00 1.50 96.00 Cft

Page 3 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
C-1-F05 8 8.50 8.50 1.50 867.00 Cft
C-1,C-1-F05 2 8.50 8.50 1.50 216.75 Cft
C-1-F06 2 9.00 9.00 1.75 283.50 Cft
C-1,C-2,C-2-F07 4 147.54 - 2.00 1180.30 Cft
Total 7782.55 Cft
Strip Footing
Strip on (Front & Back ) 2 75.50 2.000 1.00 302.00 Cft
Strip on (Right & Left) 2 50.50 2.000 1.00 202.00 Cft
Total 504.00 Cft

Total 8700.88 Cft 380.70 3,312,426

5 Providing and laying in position ready mixed concrete for


reinforced cement concrete work, using cement content as
per approved design mix, manufactured in fully automatic
batching plant and transported to site of work in transit
mixer for all leads, having continuous agitated mixer,
manufactured as per mix design of specified grade for
reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying , excluding the
cost of centering, shuttering finishing and reinforcement
including cost of admixtures in recommended proportions
as per mix design to accelerate/ retard setting of concrete,
improve workability without impairing strength and
durability as per direction of the Engineer - in - charge.

4000 Psi
Additional for Shuttering and Scafolding on a, b or c for
pillars and columns of any shape
(S.I No. 5 - 26 b+i)
R.C.C in Columns upto Plinth beam
C-1-F01 3 1.00 2.00 5.75 34.50 Cft
C-2-F01 4 2.41 - 5.75 55.52 Cft
C-1-F02 4 1.00 2.00 5.75 46.00 Cft
C-1-F03 12 1.00 2.00 5.50 132.00 Cft
C-1,C-1-F03 8 1.00 2.00 5.50 88.00 Cft
C-1-F04 40 1.00 2.00 5.25 420.00 Cft
C-1,C-1-F04 2 1.00 2.00 5.25 21.00 Cft
C-1-F05 8 1.00 2.00 5.25 84.00 Cft
C-1,C-1-F05 4 1.00 2.00 5.25 21.00 Cft
C-1-F06 2 1.00 2.00 5.00 10.00 Cft
C-1,C-2,C-2-F07 4 1.00 2.00 4.75 38.00 Cft
(C-2) 8 2.41 - 4.75 91.73 Cft

Total 1093.84 Cft 458.45 501,472

6 Providing and laying first class solid burnt brick masonry


(Brick Strength:1800psi-2000psi) including scaffolding,
raking out joints and curing in foundation and
substructure/Basement i/c cost of testing
Above 4.5" (115mm) nominal thick brickwork
Cement sand 1 : 4
(S.I No. 11-3 biii)
B.B Masonry in Foundation 9" Thick
Wall on grid (1,2,3,4 ) A to T 1 162.13 0.750 3.75 455.98 Cft
Wall on grid (19,20,21,22 ) A to T 1 154.38 0.750 3.75 434.18 Cft
Wall on grid (6) D to Q 1 47.75 0.750 3.75 134.30 Cft
Wall on grid (17 ) D to Q 1 47.75 0.750 3.75 134.30 Cft

Wall on grid ( A,B) 1 to 22 1 167.42 0.750 3.75 470.86 Cft


Wall on grid ( S,T) 1 to 22 1 164.58 0.750 3.75 462.89 Cft
Wall on grid ( Ca) 6 to 17 1 46.63 0.750 3.75 131.13 Cft

Page 4 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
Wall on grid ( Qa) 6 to 17 1 47.75 0.750 3.75 134.30 Cft
Diagonal 4 4.25 0.750 3.75 47.81 Cft
Stair 2 23.88 0.750 3.75 134.30 Cft

Total 2667.05 Cft 244.95 653,293

7 Providing and laying in position ready mixed concrete for


reinforced cement concrete work, using cement content as
per approved design mix, manufactured in fully automatic
batching plant and transported to site of work in transit
mixer for all leads, having continuous agitated mixer,
manufactured as per mix design of specified grade for
reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying , excluding the
cost of centering, shuttering finishing and reinforcement
including cost of admixtures in recommended proportions
as per mix design to accelerate/ retard setting of concrete,
improve workability without impairing strength and
durability as per direction of the Engineer - in - charge.

4000 Psi
Additional for Shuttering and Scafolding on a, b or c for
pillars and columns of any shape
(S.I No. 5 - 26 b+j)
R.C.C in Plinth band
Plinth band on grid (A ) 5 to 6,11to12 & 17to18 1 49.50 1.00 2.00 99.00 Cft
Plinth band on grid (B) 3 to 5,6 to 11,12 to 17 & 18 to 20 1 69.50 1.00 2.00 139.00 Cft
Plinth band on grid (C) 3 to 22 1 103.75 1.00 2.00 207.50 Cft
Plinth band on grid (Ca) 4 to 22 1 100.75 1.00 2.00 201.50 Cft
Plinth band on grid (D) 1 to7 & 13 to21 1 51.63 1.00 2.00 103.25 Cft
Plinth band on grid (G) 2 to 5 & 18 to 20 1 25.00 1.00 2.00 50.00 Cft
Plinth band on grid (H) 15 to 17 1 8.21 1.00 2.00 16.42 Cft
Plinth band on grid (J) 2 to 5 & 18 to 20 1 25.00 1.00 2.00 50.00 Cft
Plinth band on grid (K) 2 to 5 & 18 to 20 1 23.00 1.00 2.00 46.00 Cft
Plinth band on grid (L) 6 to 8 1 8.21 1.00 2.00 16.42 Cft
Plinth band on grid (M) 2 to 5 & 18 to 20 1 25.00 1.00 2.00 50.00 Cft
Plinth band on grid (Q) 1 to10 & 16 to22 1 71.63 1.00 2.00 143.25 Cft
Plinth band on grid (Qa) 4 to 19 1 93.25 1.00 2.00 186.50 Cft
Plinth band on grid (R) 3 to 20 1 99.50 1.00 2.00 199.00 Cft
Plinth band on grid (S) 3 to 5,6 to 11,12 to 17 & 18 to 20 1 69.50 1.00 2.00 139.00 Cft
Plinth band on grid (T ) 5to6,11to12 & 17to18 1 49.50 1.00 2.00 99.00 Cft
Plinth band on grid Diagonal 8 to 10 1 8.33 1.00 2.00 16.67 Cft
Plinth band on grid Diagonal F to H 1 8.33 1.00 2.00 16.67 Cft
Plinth band on grid Diagonal 4 4.25 1.00 2.00 34.00 Cft

Plinth band on grid (1) G to J & K to M 1 33.00 1.00 2.00 66.00 Cft
Plinth band on grid (2) D to G,J to K & M to Q 1 34.50 1.00 2.00 69.00 Cft
Plinth band on grid (3) B to C, & R to S 1 29.50 1.00 2.00 59.00 Cft
Plinth band on grid (4) C to Ca & Qa to R 1 23.50 1.00 2.00 47.00 Cft
Plinth band on grid (5 ) B to C,D to Q & R to S 1 82.50 1.00 2.00 165.00 Cft
Plinth band on grid (6) B to C,E to P & R to S 1 74.75 1.00 2.00 149.50 Cft
Plinth band on grid (9) B to C & R to S 1 25.00 1.00 2.00 50.00 Cft
Plinth band on grid (10) N to Q 1 7.00 1.00 2.00 14.00 Cft
Plinth band on grid (11) B to C 1 12.50 1.00 2.00 25.00 Cft
Plinth band on grid (12) B to C & R to S 1 27.00 1.00 2.00 54.00 Cft
Plinth band on grid (13) D to F 1 7.00 1.00 2.00 14.00 Cft
Plinth band on grid (14) B to C 1 11.50 1.00 2.00 23.00 Cft
Plinth band on grid (17) B to C,E to P 1 60.25 1.00 2.00 120.50 Cft
Plinth band on grid (18 ) B to C,D to Q & R to S 1 82.50 1.00 2.00 165.00 Cft
Plinth band on grid (19) Qa to R 1 11.75 1.00 2.00 23.50 Cft
Plinth band on grid (20) B to C, & R to S 1 29.50 1.00 2.00 59.00 Cft
Plinth band on grid (21) C to G & M to Q 1 34.75 1.00 2.00 69.50 Cft
Plinth band on grid (22) G to M 1 45.00 1.00 2.00 90.00 Cft

Page 5 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)

Total 3229.98 Cft 438.70 1,416,991

8 Providing and laying in position ready mixed concrete for


reinforced cement concrete work, using cement content as
per approved design mix, manufactured in fully automatic
batching plant and transported to site of work in transit
mixer for all leads, having continuous agitated mixer,
manufactured as per mix design of specified grade for
reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying , excluding the
cost of centering, shuttering finishing and reinforcement
including cost of admixtures in recommended proportions
as per mix design to accelerate/ retard setting of concrete,
improve workability without impairing strength and
durability as per direction of the Engineer - in - charge.

4000 Psi
Additional for Shuttering and Scafolding on a, b or c for
pillars and columns of any shape
(S.I No. 5 - 26 b+i)
R.C.C Columns upto roof level
C1 87 1.000 2.000 14.00 2436.00 Cft
C2 12 2.41 - 14.00 405.55 Cft

Total 2983.63 Cft 458.45 1,367,845

9 Providing and laying first class solid burnt brick masonry


(Brick Strength:1800psi-2000psi) including scaffolding,
raking out joints and curing in ground floor superstructure
and i/c cost of testing
Above 4.5" (115mm) nominal thick brickwork
Cement sand 1 : 4
(S.I No. 11-12 biii)
B.B Masonry in Superstructure 9" Thick
Wall on grid (A ) 5to6,11to12 & 17to18 1 40.50 0.75 12.50 379.69 Cft
Wall on grid (B) 3 to 5,6 to 11,12 to 17 & 18 to 20 1 69.50 0.75 12.50 651.56 Cft
Wall on grid (C) 3 to 5,6 to 11,12 to 17, & 18 to 20 1 63.50 0.75 12.50 595.31 Cft
Wall on grid (Ca) 7 to 16 1 47.33 0.75 12.50 443.76 Cft
Wall on grid (D) 1 to 5 & 21 to 22 1 16.00 0.75 12.50 150.00 Cft
Wall on grid (G) 1 to 5 & 18a to 22 1 24.75 0.75 12.50 232.03 Cft
Wall on grid (H) 15 to 17 1 8.21 0.75 12.50 76.95 Cft
Wall on grid (J) 1 to 5 & 18 to 22 1 24.75 0.75 12.50 232.03 Cft
Wall on grid (K) 1 to 5 & 18 to 22 1 23.00 0.75 12.50 215.63 Cft
Wall on grid (L) 6 to 8 1 8.21 0.75 12.50 76.95 Cft
Wall on grid (M) 1 to 5 & 21 to 21 1 14.00 0.75 12.50 131.25 Cft
Wall on grid (Q) 1 to 5 & 18 to22 1 27.50 0.75 12.50 257.81 Cft
Wall on grid (Qa) 7 to 16 1 47.71 0.75 12.50 447.27 Cft
Wall on grid (R) 3 to 5 & 6 to 20 1 87.50 0.75 12.50 820.31 Cft
Wall on grid (S) 3 to 5,6 to 11,12 to 17 & 18 to 20 1 69.50 0.75 12.50 651.56 Cft
Wall on grid (T ) 5 to 6,11to12 & 17to18 1 40.50 0.75 12.50 379.69 Cft
Wall on grid Diagonal L to N 1 8.33 0.75 12.50 78.13 Cft
Wall on grid Diagonal F to H 1 8.33 0.75 12.50 78.13 Cft
Diagonal 4 4.25 0.75 12.50 159.38 Cft
Projection Wall of Windows 32 2.25 0.75 9.25 499.50 Cft

Wall on grid (1) G to J & K to M 1 27.00 0.75 12.50 253.13 Cft


Wall on grid (2) D to G,J to K & M to Q 1 34.50 0.75 12.50 323.44 Cft
Wall on grid (3) A to C, & R to T 1 29.50 0.75 12.50 276.56 Cft
Wall on grid (4) C to Ca & Qa to R 1 23.50 0.75 12.50 220.31 Cft
Wall on grid (5 ) A to C,D to G,M to Q & R to T 1 51.00 0.75 12.50 478.13 Cft
Wall on grid (6) A to C,E to P & R toT 1 77.71 0.75 12.50 728.52 Cft

Page 6 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
Wall on grid (9) A to C & R to T 1 29.50 0.75 12.50 276.56 Cft
Wall on grid (10) M to Q 1 7.00 0.75 12.50 65.63 Cft
Wall on grid (11) A to C 1 15.50 0.75 12.50 145.31 Cft
Wall on grid (12) A to C & R to T 1 30.00 0.75 12.50 281.25 Cft
Wall on grid (13) D to F 1 7.00 0.75 12.50 65.63 Cft
Wall on grid (14) A to C 1 16.00 0.75 12.50 150.00 Cft
Wall on grid (17) A to C & E to P 1 61.71 0.75 12.50 578.52 Cft
Wall on grid (18 ) A to T 1 109.00 0.75 12.50 1021.88 Cft
Wall on grid (19) Qa to R 1 11.75 0.75 12.50 110.16 Cft
Wall on grid (20) A to C, & R to T 1 29.50 0.75 12.50 276.56 Cft
Wall on grid (21) D to G & M to Q 1 23.00 0.75 12.50 215.63 Cft
Wall on grid (22) G to J & K to M 1 27.00 0.75 12.50 253.13 Cft
Total 12277.27 Cft
Main Entrance Steps 2 18.00 3.00 1.00 108.00 Cft
2 16.00 2.00 0.50 32.00 Cft
2 14.00 1.00 0.50 14.00 Cft
Total 154.00 Cft

Deduction of Doors,Windows & vetilators


Opening without Doors 11 2.50 0.75 7.00 144.38 Cft
2 4.00 0.75 7.00 42.00 Cft
Verandah Openings
Openings on grid (D) 7 to 16 1 47.33 0.75 7.00 248.50 Cft
Openings on grid (Qa) 7 to 16 1 47.71 0.75 7.00 250.47 Cft
Openings on grid (6) E to P 1 47.71 0.75 7.00 250.47 Cft
Openings on grid (17) E to P 1 47.71 0.75 7.00 250.47 Cft
Diagonal 4 4.25 0.75 7.00 89.25 Cft
Lintes on Verandah Openings
Openings on grid (D) 7 to 16 1 47.33 0.75 1.00 35.50 Cft
Openings on grid (Qa) 7 to 16 1 47.71 0.75 1.00 35.78 Cft
Openings on grid (6) E to P 1 47.71 0.75 1.00 35.78 Cft
Openings on grid (17) E to P 1 47.71 0.75 1.00 35.78 Cft
Diagonal 4 4.25 0.75 1.00 12.75 Cft

D 2 6.00 0.75 8.00 72.00 Cft


D1 1 5.00 0.75 7.00 26.25 Cft
D2 1 4.50 0.75 7.00 23.63 Cft
D3 13 3.50 0.75 7.00 238.88 Cft
D4 2 2.50 0.75 7.00 26.25 Cft
Lintes on Doors 2 7.50 0.75 0.75 8.44 Cft
Lintels on Doors 1 6.50 0.75 0.75 3.66 Cft
Lintels on Doors 1 6.00 0.75 0.75 3.38 Cft
Lintels on Doors 13 5.00 0.75 0.75 36.56 Cft
Lintels on Doors 2 3.50 0.75 0.75 3.94 Cft
W 6 6.00 0.75 6.00 162.00 Cft
W1 22 4.50 0.75 6.00 445.50 Cft
W2 72 2.00 0.75 6.00 648.00 Cft
V 20 2.00 0.75 2.00 60.00 Cft
Lintels on Windows 6 7.50 0.75 0.75 25.31 Cft
Lintels on Windows 22 6.00 0.75 0.75 74.25 Cft
Lintels on Windows 72 3.00 0.75 0.75 121.50 Cft
Total 3410.67 Cft

Net 9258.00 Cft 261.75 2,423,281

10 Providing and laying first class solid burnt brick masonry


(Brick Strength:1800psi-2000psi) including scaffolding,
raking out joints and curing in ground floor superstructure
and i/c cost of testing
Upto 4.5" (115 mm) nominal thick brick work
Cement sand 1 : 4
(S.I No. 11-12 a iii )
B.B Masonry in Superstructure 4-1/2" Thick

Page 7 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
Wall without Grid 6 35.50 0.375 14.00 1118.25 Cft
Wall without Grid 1 26.50 0.375 14.00 139.13 Cft
Brick masonry for counter kitchen Shelve 1 40.00 0.375 3.00 45.00 Cft
Total 1302.38 Cft

Deduction of Doors,Windows & vetilators


D4 11 2.50 0.375 7.00 72.19 Cft
Lintels on Doors 11 3.50 0.375 0.50 7.22 Cft
Total 79.41 Cft

Net 1284.12 Cft 277.25 356,021

11 Providing and laying in position ready mixed concrete for


reinforced cement concrete work, using cement content as
per approved design mix, manufactured in fully automatic
batching plant and transported to site of work in transit
mixer for all leads, having continuous agitated mixer,
manufactured as per mix design of specified grade for
reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying , excluding the
cost of centering, shuttering finishing and reinforcement
including cost of admixtures in recommended proportions
as per mix design to accelerate/ retard setting of concrete,
improve workability without impairing strength and
durability as per direction of the Engineer - in - charge.

3000 Psi
Additional for Shuttering and Scafolding on a, b or c for
beams, lintels and cantilevers of required shape
(S.I No. 5 - 26 A+j)
R.C.C in Lintel
Lintes on Verandah Openings
Openings on grid (D) 7 to 16 1 47.33 0.75 1.00 35.50 Cft
Openings on grid (Qa) 7 to 16 1 47.71 0.75 1.00 35.78 Cft
Openings on grid (6) E to P 1 47.71 0.75 1.00 35.78 Cft
Openings on grid (17) E to P 1 47.71 0.75 1.00 35.78 Cft
Diagonal 4 4.25 0.75 1.00 12.75 Cft
Lintes on Doors 2 7.50 0.75 0.75 8.44 Cft
Lintels on Doors 1 6.50 0.75 0.75 3.66 Cft
Lintels on Doors 1 6.00 0.75 0.75 3.38 Cft
Lintels on Doors 13 5.00 0.75 0.75 36.56 Cft
Lintels on Doors 2 3.50 0.75 0.75 3.94 Cft
Lintels on Windows 8 7.50 0.75 0.75 33.75 Cft
Lintels on Windows 19 6.00 0.75 0.75 64.13 Cft
Lintels on Windows 44 3.00 0.75 0.75 74.25 Cft
Lintels on Doors 11 3.50 0.375 0.50 7.22 Cft

Total 410.45 Cft 413.50 169,723

Page 8 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
12 Providing and laying in position ready mixed concrete for
reinforced cement concrete work, using cement content as
per approved design mix, manufactured in fully automatic
batching plant and transported to site of work in transit
mixer for all leads, having continuous agitated mixer,
manufactured as per mix design of specified grade for
reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying , excluding the
cost of centering, shuttering finishing and reinforcement
including cost of admixtures in recommended proportions
as per mix design to accelerate/ retard setting of concrete,
improve workability without impairing strength and
durability as per direction of the Engineer - in - charge.

3000 Psi
Additional for Shuttering and Scafolding on a, b or c for
beams, lintels and cantilevers of required shape
(S.I No. 5 - 26 a+j)
R.C.C in Roof Beam
Roof Beam on grid (A ) 5 to 6,11to12 & 17to18 1 49.50 1.00 1.50 74.25 Cft
Roof Beam on grid (B) 3 to 5,6 to 11,12 to 17 & 18 to 20 1 69.50 1.00 1.50 104.25 Cft
Roof Beam on grid (C) 3 to 22 1 103.75 1.00 1.50 155.63 Cft
Roof Beam on grid (Ca) 4 to 22 1 100.75 1.00 1.50 151.13 Cft
Roof Beam on grid (D) 1 to7 & 13 to21 1 51.63 1.00 1.50 77.44 Cft
Roof Beam on grid (G) 2 to 6 & 17 to 20 1 49.00 1.00 1.50 73.50 Cft
Roof Beam on grid (H) 15 to 17 1 8.21 1.00 1.50 12.31 Cft
Roof Beam on grid (J) 2 to 5 & 18 to 20 1 25.00 1.00 1.50 37.50 Cft
Roof Beam on grid (K) 2 to 6 & 17 to 20 1 46.75 1.00 1.50 70.13 Cft
Roof Beam on grid (L) 6 to 8 1 8.21 1.00 1.50 12.31 Cft
Roof Beam on grid (M) 2 to 5 & 18 to 20 1 25.00 1.00 1.50 37.50 Cft
Roof Beam on grid (Q) 1 to10 & 16 to22 1 71.63 1.00 1.50 107.44 Cft
Roof Beam on grid (Qa) 4 to 19 1 93.25 1.00 1.50 139.88 Cft
Roof Beam on grid (R) 3 to 20 1 99.50 1.00 1.50 149.25 Cft
Roof Beam on grid (S) 3 to 5,6 to 11,12 to 17 & 18 to 20 1 69.50 1.00 1.50 104.25 Cft
Roof Beam on grid (T ) 5to6,11to12 & 17to18 1 49.50 1.00 1.50 74.25 Cft
Roof Beam on grid Diagonal 8 to 10 1 8.33 1.00 1.50 12.50 Cft
Roof Beam on grid Diagonal F to H 1 8.33 1.00 1.50 12.50 Cft
Roof Beam on grid Diagonal 4 4.25 1.00 1.50 25.50 Cft

Roof Beam on grid (1) G to J & K to M 1 33.00 1.00 1.50 49.50 Cft
Roof Beam on grid (2) D to G,J to K & M to Q 1 34.50 1.00 1.50 51.75 Cft
Roof Beam on grid (3) B to C, & R to S 1 29.50 1.00 1.50 44.25 Cft
Roof Beam on grid (4) C to Ca & Qa to R 1 23.50 1.00 1.50 35.25 Cft
Roof Beam on grid (5 ) B to S 1 106.00 1.00 1.50 159.00 Cft
Roof Beam on grid (6) B to C,D to Q & R to S 1 82.50 1.00 1.50 123.75 Cft
Roof Beam on grid (7) C to Ca & Qa to R 1 23.50 1.00 1.50 35.25 Cft
Roof Beam on grid (9) B to C & R to S 1 25.00 1.00 1.50 37.50 Cft
Roof Beam on grid (10) N to R 1 18.75 1.00 1.50 28.13 Cft
Roof Beam on grid (11) B to Ca & R to S 1 41.75 1.00 1.50 62.63 Cft
Roof Beam on grid (12) B to C & Qa to S 1 38.75 1.00 1.50 58.13 Cft
Roof Beam on grid (13) C to F 1 18.75 1.00 1.50 28.13 Cft
Roof Beam on grid (14) B to C & R to S 1 25.00 1.00 1.50 37.50 Cft
Roof Beam on grid (16) C to Ca & Qa to R 1 23.50 1.00 1.50 35.25 Cft
Roof Beam on grid (17) B to C,D to Q & R to S 1 82.50 1.00 1.50 123.75 Cft
Roof Beam on grid (18 ) B to S 1 106.00 1.00 1.50 159.00 Cft
Roof Beam on grid (19) Qa to R 1 11.75 1.00 1.50 17.63 Cft
Roof Beam on grid (20) B to C, & R to S 1 29.50 1.00 1.50 44.25 Cft
Roof Beam on grid (21) C to G,J to K & M to Q 1 46.25 1.00 1.50 69.38 Cft
Roof Beam on grid (22) G to J & K to K 1 33.00 1.00 1.50 49.50 Cft

Total 2815.05 Cft 413.50 1,164,024

Page 9 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
13 Providing and laying in position ready mixed concrete for
reinforced cement concrete work, using cement content as
per approved design mix, manufactured in fully automatic
batching plant and transported to site of work in transit
mixer for all leads, having continuous agitated mixer,
manufactured as per mix design of specified grade for
reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying , excluding the
cost of centering, shuttering finishing and reinforcement
including cost of admixtures in recommended proportions
as per mix design to accelerate/ retard setting of concrete,
improve workability without impairing strength and
durability as per direction of the Engineer - in - charge.

3000 Psi
Additional for Shuttering and Scafolding on a, b or c for
slabs from 6" upto 9" in thickness
(S.I No. 5 - 26 a+l)
R.C.C in Slab
Total area of Slab 1 10671.20 - 0.50 5335.60 Cft
Slab area of Enterance (Low Level) 1 651.18 - 0.50 325.59 Cft
Chajja on Windows 17 19.00 - 0.50 161.50 Cft

Total 6113.82 Cft 412.25 2,520,424

14 Providing and laying in position ready mixed concrete for


reinforced cement concrete work, using cement content as
per approved design mix, manufactured in fully automatic
batching plant and transported to site of work in transit
mixer for all leads, having continuous agitated mixer,
manufactured as per mix design of specified grade for
reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying , excluding the
cost of centering, shuttering finishing and reinforcement
including cost of admixtures in recommended proportions
as per mix design to accelerate/ retard setting of concrete,
improve workability without impairing strength and
durability as per direction of the Engineer - in - charge.

3000 Psi
Additional for Shuttering and Scafolding on a, b or c for
slabs from 6" upto 9" in thickness
(S.I No. 5 - 26 a+l)
R.C.C in Stair Case

Straight 1st.Flight 2 8.75 5.00 0.50 43.75 Cft


Straight 2nd.Flight 2 8.00 5.00 0.50 40.00 Cft
Straight 3rd.Flight 2 8.75 5.00 0.50 43.75 Cft
Half Landing 4 9.58 - 0.50 19.16 Cft
Steps /2 29.0 5.00 0.83 0.50 60.47 Cft

Total 217.48 Cft 412.25 89,657

15 Filling, watering and compacting earth under floors in


layers not exceeding 8 inchs in thickness.

Eart Filling under Floor

Rooms 8 166.750 - 2.00 2668.00 Cft


Bath 8 34.500 - 2.00 552.00 Cft
Dress 8 28.750 - 2.00 460.00 Cft
Security 1 34.50 - 2.00 69.00 Cft

Page 10 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
Water Cooler 1 32.50 - 2.00 65.00 Cft
Reception 1 32.50 - 2.00 65.00 Cft
Janitorial 1 32.50 - 2.00 65.00 Cft
Rooms 2 190.735 - 2.00 762.94 Cft
Bath 2 34.500 - 2.00 138.00 Cft
Dress 2 28.750 - 2.00 115.00 Cft
Common Hall 1 421.25 - 2.00 842.50 Cft
Dining Hall 1 622.10 - 2.00 1244.21 Cft
Bearers 1 190.76 - 2.00 381.53 Cft
Dress 1 18.69 - 2.00 37.37 Cft
Bath 1 28.75 - 2.00 57.50 Cft
Cabinet 1 54.38 - 2.00 108.75 Cft
Store 1 371.13 - 2.00 742.25 Cft
Tandoor 1 142.00 - 2.00 284.00 Cft
Kitchen 1 444.59 - 2.00 889.19 Cft
Verandah/ Cooridor 1 4790.85 - 2.00 9581.71 Cft
Stair Case 2 131.19 - 2.00 524.74 Cft
Total Quantity of Earth Filling under Floor Total 19653.69 Cft
With surplus earth from foundation etc.
(S.I No. 3-16- A)
40% of the total surplus earth 7861.48 Cft

Total 8254.55 Cft 3.80 31,367

16 Filling, watering and compacting earth under floors in


layers not exceeding 8 inchs in thickness.
With new earth excavated from outside, lead upto 100 ft.
(30m) and lift upto 5 ft. (1.5m) including royality of Clay

(S.I No. 3-16- B)


60% of the total earth borrowed from outside 11792.21 Cft

Total 12381.82 Cft 6.70 82,958

17 Providing and laying hand mixed cement concrete bed


under floors using graded Crushed Aggregate upto 1-1/2"
(37 mm) and down gauge complete with leveling, ramming,
watering and curing.
b) 1:4:8 (1 cement:4 sand and 8 shingle/bajri).
(S.I No. 14-1-b )
P.C.C 1:4:8 under Floor
Rooms 8 166.750 - 0.25 333.50 Cft
Bath 8 34.500 - 0.25 69.00 Cft
Dress 8 28.750 - 0.25 57.50 Cft
Security 1 34.50 - 0.25 8.63 Cft
Water Cooler 1 32.50 - 0.25 8.13 Cft
Reception 1 32.50 - 0.25 8.13 Cft
Janitorial 1 32.50 - 0.25 8.13 Cft
Rooms 2 190.735 - 0.25 95.37 Cft
Bath 2 34.500 - 0.25 17.25 Cft
Dress 2 28.750 - 0.25 14.38 Cft
Common Hall 1 421.25 - 0.25 105.31 Cft
Dining Hall 1 622.10 - 0.25 155.53 Cft
Bearers 1 190.76 - 0.25 47.69 Cft
Dress 1 18.69 - 0.25 4.67 Cft
Bath 1 28.75 - 0.25 7.19 Cft
Cabinet 1 54.38 - 0.25 13.59 Cft
Store 1 371.13 - 0.25 92.78 Cft
Tandoor 1 142.00 - 0.25 35.50 Cft
Kitchen 1 444.59 - 0.25 111.15 Cft
Verandah/ Cooridor 1 4790.85 - 0.25 1197.71 Cft
Stair Case 2 131.19 - 0.25 65.59 Cft

Page 11 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
Total 2579.55 Cft 145.65 375,711

18 Cement plaster using Coarse Sand on soffits of ceiling,


cantilever slabs, sides and soffits of beams, in basement
and ground floor including making edges, corners and
curing.
1/2 inch (13mm) thick cement sand plaster (1:4 Ratio)
(S.I No. 15- a iii )
Ceiling Cement Plaster 1:4
Rooms 8 166.750 - - 1334.00 Sft
Bath 8 34.500 - - 276.00 Sft
Dress 8 28.750 - - 230.00 Sft
Security 1 34.50 - - 34.50 Sft
Water Cooler 1 32.50 - - 32.50 Sft
Reception 1 32.50 - - 32.50 Sft
Janitorial 1 32.50 - - 32.50 Sft
Rooms 2 190.735 - - 381.47 Sft
Bath 2 34.500 - - 69.00 Sft
Dress 2 28.750 - - 57.50 Sft
Common Hall 1 421.25 - - 421.25 Sft
Dining Hall 1 622.10 - - 622.10 Sft
Bearers 1 190.76 - - 190.76 Sft
Dress 1 18.69 - - 18.69 Sft
Bath 1 28.75 - - 28.75 Sft
Cabinet 1 54.38 - - 54.38 Sft
Store 1 371.13 - - 371.13 Sft
Tandoor 1 142.00 - - 142.00 Sft
Kitchen 1 444.59 - - 444.59 Sft
Verandah/ Cooridor 1 4790.85 - - 4790.85 Sft
Stair Case 2 131.19 - - 262.37 Sft

Slab area of Enterance (Low Level) 1 651.18 - - 651.18 Sft


Chajja on Windows 17 19.00 - - 323.00 Sft

Total 11341.07 Sft 24.20 274,454

19 3/4 inch (19mm) thick cement plaster using Coarse Sand


on walls and columns in basement, plinth and ground floor
including making edges, corners and curing.

(S.I No. 15-4iii )


Internal Cement Plaster on Walls (1:4)
Rooms 8 52.000 - 14.25 5928.00 Sft
Bath 8 23.500 - 14.25 2679.00 Sft
Dress 8 21.500 - 14.25 2451.00 Sft
Security 1 23.50 - 14.25 334.88 Sft
Water Cooler 1 23.00 - 14.25 327.75 Sft
Reception 1 23.00 - 14.25 327.75 Sft
Janitorial 1 23.50 - 14.25 334.88 Sft
Rooms 2 56.00 - 14.25 1596.00 Sft
Bath 2 23.50 - 14.25 669.75 Sft
Dress 2 21.50 - 14.25 612.75 Sft
Common Hall 1 89.00 - 14.25 1268.25 Sft
Dining Hall 1 119.50 - 14.25 1702.88 Sft
Bearers 1 56.00 - 14.25 798.00 Sft
Dress 1 18.00 - 14.25 256.50 Sft
Bath 1 21.50 - 14.25 306.38 Sft
Cabinet 1 30.50 - 14.25 434.63 Sft
Store 1 85.00 - 14.25 1211.25 Sft
Tandoor 1 47.75 - 14.25 680.44 Sft
Kitchen 1 118.50 - 14.25 1688.63 Sft
Verandah/ Cooridor 1 772.00 - 14.25 11001.00 Sft
Stair Case 2 31.50 - 14.25 897.75 Sft

Page 12 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)

Total 37282.81 Sft 27.45 1,023,413

20 Providing and laying super white 12"x12" marble tiles floor


fine dressed on surface without winding in ground floor and
laid over 1" (25mm) thick cement sand mortar 1:2 setting
tiles with portland cement slurry over cement mortar,
jointing and washing the tiles with white cement slurry
including curing, rubbing and polishing including the cost of
cement mortar.
1/2" (13 mm) thick marble tiles floor
(S.I No. 14-9a )
Marble Tiles Flooring (Ground with out toilets )
Rooms 8 166.750 - - 1334.00 Sft
Dress 8 28.750 - - 230.00 Sft
Security 1 34.50 - - 34.50 Sft
Reception 1 32.50 - - 32.50 Sft
Rooms 2 190.735 - - 381.47 Sft
Dress 2 28.750 - - 57.50 Sft
Common Hall 1 421.25 - - 421.25 Sft
Dining Hall 1 622.10 - - 622.10 Sft
Bearers 1 190.76 - - 190.76 Sft
Dress 1 18.69 - - 18.69 Sft
Cabinet 1 54.38 - - 54.38 Sft
Store 1 371.13 - - 371.13 Sft
Stair Case 2 131.19 - - 262.37 Sft

Threshold
D 2 6.00 1.00 - 12.00 Sft
D1 1 5.00 1.00 - 5.00 Sft
D2 1 4.50 1.00 - 4.50 Sft
D3 13 3.50 1.00 - 45.50 Sft
D4 2 2.50 1.00 - 5.00 Sft
D4 11 2.50 0.50 - 13.75 Sft

Total 4301.22 Sft 227.70 979,387

21 Providing and fixing 3/8" (9mm) thick super white marble


tiles dressed on the surface in dado/skirting and facing in
ground floor over 1/2" (13mm) thick base of cement sand
mortar 1:3, setting of tiles in slurry of grey cement over
mortar base including filling the joints and washing the tiles
with white cement slurry, curing, finishing, grinding,
cleaning & polishing.
(S.I No. 14-54 a )
Marble Skirting and Dado(Internal building Walls)
Rooms 8 52.000 - 0.50 208.00 Sft
Dress 8 21.500 - 0.50 86.00 Sft
Security 1 23.50 - 0.50 11.75 Sft
Reception 1 23.00 - 0.50 11.50 Sft
Rooms 2 56.00 - 0.50 56.00 Sft
Dress 2 21.50 - 0.50 21.50 Sft
Common Hall 1 89.00 - 5.00 445.00 Sft
Dining Hall 1 119.50 - 5.00 597.50 Sft
Bearers 1 56.00 - 0.50 28.00 Sft
Dress 1 18.00 - 0.50 9.00 Sft
Cabinet 1 30.50 - 0.50 15.25 Sft
Store 1 85.00 - 0.50 42.50 Sft
Verandah/ Cooridor 1 772.00 - 5.00 3860.00 Sft
Stair Case 2 31.50 - 0.50 31.50 Sft

Total 5694.68 Sft 194.70 1,108,753

Page 13 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)

22
Providing and laying 3/4"(19mm) thick Granite polished
tiles of any size on floor of approved design in any color,
shade and pattern in ground floor over 3/8" thick base
cement sand mortar 1:3 including setting the tiles with
portland cement slurry over cement sand jointing and
washing the tiles with cement slurry of matching color
including grinding, rubbing, polishing & mortar cost.
(S.I No. 14-9a+24c )
Granite on Shelve top
1 100.00 2.00 200.00 Sft

Total 200.00 Sft 703.67 140,734

23 Providing and laying super white 12"x12" marble tiles floor


fine dressed on surface without winding in ground floor and
laid over 1" (25mm) thick cement sand mortar 1:2 setting
tiles with portland cement slurry over cement mortar,
jointing and washing the tiles with white cement slurry
including curing, rubbing and polishing including the cost of
cement mortar.
1" (25 mm) thick marble tiles floor
Extra over item 14-09 to 14-22 for the description of work
given below.
a) Extra for stair/steps.
(S.I No. 14-9b+14-24a )
Marble on Stair Case

Treads 58.0 5.00 1.00 - 290.00 Sft


Risers 62.0 5.00 0.50 - 155.00 Sft
Half Landing 4 9.58 - - 38.32 Sft

Total 507.49 Sft 336.95 170,997

24 Extra for making nosing of treads as per design and/or as


per instructions of the Engineer-in charge including
grinding marble/marble chips and polishing etc.
(S.I No. 14-22-1 )
Nosing of Tread

Treads 1.0 290.00 - - 290.00 Sft


1 54.00 - - 54.00 Sft

Total 361.20 Sft 40.60 14,665

25
Providing and laying 1/4" to 3/8" (6mm to 9mm) thick
Glazed/ Matt tiles of any colour and size in ground floor
laid over 1" (25mm) thick cement sand mortar base
including jointing and washing the tiles with white cement
slurry of matching color by using color pigment and curing
(S.I No. 14-25 a )
Glazed Tile Flooring in Toilet
Bath 8 34.500 - - 276.00 Sft
Water Cooler 1 32.50 - - 32.50 Sft
Janitorial 1 32.50 - - 32.50 Sft
Bath 2 34.500 - - 69.00 Sft
Bath 1 28.75 - - 28.75 Sft
Tandoor 1 142.00 - - 142.00 Sft
Kitchen 1 444.59 - - 444.59 Sft

Page 14 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
Total 1076.61 Sft 182.25 196,212

26 Providing and fixing 1/4" to 3/8" (6mm to 9mm) thick


Ceramic Glazed/Matt tiles (Prime Quality) of any colour
and size, as directed by Engineer-in-Charge in
dado/skirting in ground floor over 1/2" (13mm) thick base
of cement mortar 1:3, setting of tiles in slurry of grey
cement over mortar base including filling the joints and
washing the tiles with white cement slurry of matching
color, cleaning & curing.
(S.I No. 14- 64 a)
Glazed Tile Dado in Toilet
Bath 8 23.500 - 5.00 940.00 Sft
Water Cooler 1 23.00 - 5.00 115.00 Sft
Janitorial 1 23.50 - 5.00 117.50 Sft
Bath 2 23.50 - 5.00 235.00 Sft
Bath 1 21.50 - 5.00 107.50 Sft
Tandoor 1 47.75 - 5.00 238.75 Sft
Kitchen 1 118.50 - 5.00 592.50 Sft

Total 2463.56 Sft 144.05 354,876

27 1/2 inch (13mm) thick cement plaster using Coarse Sand


on walls and columns in basement, plinth and ground floor
including making edges, corners and curing.

(S.I No. 15-3 ii )


Externel Cement Plaster on Walls (1:4)
1 610.50 - 16.25 9920.63 Sft
32 5.25 - 10.00 1680.00 Sft

Total 12180.66 Sft 25.05 305,125

28 Providing and fixing First class wood frames of required


size for doors, windows, ventilators, clerestory windows,
shelves, partitions, trellis (Jafri) work.

Deodar wood
(S.I No. 16-3-a )
Wooden Door Frames
D 2 22.50 0.875 0.25 9.84 Cft
D1 1 19.50 0.875 0.25 4.27 Cft
D2 1 19.00 0.875 0.25 4.16 Cft
D3 13 18.00 0.875 0.25 51.19 Cft
D4 2 17.00 0.875 0.25 7.44 Cft
D4 11 17.00 0.5 0.25 23.38 Cft

Total 105.28 Cft 7788.85 820,002

29 Providing and fixing First class deodar wood shutters fully


panelled with same wood and fixed with approved brass
hinges and tower bolts.
2" (50 mm) thick fully panelled shutters.
(S.I No. 16-7a )
Wooden Door Shutters
D 2 6.00 - 8.00 96.00 Sft
D1 1 5.00 - 7.00 35.00 Sft
D2 1 4.50 - 7.00 31.50 Sft
D3 13 3.50 - 7.00 318.50 Sft
D4 2 2.50 - 7.00 35.00 Sft
D4 11 2.50 - 7.00 192.50 Sft

Total 743.93 Sft 1228.68 914,046

Page 15 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)

30 Providing and fixing of wooden moulded beading to door


and window framses with iron screws, plugs; 2nd Class
Teak Wood 50x12mm
(S.I No. 16-89-1 )
Wooden Door Beading
D 2 22.50 - - 45.00 Rft
D1 1 19.50 - - 19.50 Rft
D2 1 19.00 - - 19.00 Rft
D3 13 18.00 - - 234.00 Rft
D4 2 17.00 - - 34.00 Rft
D4 11 17.00 - - 187.00 Rft

Total 1077.00 Rft 37.10 39,957

31 Providing and fixing fully glazed fixed aluminium windows,


ventilators (Deluxe model - 1.6mm) of anodized
champagne or approved color of Alcop, Pakistan Cable or
any approved section as approved by Engineer incharge
including aluminium fittings, local tinted glass, lugs, cutting
holes and making good the damages to walls.

(S.I No. 28-25-1 )


Aluminium Windows
W 8 6.00 - 6.00 288.00 Sft
W1 19 4.50 - 6.00 513.00 Sft
W2 44 2.00 - 6.00 528.00 Sft
V 12 2.00 - 2.00 48.00 Sft

Total 1445.85 Sft 805.45 1,164,560

32 Providing and fixing iron grills with square bars of 3/8" size
as per approved design including welding all sides of the
section at the junction and fixing with sunk iron screws,
painting with two coats of red oxide paint and fixing in
masonry/concrete or wood
(S.I No. 28-28 - 1 )
Iron Grills on Windows
W 8 6.00 - 6.00 288.00 Sft
W1 19 4.50 - 6.00 513.00 Sft
W2 44 2.00 - 6.00 528.00 Sft
V 12 2.00 - 2.00 48.00 Sft

Total 1445.85 Sft 330.60 477,998

33 Painting with ICI/Berger or equivalent plastic emulsion


paint of approved shade in two or more coats as per
manufacturer's instructions on plastered rendered and/or
concrete surface over and including the cost of priming
coat, surface preparation, dusting, rubbing down smooth,
filling cracks, holes removing blisters and other blisters
and other imperfections in ground floor or basement. (@
atleast 1.65 Litre per 10 Sq.m)
(S.I No. 17- 8-1 )
Intrenal Paint with Plastic Emulsion Area
Ceiling Area 1 11341.07 11341.07 Sft
Internal Walls area 1 18641.40 18641.40 Sft
Total 29982.47 Sft
Deduction of Dado in Toilets 2463.56 Sft

Net 27518.91 Sft 31.90 877,853

Page 16 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
34 Applying architectural coating such as Rockwall, Durock,
Graphaito or equivalent to interior or exterior walls
including supplying all labour, materials, scaffoldings and
removal of debris etc.
(S.I No. 17.71-1 )
Graphic Art on Exterior Wall
50% of Exterior Surface 0.5 12180.66 6090.33 Sft

Total 6394.84 Sft 25.75 164,667

35 Applying french or spirit polish of approved make on wood


work in ground floor or basement
Two coats (@ atleast 1.65 Litre per 10 Sq.m)
(S.I No. 17-15 b )
Polishing on Wood work Area
2 743.93 1487.85 Sft

Total 1487.85 Sft 42.55 63,308

36 Painting with ICI/Berger or equivalent super gloss synthetic


enamel paint in two or more coats as per manufacturer's
instructions on steel and iron work over and including the
cost of priming coat, surface preparation, removing rust,
scales and dust with wire brush in ground floor or
basement. (@ atleast 1.25Litre per 10 Sq.m)

(S.I No. 17-7-1 )


Painting on Iron work
2 1445.85 2891.70 Sft

Total 2891.70 Sft 27.30 78,943

37 Providing and fixing locks with brass or specially supplied


screws including Door Closers and Floor Hinges of
approved design including cutting wood to required shape
and size with two operating keys.
(S.I.No. 16-66 e )
Main Door Lock
Main door lock kwikset make 2 - - - 2.00 Each

Total 2.00 Each 7098.00 14,196

(S.I.No. 16-66 d )
38 Internal Door Lock
Hyundi Lock
15 - - - 15.00 Each

Total 15.00 Each 2154.00 32,310

39 Providing and fixing locks with brass or specially supplied


screws including Door Closers and Floor Hinges of
approved design including cutting wood to required shape
and size with two operating keys.
(S.I.No. 16-66 a )
Toilet Lock
Union Lock
14 - - - 14.00 Each

Total 14.00 Each 763.50 10,689

(S.I.No. 16-66 f )

Page 17 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
40 Hydraulic Door Closer
Hydraulic door closer, New star make
21 21.00 Each

Total 21.00 Each 2277.00 47,817

41 Providing and fixing approved sliding bolts or aldrop bolt of


sizes with screws of same metal and galvanized iron bolts
and nuts.
ii ) 250 mm x 16 mm (10² x 5/8²) size
(S.I.No. 16-74 ii)
Sliding Bolts
55 55.00 Each

Total 55.00 Each 1154.00 63,470

42 Providing and fixing approved standard finger plate with


screws.
b) Brass finger plate 150 mm x 57 mm (6² x 2-1/4²) with
brass screws.
(S.I.No. 16-68 b)
Finger Plate 68 68.00 Each

Total 136.00 Each 498.40 67,782

43 Supply and fixing of stainless steel plates on the doors as


kick plates 1 foot wide.
( N.S.R.)
Kick Plate
D 2 6.00 - - 12.00 Rft
D1 1 5.00 - - 5.00 Rft
D2 1 4.50 - - 4.50 Rft
D3 13 3.50 - - 45.50 Rft
D4 2 2.50 - - 5.00 Rft
D4 11 2.50 - - 27.50 Rft

Total 199.00 Rft 202.50 40,298

44 Providing and fixing 2'-9" high Stair hand railing comprising


of 2½" dia 16 gauge S.S pipe hand rail fixed with 2½" dia
pipe blusters at specified distance fixed at top of steps
with expansion bolts, 2 Nos. of 16 gauge 1" dia S.S pipes
horizontally fixed with blusters, Complete in all respects.

(S.I.No. 28-82-1 )
a Stainless Steel Hand Rail of Stair Case
Hand Rail Self Supported
Stair -1 1 25.00 - - 25.00 Rft
Stair -2 1 25.00 - - 25.00 Rft

Total 50.00 Rft 2005.70 100,285

(N.S.R)
45 Hand Rail Wall Mounted
b Stair -1 1 25.00 - - 25.00 Rft
Stair -2 1 25.00 - - 25.00 Rft

Total 50.00 Rft 550.00 27,500

Page 18 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
46 Providing, fabricating and laying deformed Grade 60 steel
reinforcement (deformed bar) for all kinds of R.C.C work in
foundation, plinth and ground floor including the cost of
straightening, removal of rust, cutting, bending, binding,
wastage and providing such over-laps as are not shown on
the drawings. The cost of binding wire and cement
concrete spacer blocks or chairs for binding and holding
the reinforcement in position is inclusive upto 15 ft. (5m)
height
(S.I.NO 5-65-a)
Reinforcement
Footing 8701 38677.60 - - 38.68 Tonne
Plinth band+Lintel + Roof beam 6455 28696.23 - - 28.70 Tonne
Columns 4077 27188.07 - - 27.19 Tonne
Slabs 6114 16639.27 - - 16.64 Tonne
Stair 217 591.89 0.59 Tonne

Total 111.79 Tonne 128365.80 14,350,407

47 Providing and laying 1:2:4 cement concrete floor using


using crushed aggrgate 3/4" (19mm) and down gauge in
ground floor laid in panels including formwork,
consolidation, finishing and curing.
(S.I No. 14-2 a iv )
P.C.C 1:2:4 in Plinth Protection
1 602.00 2.00 1204.00 Sft

Total 1204.00 Sft 87.80 105,711.2

48 Providing and fixing Gypsum Board false ceiling of


approved size and texture consisting of imported powder
coated aluminum angle and tee framing (size 1" x 1")
hunged by approved suspension system, including
provision of extra framing for lights fittings, A/C diffusers
and around columns, etc, complete in all respectas
directed by the Engineer.
(S.I No. 15-58 b )
Gypsum Board false ceiling
1 13.00 - - 13.00 Sft

Total 13.00 Sft 74.70 971

Page 19 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)

48 Providing and fixing wooden box type wardrobe 22"


(550mm) deep including 3/4" (19mm) thick boxing and
shelves hanger rods, hardboard 3/16" (5mm) thick back
drawers, brass fitting, locking arrangement, handles,
internal bolts, shoe rods including painting.

Laminated board 3/4" (19mm) thick boxing, shelves and


back with 3/4" thick deodar wood vaneer board
(S.I No. 16-82-c )
Wooden cabinets and Shelves
13 5.75 10.00 747.50 Sft

Total 747.50 Sft 636.60 475,859

49 Providing and fixing of 3/4" (19mm) thick 12" x 24"


travetine sand stone in beach color (Loralai stone) on
exterior wall and cladding including with cement sand
mortar 1:3 complete in all respect.
(S.I No. 15-56-1 )
Face Stone on Exterior Wall
50% of Exterior Surface 0.5 12180.66 6090.33 Sft

Total 6394.84 Sft 136.95 875,774

50 Providing and laying 1/4" to 3/8" (6mm to 9mm) thick


Glazed/ Matt tiles of any colour and size in ground floor
laid over 1" (25mm) thick cement sand mortar base
including jointing and washing the tiles with white cement
slurry of matching color by using color pigment and curing

(S.I No. 14-25-1 )


Matt Tiles Flooring in Verandah and Cooridors
Verandah/ Cooridor 1 4790.85 - - 4790.85 Sft
Main Entrance Steps Trade 2.0 54.00 1.00 - 108.00 Sft
Main Entrance Steps Riser 2.0 60.00 0.50 - 60.00 Sft

Total 5206.80 Sft 182.25 948,939

SUB TOTAL 41,518,186


175 % Premium above steel items 25,113,213
90 % Premium above Concrete items 10,102,378
G-TOTAL 0.00 76,733,777

Page 20 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)

FIRST FLOOR (Covered Area = 10671.20Sft)

BUILDING CIVIL WORKS

1 Providing and laying in position ready mixed concrete


for reinforced cement concrete work, using cement
content as per approved design mix, manufactured in
fully automatic batching plant and transported to site of
work in transit mixer for all leads, having continuous
agitated mixer, manufactured as per mix design of
specified grade for reinforced cement concrete work
including pumping of R.M.C. from transit mixer to site of
laying , excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures
in recommended proportions as per mix design to
accelerate/ retard setting of concrete, improve
workability without impairing strength and durability as
per direction of the Engineer - in - charge.
4000 Psi
Additional for Shuttering and Scafolding on a, b or c for
pillars and columns of any shape
For first floor
(S.I No. 5 - 26 b+i+n)
R.C.C Columns upto roof level
C1 87 1.000 2.000 14.00 2436.00 Cft
C2 12 2.41 - 14.00 405.55 Cft

Total 2983.63 Cft 504.30 1,504,629

2 Providing and laying first class solid burnt brick masonry


(Brick Strength:1800psi-2000psi) including scaffolding,
raking out joints and curing in ground floor
superstructure and i/c cost of testing
Above 4.5" (115mm) nominal thick brickwork
Cement sand 1 : 4
Extra for brick masonry (Brick Strength:1800psi-2000psi)
in first floor
For first floor
(S.I No. 11-12 biii+26a)
B.B Masonry in Superstructure 9" Thick
Wall on grid (A ) 5to6,11to12 & 17to18 1 40.50 0.75 12.50 379.69 Cft
Wall on grid (B) 3 to 5,6 to 11,12 to 17 & 18 to 20 1 69.50 0.75 12.50 651.56 Cft
Wall on grid (C) 3 to 5,6 to 11,12 to 17, & 18 to 20 1 63.50 0.75 12.50 595.31 Cft
Wall on grid (Ca) 7 to 16 1 47.33 0.75 12.50 443.76 Cft
Wall on grid (D) 1 to 5 & 18 to 22 1 27.50 0.75 12.50 257.81 Cft
Wall on grid (G) 1 to 5 & 18a to 22 1 28.75 0.75 12.50 269.53 Cft
Wall on grid (H) 15 to 17 1 8.21 0.75 12.50 76.95 Cft
Wall on grid (J) 1 to 5 & 18 to 22 1 24.75 0.75 12.50 232.03 Cft
Wall on grid (K) 1 to 5 & 18 to 22 1 23.00 0.75 12.50 215.63 Cft
Wall on grid (L) 6 to 8 1 8.21 0.75 12.50 76.95 Cft
Wall on grid (M) 1 to 5 & 18 to 21 1 26.50 0.75 12.50 248.44 Cft
Wall on grid (Q) 1 to 5 & 18 to22 1 27.50 0.75 12.50 257.81 Cft
Wall on grid (Qa) 7 to 16 1 47.71 0.75 12.50 447.27 Cft
Wall on grid (R) 3 to 5 & 6 to 20 1 87.50 0.75 12.50 820.31 Cft
Wall on grid (S) 3 to 5,6 to 11,12 to 17 & 18 to 20 1 69.50 0.75 12.50 651.56 Cft
Wall on grid (T ) 5 to 6,11to12 & 17to18 1 40.50 0.75 12.50 379.69 Cft
Wall on grid Diagonal L to N 1 8.33 0.75 12.50 78.13 Cft
Wall on grid Diagonal F to H 1 8.33 0.75 12.50 78.13 Cft
Diagonal 4 4.25 0.75 12.50 159.38 Cft
Projection Wall of Windows 32 2.25 0.75 9.25 499.50 Cft

Page 21 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
Wall on grid (1) G to J & K to M 1 27.00 0.75 12.50 253.13 Cft
Wall on grid (2) D to G,J to K & M to Q 1 34.50 0.75 12.50 323.44 Cft
Wall on grid (3) A to C, & R to T 1 29.50 0.75 12.50 276.56 Cft
Wall on grid (4) C to Ca & Qa to R 1 23.50 0.75 12.50 220.31 Cft
Wall on grid (5 ) A to C,D to G,J to K,M to Q & R to T 1 61.50 0.75 12.50 576.56 Cft
Wall on grid (6) A to C,E to P & R toT 1 77.71 0.75 12.50 728.52 Cft
Wall on grid (9) A to C & R to T 1 29.50 0.75 12.50 276.56 Cft
Wall on grid (10) M to Q 1 7.00 0.75 12.50 65.63 Cft
Wall on grid (11) A to C & R to T 1 30.00 0.75 12.50 281.25 Cft
Wall on grid (12) A to C & R to T 1 30.00 0.75 12.50 281.25 Cft
Wall on grid (13) D to F 1 7.00 0.75 12.50 65.63 Cft
Wall on grid (14) A to C & R to T 1 29.50 0.75 12.50 276.56 Cft
Wall on grid (17) A to C & E to P & R to T 1 76.21 0.75 12.50 714.46 Cft
Wall on grid (18 ) A to T 1 109.00 0.75 12.50 1021.88 Cft
Wall on grid (19) C to Ca & Qa to R 1 23.75 0.75 12.50 222.66 Cft
Wall on grid (20) A to C, & R to T 1 29.50 0.75 12.50 276.56 Cft
Wall on grid (21) D to G,J to K & M to Q 1 34.50 0.75 12.50 323.44 Cft
Wall on grid (22) G to J & K to M 1 27.00 0.75 12.50 253.13 Cft
Total 12570.00 Cft
Main Entrance Steps 2 18.00 3.00 1.00 108.00 Cft
2 16.00 2.00 0.50 32.00 Cft
2 14.00 1.00 0.50 14.00 Cft
Total 154.00 Cft

Deduction of Doors,Windows & vetilators


Opening without Doors 18 2.50 0.75 7.00 236.25 Cft

Verandah Openings
Openings on grid (D) 7 to 16 1 47.33 0.75 7.00 248.50 Cft
Openings on grid (Qa) 7 to 16 1 47.71 0.75 7.00 250.47 Cft
Openings on grid (6) E to P 1 47.71 0.75 7.00 250.47 Cft
Openings on grid (17) E to P 1 47.71 0.75 7.00 250.47 Cft
Diagonal 4 4.25 0.75 7.00 89.25 Cft
Lintes on Verandah Openings
Openings on grid (D) 7 to 16 1 47.33 0.75 1.00 35.50 Cft
Openings on grid (Qa) 7 to 16 1 47.71 0.75 1.00 35.78 Cft
Openings on grid (6) E to P 1 47.71 0.75 1.00 35.78 Cft
Openings on grid (17) E to P 1 47.71 0.75 1.00 35.78 Cft
Diagonal 4 4.25 0.75 1.00 12.75 Cft

D3 18 3.5 0.75 7.00 330.75 Cft


Lintels on Doors 18 5.00 0.75 0.75 50.63 Cft
W 6 6.00 0.75 6.00 162.00 Cft
W1 22 4.50 0.75 6.00 445.50 Cft
W2 72 2.00 0.75 6.00 550.00 Cft
V 20 2.00 0.75 2.00 60.00 Cft
Lintels on Windows 6 7.50 0.75 0.75 25.31 Cft
Lintels on Windows 22 6.00 0.75 0.75 74.25 Cft
Lintels on Windows 72 3.00 0.75 0.75 121.50 Cft
Total 3300.95 Cft

Net 9894.20 Cft 280.85 2,778,786

10 Providing and laying first class solid burnt brick masonry


(Brick Strength:1800psi-2000psi) including scaffolding,
raking out joints and curing in ground floor
superstructure and i/c cost of testing
Upto 4.5" (115 mm) nominal thick brick work
Cement sand 1 : 4
For first floor
(S.I No. 11-12 a iii+26a )
B.B Masonry in Superstructure 4-1/2" Thick
Wall without Grid 18 35.50 0.375 14.00 3354.75 Cft

Page 22 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
Brick masonry for counter kitchen Shelve 1 40.00 0.375 3.00 45.00 Cft
Total 3399.75 Cft

Deduction of Doors,Windows & vetilators


D2 2 3.00 0.375 7.00 15.75 Cft
D4 18 2.50 0.375 7.00 118.13 Cft
Lintels on Doors 18 3.50 0.375 0.50 11.81 Cft
Total 129.94 Cft

Net 3433.30 Cft 296.35 1,017,459

4 Providing and laying in position ready mixed concrete


for reinforced cement concrete work, using cement
content as per approved design mix, manufactured in
fully automatic batching plant and transported to site of
work in transit mixer for all leads, having continuous
agitated mixer, manufactured as per mix design of
specified grade for reinforced cement concrete work
including pumping of R.M.C. from transit mixer to site of
laying , excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures
in recommended proportions as per mix design to
accelerate/ retard setting of concrete, improve
workability without impairing strength and durability as
per direction of the Engineer - in - charge.
3000 Psi
Additional for Shuttering and Scafolding on a, b or c for
beams, lintels and cantilevers of required shape
For first floor
(S.I No. 5 - 26 a+j+n)
R.C.C in Lintels
Lintes on Verandah Openings
Openings on grid (D) 7 to 16 1 47.33 0.75 1.00 35.50 Cft
Openings on grid (Qa) 7 to 16 1 47.71 0.75 1.00 35.78 Cft
Openings on grid (6) E to P 1 47.71 0.75 1.00 35.78 Cft
Openings on grid (17) E to P 1 47.71 0.75 1.00 35.78 Cft
Diagonal 4 4.25 0.75 1.00 12.75 Cft

Lintels on Doors 4 5.00 0.75 0.75 11.25 Cft

Lintels on Windows 6 7.50 0.75 0.75 25.31 Cft


Lintels on Windows 22 6.00 0.75 0.75 74.25 Cft
Lintels on Windows 72 3.00 0.75 0.75 121.50 Cft

Total 407.30 Cft 454.85 185,262

5 Providing and laying in position ready mixed concrete


for reinforced cement concrete work, using cement
content as per approved design mix, manufactured in
fully automatic batching plant and transported to site of
work in transit mixer for all leads, having continuous
agitated mixer, manufactured as per mix design of
specified grade for reinforced cement concrete work
including pumping of R.M.C. from transit mixer to site of
laying , excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures
in recommended proportions as per mix design to
accelerate/ retard setting of concrete, improve
workability without impairing strength and durability as
per direction of the Engineer - in - charge.
3000 Psi

Page 23 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
Additional for Shuttering and Scafolding on a, b or c for
beams, lintels and cantilevers of required shape
For first floor
(S.I No. 5 - 26 a+j+n)
R.C.C in Roof Beam
Roof Beam on grid (A ) 5 to 6,11to12 & 17to18 1 49.50 1.00 1.50 74.25 Cft
Roof Beam on grid (B) 3 to 5,6 to 11,12 to 17 & 18 to 20 1 69.50 1.00 1.50 104.25 Cft
Roof Beam on grid (C) 3 to 22 1 103.75 1.00 1.50 155.63 Cft
Roof Beam on grid (Ca) 4 to 22 1 100.75 1.00 1.50 151.13 Cft
Roof Beam on grid (D) 1 to7 & 13 to21 1 51.63 1.00 1.50 77.44 Cft
Roof Beam on grid (G) 2 to 6 & 17 to 20 1 49.00 1.00 1.50 73.50 Cft
Roof Beam on grid (H) 15 to 17 1 8.21 1.00 1.50 12.31 Cft
Roof Beam on grid (J) 2 to 5 & 18 to 20 1 25.00 1.00 1.50 37.50 Cft
Roof Beam on grid (K) 2 to 6 & 17 to 20 1 46.75 1.00 1.50 70.13 Cft
Roof Beam on grid (L) 6 to 8 1 8.21 1.00 1.50 12.31 Cft
Roof Beam on grid (M) 2 to 5 & 18 to 20 1 25.00 1.00 1.50 37.50 Cft
Roof Beam on grid (Q) 1 to10 & 16 to22 1 71.63 1.00 1.50 107.44 Cft
Roof Beam on grid (Qa) 4 to 19 1 93.25 1.00 1.50 139.88 Cft
Roof Beam on grid (R) 3 to 20 1 99.50 1.00 1.50 149.25 Cft
Roof Beam on grid (S) 3 to 5,6 to 11,12 to 17 & 18 to 20 1 69.50 1.00 1.50 104.25 Cft
Roof Beam on grid (T ) 5to6,11to12 & 17to18 1 49.50 1.00 1.50 74.25 Cft
Roof Beam on grid Diagonal 8 to 10 1 8.33 1.00 1.50 12.50 Cft
Roof Beam on grid Diagonal F to H 1 8.33 1.00 1.50 12.50 Cft
Roof Beam on grid Diagonal 4 4.25 1.00 1.50 25.50 Cft

Roof Beam on grid (1) G to J & K to M 1 33.00 1.00 1.50 49.50 Cft
Roof Beam on grid (2) D to G,J to K & M to Q 1 34.50 1.00 1.50 51.75 Cft
Roof Beam on grid (3) B to C, & R to S 1 29.50 1.00 1.50 150.00 Cft
Roof Beam on grid (4) C to Ca & Qa to R 1 23.50 1.00 1.50 50.00 Cft
Roof Beam on grid (5 ) B to S 1 106.00 1.00 1.50 50.00 Cft
Roof Beam on grid (6) B to C,D to Q & R to S 1 82.50 1.00 1.50 123.75 Cft
Roof Beam on grid (7) C to Ca & Qa to R 1 23.50 1.00 1.50 35.25 Cft
Roof Beam on grid (9) B to C & R to S 1 25.00 1.00 1.50 37.50 Cft
Roof Beam on grid (10) N to R 1 18.75 1.00 1.50 20.00 Cft
Roof Beam on grid (11) B to Ca & R to S 1 41.75 1.00 1.50 62.63 Cft
Roof Beam on grid (12) B to C & Qa to S 1 38.75 1.00 1.50 58.13 Cft
Roof Beam on grid (13) C to F 1 18.75 1.00 1.50 28.13 Cft
Roof Beam on grid (14) B to C & R to S 1 25.00 1.00 1.50 37.50 Cft
Roof Beam on grid (16) C to Ca & Qa to R 1 23.50 1.00 1.50 35.25 Cft
Roof Beam on grid (17) B to C,D to Q & R to S 1 82.50 1.00 1.50 123.75 Cft
Roof Beam on grid (18 ) B to S 1 106.00 1.00 1.50 159.00 Cft
Roof Beam on grid (19) Qa to R 1 11.75 1.00 1.50 17.63 Cft
Roof Beam on grid (20) B to C, & R to S 1 29.50 1.00 1.50 44.25 Cft
Roof Beam on grid (21) C to G,J to K & M to Q 1 46.25 1.00 1.50 350.00 Cft
Roof Beam on grid (22) G to J & K to K 1 33.00 1.00 1.50 450.00 Cft

Total 3533.78 Cft 454.85 1,607,338

6 Providing and laying in position ready mixed concrete


for reinforced cement concrete work, using cement
content as per approved design mix, manufactured in
fully automatic batching plant and transported to site of
work in transit mixer for all leads, having continuous
agitated mixer, manufactured as per mix design of
specified grade for reinforced cement concrete work
including pumping of R.M.C. from transit mixer to site of
laying , excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures
in recommended proportions as per mix design to
accelerate/ retard setting of concrete, improve
workability without impairing strength and durability as
per direction of the Engineer - in - charge.

Page 24 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
3000 Psi
Additional for Shuttering and Scafolding on a, b or c for
slabs from 6" upto 9" in thickness
(S.I No. 5 - 26 a+l)
R.C.C in Slab
Total area of Slab 1 10671.20 - 0.50 5335.60 Cft
Chajja on Windows 18 19.00 - 0.50 171.00 Cft

Total 5781.93 Cft 453.48 2,621,961

7 Providing and laying in position ready mixed concrete


for reinforced cement concrete work, using cement
content as per approved design mix, manufactured in
fully automatic batching plant and transported to site of
work in transit mixer for all leads, having continuous
agitated mixer, manufactured as per mix design of
specified grade for reinforced cement concrete work
including pumping of R.M.C. from transit mixer to site of
laying , excluding the cost of centering, shuttering
finishing and reinforcement including cost of admixtures
in recommended proportions as per mix design to
accelerate/ retard setting of concrete, improve
workability without impairing strength and durability as
per direction of the Engineer - in - charge.

3000 Psi
Additional for Shuttering and Scafolding on a, b or c for
slabs from 6" upto 9" in thickness
(S.I No. 5 - 26 a+l)
R.C.C in Stair Case

Straight 1st.Flight 2 8.75 5.00 0.50 43.75 Cft


Straight 2nd.Flight 2 8.00 5.00 0.50 40.00 Cft
Straight 3rd.Flight 2 8.75 5.00 0.50 43.75 Cft
Half Landing 4 9.58 - 0.50 19.16 Cft
Steps /2 29.0 5.00 0.83 0.50 60.47 Cft

Total 217.48 Cft 453.48 98,622

8 Providing and laying hand mixed cement concrete bed


under floors using graded Crushed Aggregate upto 1-
1/2" (37 mm) and down gauge complete with leveling,
ramming, watering and curing.
b) 1:4:8 (1 cement:4 sand and 8 shingle/bajri).
(S.I No. 14-1-b+14-69 a )
P.C.C 1:4:8 under Floor
Rooms 12 166.750 - 0.125 250.13 Cft
Bath 12 34.500 - 0.125 51.75 Cft
Dress 12 28.750 - 0.125 43.13 Cft
Janitorial 1 66.13 - 0.125 8.27 Cft
Rooms 6 190.735 - 0.125 143.05 Cft
Bath 6 34.500 - 0.125 25.88 Cft
Dress 6 28.750 - 0.125 21.56 Cft
Store 1 66.13 - 0.125 8.27 Cft
Verandah/ Cooridor 1 4790.85 - 0.125 598.86 Cft
Stair Case 2 131.19 - 0.125 32.80 Cft

Total 1242.86 Cft 160.22 199,124

Page 25 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
9 Cement plaster using Coarse Sand on soffits of ceiling,
cantilever slabs, sides and soffits of beams, in basement
and ground floor including making edges, corners and
curing.
1/2 inch (13mm) thick cement sand plaster (1:4 Ratio)

Extra over respective payable items of ground floor


For first floor
(S.I No. 15- a iii +46a)
Ceiling Cement Plaster 1:4
Rooms 12 166.750 - - 2001.00 Sft
Bath 12 34.500 - - 414.00 Sft
Dress 12 28.750 - - 345.00 Sft
Janitorial 1 66.13 - - 66.13 Sft
Rooms 6 190.735 - - 1144.41 Sft
Bath 6 34.500 - - 207.00 Sft
Dress 6 28.750 - - 172.50 Sft
Store 1 66.13 - - 66.13 Sft
Verandah/ Cooridor 1 4790.85 - - 4790.85 Sft
Stair Case 2 131.19 - - 262.37 Sft

Total 9942.86 Sft 26.62 264,679

10 3/4 inch (19mm) thick cement plaster using Coarse Sand


on walls and columns in basement, plinth and ground
floor including making edges, corners and curing.

Extra over respective payable items of ground floor


For first floor
(S.I No. 15-4iii +46a)
Internal Cement Plaster on Walls (1:4)
Rooms 12 52.000 - 14.25 8892.00 Sft
Bath 12 23.500 - 14.25 4018.50 Sft
Dress 12 21.500 - 14.25 3676.50 Sft
Janitorial 1 34.50 - 14.25 491.63 Sft
Rooms 6 56.00 - 14.25 4788.00 Sft
Bath 6 23.50 - 14.25 2009.25 Sft
Dress 6 21.50 - 14.25 1838.25 Sft
Store 1 34.50 - 14.25 491.63 Sft
Verandah/ Cooridor 1 772.00 - 14.25 11001.00 Sft
Stair Case 2 31.50 - 14.25 897.75 Sft

Total 40009.73 Sft 30.20 1,208,094

11
Providing and laying super white 12"x12" marble tiles
floor fine dressed on surface without winding in ground
floor and laid over 1" (25mm) thick cement sand mortar
1:2 setting tiles with portland cement slurry over cement
mortar, jointing and washing the tiles with white cement
slurry including curing, rubbing and polishing including
the cost of cement mortar.
1/2" (13 mm) thick marble tiles floor
Extra over item 14-9 to 14-22-1 for the description of
work given below:
Extra for first floor
(S.I No. 14-9a+24c )
Marble Tiles Flooring
Rooms 12 166.750 - - 2001.00 Sft
Dress 12 28.750 - - 345.00 Sft
Rooms 6 190.735 - - 1144.41 Sft
Dress 6 28.750 - - 172.50 Sft
Store 1 66.13 - - 66.13 Sft

Page 26 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
Threshold
D3 18 3.5 1.00 - 63.00 Sft

D2 2 3.00 0.50 - 3.00 Sft


D4 18 2.50 0.50 - 22.50 Sft

Total 4008.41 Sft 231.10 926,344

12 Providing and fixing 3/8" (9mm) thick super white marble


tiles dressed on the surface in dado/skirting and facing in
ground floor over 1/2" (13mm) thick base of cement
sand mortar 1:3, setting of tiles in slurry of grey cement
over mortar base including filling the joints and washing
the tiles with white cement slurry, curing, finishing,
grinding, cleaning & polishing.
Slab area of Enterance (Low Level)
Extra for first floor
(S.I No. 14-54 a+55b )
Marble Skirting and Dado(Internal building Walls)
Rooms 12 52.000 - 0.50 312.00 Sft
Dress 12 21.500 - 0.50 129.00 Sft
Rooms 6 56.00 - 0.50 168.00 Sft
Dress 6 21.50 - 0.50 64.50 Sft
Store 1 34.50 - 0.50 17.25 Sft
Verandah/ Cooridor 1 772.00 - 5.00 3860.00 Sft
Stair Case 2 31.50 - 0.50 31.50 Sft

Total 4811.36 Sft 198.10 953,131

13
Providing and laying 3/4"(19mm) thick Granite polished
tiles of any size on floor of approved design in any color,
shade and pattern in ground floor over 3/8" thick base
cement sand mortar 1:3 including setting the tiles with
portland cement slurry over cement sand jointing and
washing the tiles with cement slurry of matching color
including grinding, rubbing, polishing & mortar cost.
(S.I No. 14-9a+24c )
Granite on Shelve top
1 100.00 2.00 200.00 Sft

Total 200.00 Sft 703.67 140,734

14
Providing and laying super white 12"x12" marble tiles
floor fine dressed on surface without winding in ground
floor and laid over 1" (25mm) thick cement sand mortar
1:2 setting tiles with portland cement slurry over cement
mortar, jointing and washing the tiles with white cement
slurry including curing, rubbing and polishing including
the cost of cement mortar.
1" (25 mm) thick marble tiles floor
Extra over item 14-09 to 14-22 for the description of
work given below.
a) Extra for stair/steps.
Extra for first floor
(S.I No. 14-9c+14-24a+c )
Marble on Stair Case
Treads 58.0 5.00 1.00 - 290.00 Sft
Risers 62.0 5.00 0.50 - 155.00 Sft
Half Landing 4 9.58 - - 38.32 Sft

Page 27 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
Total 507.49 Sft 498.95 253,210

15 Extra for making nosing of treads as per design and/or


as per instructions of the Engineer-in charge including
grinding marble/marble chips and polishing etc.

Extra over item 14-09 to 14-22 for the description of


work given below.
Extra for first floor
(S.I No. 14-22-1+24c )
Nosing of Tread
Treads 1.0 290.00 - - 290.00 Sft

Total 290.00 Sft 44.00 12,760

16 Providing and laying 1/4" to 3/8" (6mm to 9mm) thick


Glazed/ Matt tiles of any colour and size in ground floor
laid over 1" (25mm) thick cement sand mortar base
including jointing and washing the tiles with white cement
slurry of matching color by using color pigment and
curing
Extra for first floor
(S.I No. 14-25 a+c )
Glazed Tile Flooring in Toilet
Bath 12 34.500 - - 414.00 Sft
Janitorial 1 66.13 - - 66.13 Sft
Bath 6 34.500 - - 207.00 Sft

Total 721.48 Sft 184.70 133,258

17 Providing and fixing 1/4" to 3/8" (6mm to 9mm) thick


Ceramic Glazed/Matt tiles (Prime Quality) of any colour
and size, as directed by Engineer-in-Charge in
dado/skirting in ground floor over 1/2" (13mm) thick base
of cement mortar 1:3, setting of tiles in slurry of grey
cement over mortar base including filling the joints and
washing the tiles with white cement slurry of matching
color, cleaning & curing.
Extra for first floor
(S.I No. 14- 64 a)
Glazed Tile Dado in Toilet
Bath 12 23.500 - 5.00 1410.00 Sft
Janitorial 1 34.50 - 5.00 172.50 Sft
Bath 6 23.50 - 5.00 705.00 Sft

Total 2401.88 Sft 146.50 351,875

18 1/2 inch (13mm) thick cement plaster using Coarse Sand


on walls and columns in basement, plinth and ground
floor including making edges, corners and curing.

Extra over respective payable items of ground floor


For first floor
(S.I No. 15-3 iii +46.a)
Externel Cement Plaster on Walls (1:4)
1 610.50 - 15.25 9310.13 Sft
36 5.25 - 7.25 1370.25 Sft

Total 11214.39 Sft 25.25 283,107

Page 28 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
19 Providing and fixing First class wood frames of required
size for doors, windows, ventilators, clerestory windows,
shelves, partitions, trellis (Jafri) work.

Deodar wood
Extra for respective payable item of ground floor
For first floor
(S.I No. 16-3-a+87a )
Wooden Door Frames
D3 18 18.00 0.875 0.25 70.88 Cft

D2 2 17.50 0.50 0.25 4.38 Cft


D4 18 17.00 0.50 0.25 38.25 Cft

Total 119.18 Cft 8567.74 1,021,060

20 Providing and fixing First class deodar wood shutters


fully panelled with same wood and fixed with approved
brass hinges and tower bolts.
2" (50 mm) thick fully panelled shutters.
Extra for respective payable item of ground floor
For first floor
(S.I No. 16-7c+87a )
Wooden Door Shutters
D3 18 3.5 - 7.00 441.00 Sft

D2 2 3.00 - 7.00 42.00 Sft


D4 18 2.50 - 7.00 315.00 Sft

Total 837.90 Sft 1351.55 1,132,462

21 Providing and fixing of wooden moulded beading to door


and window framses with iron screws, plugs; 2nd Class
Teak Wood 50x12mm
(S.I No. 16-89-1 )
Wooden Door Beading
D3 18 18.00 - - 324.00 Rft

D2 2 17.50 - - 35.00 Rft


D4 18 17.00 - - 306.00 Rft

Total 1330.00 Rft 37.10 49,343

22 Providing and fixing fully glazed fixed aluminium


windows, ventilators (Deluxe model - 1.6mm) of
anodized champagne or approved color of Alcop,
Pakistan Cable or any approved section as approved by
Engineer incharge including aluminium fittings, local
tinted glass, lugs, cutting holes and making good the
damages to walls.
(S.I No. 28-25-1+67a )
Aluminium Windows
W 6 6.00 - 6.00 216.00 Sft
W1 22 4.50 - 6.00 594.00 Sft
W2 72 2.00 - 6.00 864.00 Sft
V 20 2.00 - 2.00 80.00 Sft

Total 1841.70 Sft 886.00 1,631,737

Page 29 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
23 Providing and fixing iron grills with square bars of 3/8"
size as per approved design including welding all sides
of the section at the junction and fixing with sunk iron
screws, painting with two coats of red oxide paint and
fixing in masonry/concrete or wood
Extra for respective payable item of ground floor
For first floor
(S.I No. 28-28 - 1+67a )
Iron Grills on Windows
W 6 6.00 - 6.00 216.00 Sft
W1 22 4.50 - 6.00 594.00 Sft
W2 72 2.00 - 6.00 864.00 Sft
V 20 2.00 - 2.00 80.00 Sft

Total 1841.70 Sft 363.66 669,753

24 Painting with ICI/Berger or equivalent plastic emulsion


paint of approved shade in two or more coats as per
manufacturer's instructions on plastered rendered and/or
concrete surface over and including the cost of priming
coat, surface preparation, dusting, rubbing down smooth,
filling cracks, holes removing blisters and other blisters
and other imperfections in ground floor or basement. (@
atleast 1.65 Litre per 10 Sq.m)

Extra for respective payable item of ground floor


For first floor
(S.I No. 17- 8-1+47a )
Intrenal Paint with Plastic Emulsion Area
Ceiling Area 1 9942.86 9942.86 Sft
Internal Walls area 1 40009.73 40009.73 Sft
Total 49952.58 Sft
Deduction of Dado in Toilets 7213.24 Sft

Total 42739.34 Sft 35.09 1,499,724

25 Applying architectural coating such as Rockwall, Durock,


Graphaito or equivalent to interior or exterior walls
including supplying all labour, materials, scaffoldings and
removal of debris etc.
(S.I No. 17.71-1+47 )
Graphic Art on Exterior Wall
50% of Exterior Surface 0.5 12592.39 6296.20 Sft

Total 6611.01 Sft 28.33 187,257

26 Applying french or spirit polish of approved make on


wood work in ground floor or basement
Two coats (@ atleast 1.65 Litre per 10 Sq.m)
Extra for respective payable item of ground floor
For first floor
(S.I No. 17-15 b +47a)
Polishing on Wood work Area
2 838 1675.80 Sft

Total 1675.80 Sft 46.81 78,436

Page 30 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
27 Painting with ICI/Berger or equivalent super gloss
synthetic enamel paint in two or more coats as per
manufacturer's instructions on steel and iron work over
and including the cost of priming coat, surface
preparation, removing rust, scales and dust with wire
brush in ground floor or basement. (@ atleast 1.25Litre
per 10 Sq.m)
Extra for respective payable item of ground floor
For first floor
(S.I No. 17-7-1 +47a)
Painting on Iron work
2 1842 3683.40 Sft

Total 3683.40 Sft 30.03 110,613

28 Providing and fixing locks with brass or specially


supplied screws including Door Closers and Floor
Hinges of approved design including cutting wood to
required shape and size with two operating keys.
(S.I.No. 16-66 d )
Internal Door Lock
Hyundi Lock
18 - - - 18.00 Each

Total 18.00 Each 2154.00 38,772

29 Providing and fixing locks with brass or specially


supplied screws including Door Closers and Floor
Hinges of approved design including cutting wood to
required shape and size with two operating keys.
Extra for respective payable item of ground floor
For first floor
(S.I.No. 16-66 a )
Toilet Lock
Union Lock
20 - - - 20.00 Each

Total 20.00 Each 763.50 15,270

30 Hydraulic Door Closer


Hydraulic door closer, New star make
(S.I.No. 16-66 f + 87a )

18 18.00 Each

Total 18.00 Each 2504.70 45,085

31 Providing and fixing approved sliding bolts or aldrop bolt


of sizes with screws of same metal and galvanized iron
bolts and nuts.
ii ) 250 mm x 16 mm (10² x 5/8²) size
Add extra for respective payable item of ground floor.

a)For first floor.


(S.I.No. 16-74 ii + 87a)
Sliding Bolts
56 56.00 Each

Total 56.00 Each 1269.40 71,086

32 Providing and fixing approved standard finger plate with


screws.

Page 31 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
b) Brass finger plate 150 mm x 57 mm (6² x 2-1/4²) with
brass screws.
Add extra for respective payable item of ground floor.

a)For first floor.


(S.I.No. 16-68 b + 87a)
Finger Plate
76 57.00 4332.00 Each

Total 4332.00 Each 548.24 2,374,976

33 Supply and fixing of stainless steel plates on the doors


as kick plates 1 foot wide.
( N.S.R.)
Kick Plate
D3 18 3.5 - - 63.0 Rft

D2 2 3.00 - - 6.0 Rft


D4 18 2.50 - - 45.0 Rft

Total 228.00 Rft 202.50 46,170

34 Providing and fixing 2'-9" high Stair hand railing


comprising of 2½" dia 16 gauge S.S pipe hand rail fixed
with 2½" dia pipe blusters at specified distance fixed at
top of steps with expansion bolts, 2 Nos. of 16 gauge 1"
dia S.S pipes horizontally fixed with blusters, Complete
in all respects.
Add extra for respective payable item of ground floor.

(S.I.No. 28-82-1+67a )
a Stainless Steel Hand Rail of Stair Case
Hand Rail Self Supported
Stair -1 1 25.00 - - 25.00 Rft
Stair -2 1 25.00 - - 25.00 Rft

Total 50.00 Rft 2206.27 110,314

35 Hand Rail Wall Mounted


(N.S.R)
b Stair -1 1 25.00 - - 25.00 Rft
Stair -2 1 25.00 - - 25.00 Rft

Total 50.00 Rft 550.00 27,500

36 Providing, fabricating and laying deformed Grade 60


steel reinforcement (deformed bar) for all kinds of R.C.C
work in foundation, plinth and ground floor including the
cost of straightening, removal of rust, cutting, bending,
binding, wastage and providing such over-laps as are
not shown on the drawings. The cost of binding wire and
cement concrete spacer blocks or chairs for binding and
holding the reinforcement in position is inclusive upto 15
ft. (5m) height

Extra for first floor on Item No.5-65(a)


(S.I.NO 5-65-a+f)
Reinforcement
Roof beam 3534 15708.52 - - 15.71 Tonne
Lintels 407 1810.57 1.81 Tonne
Columns 2984 19894.47 - - 19.89 Tonne
Slabs 5782 15736.00 - - 15.74 Tonne

Page 32 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
Stair 217 591.89 0.59 Tonne

Total 53.74 Tonne 130465.80 7,011,422

37 Providing and laying 1:2:4 P.C.C roof screeding using


crushed stone 3/4" (19mm) including formwork,
consolidation, finishing and curing
c) 75.00 mm (3²) nominal thick P.C.C. roof screeding.

a)For first floor.


(S.I No. 14- 68 c+d )
P.C.C.1:2:4 Roof Screeding Area
1 10671.20 10671.20 Sft

Total 10671.20 Sft 86.60 924,126

38 Providing and laying first class solid burnt brick masonry


(Brick Strength:1800psi-2000psi) including scaffolding,
raking out joints and curing in ground floor
superstructure and i/c cost of testing
Above 4.5" (115mm) nominal thick brickwork
Cement sand 1 : 4
Extra for brick masonry (Brick Strength:1800psi-2000psi)
in first floor
Extra for brick or tile masonry in every additional floor
over first floor.
(S.I No. 11-12 biii+26a+b)
B.B Masonry in Parapet wall 9" Thick
1 787.50 0.75 3.00 1771.88 Cft

Total 1771.88 Cft 293.10 519,337

39 1/2 inch (13mm) thick cement plaster using Coarse Sand


on walls and columns in basement, plinth and ground
floor including making edges, corners and curing.

Add extra for respective payable item of ground floor.

a) For first floor.


b) For every additional floor above first floor.
(S.I No. 15-3 iii+46 a+b )
Externel Cement Plaster on Parapet Walls (1:4)
1 787.50 - 7.00 5512.50 Sft

Total 5512.50 Sft 26.97 148,651

40 Providing and fixing wooden box type wardrobe 22"


(550mm) deep including 3/4" (19mm) thick boxing and
shelves hanger rods, hardboard 3/16" (5mm) thick back
drawers, brass fitting, locking arrangement, handles,
internal bolts, shoe rods including painting.

Laminated board 3/4" (19mm) thick boxing, shelves and


back with 3/4" thick deodar wood vaneer board
(S.I No. 16-82-c )
Wooden cabinets and Shelves
18 5.75 10.00 1035.00 Sft

Total 1035.00 Sft 636.60 658,881

Page 33 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
41 Providing and fixing of 3/4" (19mm) thick 12" x 24"
travetine sand stone in beach color (Loralai stone) on
exterior wall and cladding including with cement sand
mortar 1:3 complete in all respect.
(S.I No. 15-56-1 )
Face Stone on Exterior Wall
50% of Exterior Surface 0.5 12592.39 6296.20 Sft

Total 6611.01 Sft 136.95 905,377

42 Providing and laying 1/4" to 3/8" (6mm to 9mm) thick


Glazed/ Matt tiles of any colour and size in ground floor
laid over 1" (25mm) thick cement sand mortar base
including jointing and washing the tiles with white cement
slurry of matching color by using color pigment and
curing
(S.I No. 14-25-1+c )
Matt Tiles Flooring in Verandah and Cooridors
Verandah/ Cooridor 1 4790.85 - - 4790.85 Sft

Total 5030.40 Sft 184.70 929,114

SUB TOTAL 34,746,838


175 % Premium above steel items 12,269,988
90 % Premium above Concrete items 6,426,957
G-TOTAL 0.00 53,443,783

Page 34 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)

MUMTY (Covered Area = 290.50x2 =581.0Sft)


BUILDING CIVIL WORKS

1 Providing and laying in position ready mixed concrete for


reinforced cement concrete work, using cement content
as per approved design mix, manufactured in fully
automatic batching plant and transported to site of work
in transit mixer for all leads, having continuous agitated
mixer, manufactured as per mix design of specified grade
for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying , excluding the
cost of centering, shuttering finishing and reinforcement
including cost of admixtures in recommended proportions
as per mix design to accelerate/ retard setting of
concrete, improve workability without impairing strength
and durability as per direction of the Engineer - in -
charge.
4000 Psi
Additional for Shuttering and Scafolding on a, b or c for
pillars and columns of any shape
For first floor
Extra for every additional floor over first floor.
(S.I No. 5 - 26 b+i+n+o)
R.C.C Columns upto roof level
C2 8 2.41 - 10.00 193.04 Cft

Total 202.69 Cft 538.68 109,186

2 Providing and laying first class solid burnt brick masonry


(Brick Strength:1800psi-2000psi) including scaffolding,
raking out joints and curing in ground floor superstructure
and i/c cost of testing
Above 4.5" (115mm) nominal thick brickwork
Cement sand 1 : 4
Extra for brick masonry (Brick Strength:1800psi-2000psi)
in first floor
Extra for every additional floor over first floor.
(S.I No. 11-12 biii+26a+b)
Wall 2 55.750 0.750 8.50 710.81 Cft
Total 710.81 Cft
Deduction of Doors,Windows & vetilators
Lintels on Doors 2 5.00 0.75 0.75 5.63 Cft
Lintels on Windows 6 7.50 0.75 0.75 25.31 Cft
D2 2 3.50 0.75 7.00 36.75 Cft
W1 6 6.00 0.75 6.00 162.00 Cft
Total 198.75 Cft

Net 537.67 Cft 293.10 157,589.79

Page 35 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
3 Providing and laying in position ready mixed concrete for
reinforced cement concrete work, using cement content
as per approved design mix, manufactured in fully
automatic batching plant and transported to site of work
in transit mixer for all leads, having continuous agitated
mixer, manufactured as per mix design of specified grade
for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying , excluding the
cost of centering, shuttering finishing and reinforcement
including cost of admixtures in recommended proportions
as per mix design to accelerate/ retard setting of
concrete, improve workability without impairing strength
and durability as per direction of the Engineer - in -
charge.
3000 Psi
Additional for Shuttering and Scafolding on a, b or c for
beams, lintels and cantilevers of required shape
For first floor
Extra for every additional floor over first floor.
(S.I No. 5 - 26 a+j+n)
R.C.C 1:2:4 in Lintel
Lintels on Doors 2 5.00 0.75 0.75 5.63 Cft
Lintels on Windows 6 7.50 0.75 0.75 25.31 Cft

Total 32.48 Cft 485.86 15,782.94

4 Providing and laying in position ready mixed concrete for


reinforced cement concrete work, using cement content
as per approved design mix, manufactured in fully
automatic batching plant and transported to site of work
in transit mixer for all leads, having continuous agitated
mixer, manufactured as per mix design of specified grade
for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying , excluding the
cost of centering, shuttering finishing and reinforcement
including cost of admixtures in recommended proportions
as per mix design to accelerate/ retard setting of
concrete, improve workability without impairing strength
and durability as per direction of the Engineer - in -
charge.
3000 Psi
Additional for Shuttering and Scafolding on a, b or c for
beams, lintels and cantilevers of required shape
For first floor
Extra for every additional floor over first floor.
(S.I No. 5 - 26 a+j+n)
R.C.C in Roof Beam
Roof Beam 2 55.750 1.00 1.50 167.25 Cft

Total 175.61 Cft 485.86 85,324

Page 36 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
5 Providing and laying in position ready mixed concrete for
reinforced cement concrete work, using cement content
as per approved design mix, manufactured in fully
automatic batching plant and transported to site of work
in transit mixer for all leads, having continuous agitated
mixer, manufactured as per mix design of specified grade
for reinforced cement concrete work including pumping of
R.M.C. from transit mixer to site of laying , excluding the
cost of centering, shuttering finishing and reinforcement
including cost of admixtures in recommended proportions
as per mix design to accelerate/ retard setting of
concrete, improve workability without impairing strength
and durability as per direction of the Engineer - in -
charge.
3000 Psi
Additional for Shuttering and Scafolding on a, b or c for
slabs from 6" upto 9" in thickness
(S.I No. 5 - 26 a+l)
R.C.C 1:2:4 in Slab 6" Thick
2 290.50 - 0.500 290.50 Cft

Total 290.50 Cft 484.39 140,716.38

6
Providing and fixing single leaf steel door with frame fully
panelled with M.S sheet 16 gauge (1.59mm) painted with
two coats of red oxide paint with brass fitting of approved
make including cost of fabrication, iron lugs, cutting holes
and making good the damages to walls.
Extra for first floor
Extra for every additional floor above first floor
(S.I No. 28-6-1+67a +b)
Steel Door
2 3.50 7.00 49.00 Sft

Total 49.00 Sft 692.13 33,914.55

7 Cement plaster using Coarse Sand on soffits of ceiling,


cantilever slabs, sides and soffits of beams, in basement
and ground floor including making edges, corners and
curing.

1/2 inch (13mm) thick cement sand plaster (1:4 Ratio)


Extra over respective payable items of ground floor
For first floor
b) For every additional floor above first floor.
(S.I No. 15- a iii +46a+b)
Ceiling Cement Plaster 1:4 Area
2 243.38 486.76 Sft

Total 486.76 Sft 28.44 13,841.02

8 3/4 inch (19mm) thick cement plaster using Coarse Sand


on walls and columns in basement, plinth and ground
floor including making edges, corners and curing.

Extra over respective payable items of ground floor


For first floor
b) For every additional floor above first floor.
(S.I No. 15-4iii +46a+b)
Internal Cement Plaster on Walls (1:4)

Page 37 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
2 60.00 - 10.00 1200.00 Sft

Total 1200.00 Sft 26.97 32,359.50

9 Providing and fixing fully glazed fixed aluminium windows,


ventilators (Deluxe model - 1.6mm) of anodized
champagne or approved color of Alcop, Pakistan Cable
or any approved section as approved by Engineer
incharge including aluminium fittings, local tinted glass,
lugs, cutting holes and making good the damages to
walls.
(S.I No. 28-25-1 )
Aluminium Windows
W1 6 6.00 - 6.00 216.00 Sft

Total 216.00 Sft 946.40 204,423.21

10 Providing and fixing iron grills with square bars of 3/8"


size as per approved design including welding all sides of
the section at the junction and fixing with sunk iron
screws, painting with two coats of red oxide paint and
fixing in masonry/concrete or wood
Extra for respective payable item of ground floor
For first floor
(S.I No. 28-28 - 1+67a+b )
Iron Grills on Windows
W1 6 6.00 - 6.00 216.00 Sft

Total 216.00 Sft 388.46 83,906.28

11 Painting with ICI/Berger or equivalent plastic emulsion


paint of approved shade in two or more coats as per
manufacturer's instructions on plastered rendered and/or
concrete surface over and including the cost of priming
coat, surface preparation, dusting, rubbing down smooth,
filling cracks, holes removing blisters and other blisters
and other imperfections in ground floor or basement. (@
atleast 1.65 Litre per 10 Sq.m)

(S.I No. 5 - 26 a+j+n)


For first floor
Extra for each additional floor above first floor.
(S.I No. 17- 8-1+47a+b )
Intrenal Paint with Plastic Emulsion Area
Ceiling Area 1 487 486.76 Sft
Internal Walls area 1 1200 1200.00 Sft

Total 1686.76 Sft 37.48 63,223.98

12 Applying weather resistant paint coating such as ICI


weather shield,Berger weather coat or equivalent to
interior or exterior walls or ceiling including supplying all
labour, materials, scaffoldings and removal of debris etc.
@ atleast 3.50 litre per 10 Sq.m.
Extra for respective payable item of ground floor
For first floor
Extra for each additional floor above first floor.
(S.I No. 17-69 -1+47a+b )
Externel Paint with Weather Coat Area
Externel Walls area 2 66 10.50 1375.50 Sft

Total 1375.50 Sft 37.37 51,395.56

Page 38 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)

13 Painting with ICI/Berger or equivalent super gloss


synthetic enamel paint in two or more coats as per
manufacturer's instructions on steel and iron work over
and including the cost of priming coat, surface
preparation, removing rust, scales and dust with wire
brush in ground floor or basement. (@ atleast 1.25Litre
per 10 Sq.m)
Extra for respective payable item of ground floor
For first floor
Extra for each additional floor above first floor.
(S.I No. 17-7-1 +47a+b)
Painting on Iron work
Grill 2 216 432.00 Sft
Door 2 3.50 7.00 49.00 Sft

Total 962.00 Sft 32.08 30,858.56

14
Extra for first floor on Item No.5-65(a)
(S.I.NO 5-65-a+f)
Reinforcement
Lintels 32 144.40 0.14 Tonne
Columns 203 1351.53 - - 1.35 Tonne
Slabs 291 790.62 - - 0.79 Tonne

Total 2.29 Tonne 130465.80 298,316

SUB TOTAL 1,320,837


175 % Premium above steel items 522,053
90 % Premium above Concrete items 315,908
G-TOTAL 0.00 2,158,798

Page 39 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
SEWERAGE AND WATER SUPPLY
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)

SEWERAGE AND WATER SUPPLY

BATH ROOM FIXTURES AND ACCESSORIES


1 Providing and fixing European type glazed earthenware
water closet ICL Ifo/Forte or approved equivalent make
including cost of inlet pipe, lid cistern kit, stop cock deluxe
and other accessories, fitting material such as brackets,
PVC down pipe where required, rubber rings/washers,
making requisite number of holes in walls, plinth and floor
for pipe connection and making good with approved
material.
(S.I No. 23-3-a)

15 15.00 Each 13527.00 202905.00

2 Providing and fixing squatting type water closet with


integral treads ICL Boch/Karam Cera or approved
equivalent make including cost of inlet pipe cistern and lid
cistern kit, stop cock deluxe type and other accessories,
fittings, brackets, PVC down pipe, rubber rings/washers,
making requisite number of holes in walls, plinth and floor
for pipe connection and making good with approved
material.
W.C. Indian/Desi/902 with glazed earthen ware 4" (100
mm) trap
(S.I No. 23-2-ai)

14 14.00 Each 7295.40 102135.60

3 Providing and fixing export quality glazed earthen ware


wash basin manufactured by ICL Boch/Karam Cera or
equivalent approved make with single hole chromium
plated mixer tap 1/2" (15mm), pillar tap delux, stop cocks,
C.I. or W.I. brackets 6" (150mm) built into walls 1.5"
(40mm) C.P. brass waste with malleable iron or C.P. brass
trap with malleable iron or brass union and making
requisite number of holes in walls, plinth and floor for pipe
connections and making good with approved material.

Wash basin 24" (610 mm) Futura without pedestal


Extra over above for providing and fixing white glazed
earthen ware pedestal manufactured by ICL/Karam Cera or
approved equivalent make.
(S.I No. 23-5 b-i+d)

29 29.00 Each 12193.35 353607.15

4 Providing and fixing superior quality C.P. bib cock of


approved make.
Grohe European Spout (Product Code 13252000)
1/2" (12 mm) dia.
(S.I No. 23-34 ba)

29 29.00 Each 5331.00 154599.00

5 Providing and fixing standing shower concealed in wall with


approved quality control valves, mixer unit and moveable
shower head.
(S.I No. 23-11-1)

29 29.00 Each 12540.00 363660.00

Page 40 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
SEWERAGE AND WATER SUPPLY
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
6
Providing and fixing looking mirror of Belgium/ Malaysian/
Indonesian glass with chromium plated screws.
(S.I No. 23-15-1)
29 2.00 2.00 116.00 Sft

116.00 Sft 137.10 15903.60

7 Providing and fixing C.P. brass telephonic shower including


holder clamps, screw and bib cock.
(S.I No. 23-15-1) 29 29.00 Each

29.00 Each 3863.25 112034.25

8 Providing and fixing soap dish.


(S.I No. 23-29 a)
29 29.00 Each

29.00 Each 915.00 26535.00

9 Providing and fixing approved quality chromium plated


towel rail with bracket and screws.
(S.I No. 23-13-a)
29 29.00 Each

29.00 Each 1923.00 55767.00

WATER SUPPLY
10 Providing and fixing superior quality gun-metal peet/gate
valve (Class150) of approved make.
(S.I No. 23-39)
i) 15 mm(1/2") dia. 42 42.00 No.s 265.50 11151.00
ii) 20 mm (.75²) i/d. 30 30.00 No.s 331.50 9945.00
iii) 25 mm(1") dia. 10 10.00 No.s 479.25 4792.50

11 Providing, laying, cutting, jointing, testing and disinfecting


PPRC pipes confirming to ISO 4427, PN-20, complete in
all respects with specials and valves etc. including all
fittings, connnections and jointing material

(S.I No. 27-47)

20mm 1 1800.00 1800.00 Rft 30.20 54,360.00


25mm 1 2000.00 2000.00 Rft 49.86 99,720.00
32 mm 1 2500.00 2500.00 Rft 55.96 139,900.00
SEWERAGE SYSTEM
12 Providing and fixing floor trap of approved self cleaning
design with screwed down grating with or without a vent
arm with and including making requisite number of holes in
walls, plinth and floor for pipe connection and making good
with
C.I. floor trap 6" x 2" and 6" x 3" size with grating.
(S.I No. 23-9a)
62 62.00 Each 1455.00 90210.00

Page 41 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
SEWERAGE AND WATER SUPPLY
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
13 Providing manhole type 'A' size 24" x 18" (inside
dimensions) as per approved design and specifications
complete for 4" to 12" dia pipes upto 4 ft. (1.2 m) depth with
16" dia.Concrete Cover fixed in 4" thick RCC 1:2:4 slab
(with 5 lbs per Cu.ft. or 80 kg/Cu.m of steel), burnt brick
masonry walls 9" (225 mm) thick set in 1:3 cement sand
mortar, 6" thick 1:3:6 cement concrete in foundation, 4" av.
thickness 1:2:4 cement concrete in benching and 1/2"
(13mm) thick cement sand plaster in 1:3 to all inside wall
surfaces, channels and benching including making
requisite number of main and branch channels but
excluding the cost of excavation, back filling and disposal
of excavated stuff.

(S.I No. 25-4(a))

10 10.00 Each 12811.70 128117.00

14 Providing manhole type 'B' size 36" x 30" (inside


dimensions) x 48" deep as per approved design and
specifications complete for 4" to 12" dia. pipe 4ft to 7'-6"
depth with 18" dia (inside) Concrete Cover fixed in 6" thick
RCC 1:2:4 slab with 5 lbs. per Cu.ft steel and brick
masonry walls set in 1:3 cement sand mortar,6" thick 1:3:6
cement concrete foundation, 4" av. thick 1:2:4 cement
concrete in benching and 1/2" (13mm) thick cement plaster
in 1:3 cement sand mortar, to all inner wall surfaces,
channels and benching including providing and making
requisite number of main and branch channels but
excluding the cost of excavation, back filling, disposal of
excavated stuff.
(S.I No. 25-5(a))

8 8.00 Each 21057.10 168456.80

15 Providing and Installing uPVC pipe IIL, Dadex or


equivalent make registered with PSQCA in tubewell bore
hole and/or laying, cutting, jointing and testing uPVC pipe
lines in trenches.
Class B
(S.I No. 25-20 a)
3" dia 1 1000.00 - - 1000.00 Rft 163.45 163,450.00
4" dia (Including Rain Pipe) 1 1200.00 - - 1200.00 Rft 242.60 291,120.00
6" dia 1 1000.00 - - 1000.00 Rft 470.80 470,800.00

Page 42 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
SEWERAGE AND WATER SUPPLY
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
16 Excavation in open cutting for sewers and manholes as
shown in drawings, dressing to correct sections and
dimensions according to templates and levels and
removing surface water in all types of soil except rock
(i) The rate includes back filling after laying of sewer, which
is payable separately.
(ii) The rate for close/open shuttering & timbering will be as
per item No. 3-43 & 3-44 where actually used at site.

(S.I No. 3-42 Aiii)


1 1000.00 2.00 3.00 6000.00 Cft
Manhole 10 4.50 3.00 2.50 337.50 Cft
Manhole 8 4.50 3.00 4.50 486.00 Cft

7505.85 Cft 4.40 33025.74

17 Providing and fixing gulley trap with 4" (100mm) outlet,


complete with 4" (100mm) thick 1:2:4 cement concrete
using 3/4" (19mm) crushed aggregate for bed and kerb,
1/2" (13mm) thick cement plaster 1:3, 12"x12"x18" deep
inside dimension chamber with C.I. grating 6"x6" cover and
frame 12"x12".
Cement concrete gulley trap 6" x 6" x 4" (150 x 150 x 100
mm) with C.I. cover and frame weighing not less than 10
kg.
(S.I No. 25-2a )
20 20.00 Each

20.00 Each 4540.200 90804.00

TOTAL 3,142,999

S
G-TOTAL 0.00 3,142,999

Page 43 of 55
COMMUNICATION & WORKS DEPARTMENT
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
GAS WORKS
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S/No. DESCRIPTION QUANTITY UNIT
(Pak Rs) (Pak Rs)

1 Providing, laying, cutting, jointing, testing and disinfecting


G.I pipe manufactured by ILL or equivalent gas line
including the cost of jointing material.

(S.I No. 23-52)


i) 15 mm (½") dia 500.00 Rft 184.20 92100
ii) 20 mm (0.75") dia 1000.00 Rft 234.75 234750
iii) 25mm (1") dia 300.00 Rft 328.25 98475
iv) 40mm (1.5") dia 100.00 Rft 511.00 51100

2 Providing and fixing brass ball valvewith unsoldered


copper ball
(S.I No. 23-6(a,b )
a) 15mm (½") dia 30.00 Each 138.00 4140
b) 20mm (.75") dia 5.00 Each 192.00 960

3 Providing and laying Non Asbestos Cement Fibre


building and sanitary pipe with cement chaulked or comet
joint including cost of sockets, bends and specials.

(S.I No. 23-45 b )


1600.00 Rft 242.10 387360

4 Supply and fix gas items including all accessories and


fittings such as G.I pipe, rubber pipe, specials, gas stop
cocks etc.
(S.I No. 23-66 a+d)

a Gyser 35 gallons capacity. 8.00 Nos. 13311.00 106488


d Gas room heater (ordinary, double burner) 29.00 Nos. 7950.00 230550

SUB TOTAL 1,205,923

G-TOTAL 1,205,923

Page 44 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BASED ON COMPOSITE SCHEDULE OF RATES - 2018
Electric Work Ground , First Floor. Abstract Sheet
Schedule
Sr. No. Description Quantity Unit Rate Total
item no
Light circuit concealed / open wiring with length upto
75 ft. (25m) from distribution board to point/switch
with 3x2.5 Sq.mm PVC insulated single core copper
conductor Pak , Pakistan Cables, Pioneer, Newage
1
or approved equivalent cables for offices/multi
storeyed buildings. (Concealed wiring with 3/4" 20
(mm )dia. PVC pipe conduit and accessories such
as bends, elbows, junction boxes etc.)
30-1 (a) Ground Floor 24 Point 4,433.25 106398.00
30-1 a +30-
First Floor 26 Point 4,876.58 126790.95
127 a

Concealed / open wiring from point to switch length


upto 30 ft.(10m) including any switch to switch wiring
with 3x1.5 mm PVC insulated single core copper
2 conduct Pakistan Cables, Pioneer , Newage or as
approved equivalent cables, (Concealed wiring with
3/4" 20 (mm ) dia.PVC conduit and acessories such
as bends, elbows , junction boxes etc. )
30-3 (a) Ground Floor 190 Point 1,877.30 356687.00
30-3 (a) +30-
First Floor 196 Point 2,065.03 404745.88
127a

Concealed /open wiring from point to point with


length upto 10 ft. (3m) Sq.mm PVC insulated single
3 core copper conductor with 3x1.5 Pakistan Cables,
Pioneer, Newage or approved equivalent cables.

30-4 (a) Ground Floor 70 Point 563.20 39424.00


30-4 +30-
First Floor 72 Point 619.52 44605.44
127 (a)

Concealed/open wiring for two way light points such


that two light points are controlled by 2 numbers two
way switches and length from (12.5 m) with 3 x 1.5
4
Sq mm PVC insulated single core copper conductor
Pakistan Cables, Pioneer, Newage or approved
equivalent cables. switches to point is upto 40 ft.
30-6 (a) Ground Floor 2 Point 3,284.65 6569.30
30-6 a +30-
First Floor 2 Point 3,613.12 7226.23
127 a

Concealed/open wiring for 5 Amp. Socket outlets


from nearest available circuit with a length upto 20
ft. (6m) with 3x1.5 Sq.mm PVC insulated single
core copper conductor Pakistan Cables, Pioneer,
5
Newage or approved equivalent cables. (Concealed
wiring with 3/4" -20 mm) dia. PVC conduit and
accessories such as bends, elbows, junction boxes
etc)
30-8 (a) Ground Floor 75 Point 1,469.55 110216.25
30-8 a +30-
First Floor 78 Point 1,616.51 126087.39
127 a

Page 45 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BASED ON COMPOSITE SCHEDULE OF RATES - 2018
Electric Work Ground , First Floor. Abstract Sheet
Schedule
Sr. No. Description Quantity Unit Rate Total
item no
Wiring of Power Plug 5 Amps. socket outlet with 4
sq.mm PVC insulated single core copper conductor
cable including 3/4" (20mm) dia. PVC conduit,
6
8.7sq.mm (10SWG) copper wire as earth continuity
conductor and wiring accessories such as bends,
elbows, junction boxes etc.
30-9 (a) Ground Floor 120 R.ft. 101.95 12234.00
30-9 a +30-
First Floor 120 R.ft. 112.15 13457.40
127 a

Wiring of 5 Amps. socket outlet with 2.5 sq.mm PVC


insulated single core copper conductor cable
including 3/4" (20mm) dia. PVC conduit, 8.7sq.mm
(10SWG) copper wire as earth continuity conductor
7
and wiring accessories such as bends, elbows,
junction boxes etc. (for Lighting Circut From Switch
Board To Other Switch Boards)

30-10 Ground Floor 450 R.ft. 69.55 31297.50


30-10 +30-
First Floor 500 R.ft. 76.51 38252.50
127 a

Supply and install 1-gang, 5 Amp, 250 Volt,. plate


8 type mouldedn switch including appropriate size
plastic box to be fixed recessed I wall.
30-11 Ground Floor 9 No. 515.40 4638.60
30-11 +30-
First Floor 10 No. 566.94 5669.40
127 a

Supply and install 2-gang, 5 Amp, 250 Volt,. plate


9 type mouldedn switch including appropriate size
plastic box to be fixed recessed I wall.
30-12 Ground Floor 8 No 720.20 5761.60
30-12 +30-
First Floor 8 No 792.22 6337.76
127 a

Supply and install 3-gang, 5 Amp, 250 Volt,. plate


10 type mouldedn switch including appropriate size
plastic box to be fixed recessed I wall.
30-13 Ground Floor 12 No. 845.80 10149.60
30-13 +30-
First Floor 12 No. 930.38 11164.56
127 a

Supply and install 4-gang, 5 Amp, 250 Volt,. plate


11 type mouldedn switch including appropriate size
plastic box to be fixed recessed I wall.
30-14 Ground Floor 18 No. 976.70 17580.60
30-14 +30-
First Floor 20 No. 1,074.37 21487.40
127 a

Supply and installation of 5 Amp. 250 Volt, moulded,


two-way single pole, flush mounting type light
12
control single switch including appropriate size
plastic box to be fixed recessed in wall.
30-15 Ground Floor 2 No. 1,091.30 2182.60

Page 46 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BASED ON COMPOSITE SCHEDULE OF RATES - 2018
Electric Work Ground , First Floor. Abstract Sheet
Schedule
Sr. No. Description Quantity Unit Rate Total
item no
30-15 +30-
First Floor 4 No. 1,200.43 4801.72
127 a

Supply and install combined 2/3 pin 5 Amps, 250


13 Volt switch socket unit including plastic box to be
fixed recessed in wall.
30-19 Ground Floor 75 No. 938.75 70406.25
30-19 +30-
First Floor 78 No. 1,032.63 80544.75
127 a

Supply and install combined 3 pin 15 Amps. 250


14 Volt switch socket unit including plastic box to be
fixed recessed in wall.
30-20 Ground Floor 4 No. 1,045.00 4180.00
30-20 +30-
First Floor 4 No. 1,149.50 4598.00
127 a

Supply and installation of 1" (25mm) dia PVC


15 concealed conduit including all accessories such as
bends, elbows etc.
30-22 Ground Floor 1200 R.ft. 24.65 29580.00
30-22 +30-
First Floor 1230 R.ft. 27.12 33351.45
127 a

Supply and installation of 1.5" (40mm) dia PVC


16 Conduit including all accessories such as bends,
elbows etc.
30-24 Ground Floor 150 R.ft. 39.85 5977.50
30-24+30-
First Floor 150 R.ft. 43.84 6575.25
127 a

Supply and installation of 2" (50mm) dia PVC


17 Conduit including all accessories such as bends,
elbows etc.
30-25 Ground Floor 30 R.ft. 54.10 1623.00
30-25 +30-
First Floor 200 R.ft. 59.51 11902.00
127 a

Supply and install 10 sq.mm PVC insultated


single core 600/1000V.cable with copper conductor
18
in already concealed PVC conduit. Green Color For
E.C.C .
30-35 Ground Floor 370 R.ft. 70.70 26159.00
30-35 +30-
First Floor 80 R.ft. 77.77 6221.60
127 a

Supply and install 16 sq.mm PVC insultated


19 single core 600/1000V.cable with copper conductor
in already concealed PVC conduit.
30-36 Ground Floor 110 R.ft. 359.50 39545.00
30-36 +30-
First Floor 110 R.ft. 395.45 43499.50
127 a

Page 47 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BASED ON COMPOSITE SCHEDULE OF RATES - 2018
Electric Work Ground , First Floor. Abstract Sheet
Schedule
Sr. No. Description Quantity Unit Rate Total
item no
Supply and install 25 sq.mm, 3.5 core, PVC insulated
and sheathed multicore, 600/1000V cable with
20 30-41 copper conductor directly clipped on surface of wall, 240 R.ft. 666.20 159888.00
column, beam, ceiling, etc. for power wiring.

Supply and install 35 sq.mm, 3.5 core, PVC insulated


and sheathed multicore, 600/1000V cable with
21 30-42 copper conductor directly clipped on surface of wall, 220 R.ft. 851.00 187220.00
column, beam, ceiling, etc. for power wiring.

Supply and install 70 sq.mm, 3.5 core, PVC


insulated and sheathed multicore, 600/1000V cable
22 30-43 with copper conductor directly clipped on surface of 250 R.ft. 1621.05 405262.50
wall, column, beam, ceiling, etc. for power wiring.

Supply and install surface mounted flourescent light


23 fixture with batten and one No. 20W. Lamps, Philips
type P-120 or approved equivalent.
30-68 Ground Floor 17 No. 1,311.40 22293.80
30-68 +30- First Floor 18
No. 1,442.54 25965.72
127 a

Supply and install weather proof incandescent light


fixture comprising die-cast aluminium body with
front glass cover fixed to the body by means of
24 30-73 stainless steel screws and neoprene gasket, G.I. 14 No. 7,964.50 111503.00
Wire guard, 1 No 100W lamp, including all
installation material Philips type or approved
equivalent.

Supply and install ceiling mounted incandescent


light fixture with glass cover and 2 - 60W lamps,
25
Philips type NCD-533 or approved equivalent.
( Bath Rooms , Corrider & Stor )
30-74 Ground Floor 100 No. 4,724.50 472450.00
30-74 +30- First Floor
102 No. 5,196.95 530088.90
127 a

Supply and install 56" (1.42 m) sweep ceiling fan


26 with fan hook and dimmer complete with all
accessories.
30-87 Ground Floor 17 No. 4,560.00 77520.00
30-87 +30-
First Floor 18 No. 5,016.00 90288.00
127 a

Supply and install earth connecting point of 10"x 2"x


1/4" (255mm x 50mm x 6mm) size of tinned
27 30-90 2 No. 643.20 1286.40
copper bar, including brass/tinned copper bolts,
nuts and washers.

Page 48 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BASED ON COMPOSITE SCHEDULE OF RATES - 2018
Electric Work Ground , First Floor. Abstract Sheet
Schedule
Sr. No. Description Quantity Unit Rate Total
item no
Supply and install pair of earth electrode each
comprising 24"x12" ( 600mm x 3mm) thick copper
plate buried 13 ft (4M) deep underground in upright
position in a pit and surrounded by mixture of salt
28 30-91 and charcoal (1:3), 12" (300mm) min dia around the 2 Job 60,471.15 120942.30
plate. The job also includes providing and fixing all
accessories such as nuts, bolts, washers, 2x3/0
SWG (2x70mm) copper conductor earthing lead.

Construction of 20" x 20" (500mm x 500 mm) square


inspection chamber for earth electrodes including
29 30-97 2 Job 7,948.95 15897.90
medium duty C.I. cover and all associated civil
works.

Supply and install wall mounted 4 ways, 5 Amp, flush


30 30-98 mounting type telephone rosette including plastic box
and face plate.
30-98 Ground Floor 18 No. 245.20 4413.60
30-98 +30-
First Floor 18 No. 269.72 4854.96
127 a

Supply and install recessed type telephone


distribution box suitable for 30 pair cable including
31 0.00
appropriate size 16 SWG sheet steel box with
hinged, latched and lockable cover.
30-100 Ground Floor 1 No. 7,521.55 7521.55
30-100 +30-
First Floor 1 No. 8,273.71 8273.71
127 a

Supply and install single arm fancy wall bracket


32 30-112 comprising brass bracket, apple white cylinderical
glass shade, lamp holder with 100W lamp.
30-112 Ground Floor 56 Each 2,014.00 112784.00
30-112 +30-
First Floor 58 Each 2,215.40 128493.20
127 a

Supply and install 10" (250 mm) sweep exhaust fan


33
including plastic louvers.
30-113 Ground Floor 14 Each 2,760.00 38640.00
30-113+30-
First Floor 18 Each 3,036.00 54648.00
127 a

Supply and install distribution board, 18 SWG steel


sheet 18"x24" enclosure, suitable for recess
mounting, comprising one incoming MCCB-TP/100A,
34 Outgoing 9 single phase MCB of various capacity
with internal wiring earthing, neutral link etc.
alongwith three Digital Amp. meters with lights.

30-115 (a) Ground Floor 4 Job 25,356.00 101424.00


30-115+30-
First Floor 4 Job 27,891.60 111566.40
127 a

Page 49 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BASED ON COMPOSITE SCHEDULE OF RATES - 2018
Electric Work Ground , First Floor. Abstract Sheet
Schedule
Sr. No. Description Quantity Unit Rate Total
item no
Extra for installing each number circuit breaker 6
35 30-116 (b) Ampere on same distribution board and bus bar (For 4 Job 2,748.00 10992.00
outgoing)

Light Fixture Philips Type LED 13W Bulb ,complete


in all respect with allied accessories or approved
36
equivalent. The fitting shall be approved by the
Engineer. (for Item no 30-74 )
30-124 (a) Ground Floor 200 Each 822.95 164590.00
30-124+30-
First Floor 204 Each 905.25 184669.98
127 a

Light Fixture Philips Type LED 13W Tube Lights


,complete in all respect with allied accessories or
37
approved equivalent. The fitting shall be approved
by the Engineer.
30-124 (c) Ground Floor 44 Each 2,382.95 104849.80
30-124+30- 46
First Floor Each 2,621.25 120577.27
127 a

Supply ,Installing ,ConnectionWiring for Fire Alaram


System with Fire resistance insulated 2-core,
38
1.5mm2 cable ,Including in PVC Conduits in 25
mm2 conduit
30-126 (a) Ground Floor R.M. 268.35 0.00
30-126+30-
First Floor R.M. 295.19 0.00
127 a

Supply ,Installing ,Connection of Addressable


break glass manual call stations (Copper Menvier
39
UK, Honey well,Gent or approved equivalent).

30-126 (b) Ground Floor 2 Each 4,482.95 8965.90


30-126b+30-
First Floor 2 Each 4,931.25 9862.49
127 a

Supply ,Installing ,Connection of Addressable


40 sounder and accessories (Copper Menvier UK,
Honey well,Gent or approved equivalent).
30-126 (c) Ground Floor 4 Each 7,362.95 29451.80
30-126c+30-
First Floor 4 Each 8,099.25 32396.98
127 a

Supply ,Installing ,Connection of Addressable


Photo electric Smoke Detectors as approved by the
41
engineer (Copper Menvier UK, Honey well, Gent or
approved equivalent).
30-126 (d) Ground Floor 18 Each 3,769.75 67855.50
30-126d+30-
First Floor 18 Each 4,146.73 74641.05
127 a

Supply ,Installing ,Connection of Addressable Fire


Alarm Control Panel as per project specified
requirements (2 Loop) including backup battery,
42 30-126 ( f ) 1 Job 198,842.50 198842.50
complete with all installation accessories, testing and
commissioning (Copper Menvier UK, Honey well,
Gent or approved equivalent).

Page 50 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
BASED ON COMPOSITE SCHEDULE OF RATES - 2018
Electric Work Ground , First Floor. Abstract Sheet
Schedule
Sr. No. Description Quantity Unit Rate Total
item no

Supply ,Installing ,Connection of Single Pole


43
Circuit Breaker 16 Ampere
30-22 (a) Ground Floor 36 Each 1,894.40 68198.40
30-22 a+30-
First Floor 36 Each 2,083.84 75018.24
127 a

Supply ,Installing ,Connection of 3 Pole Circuit


44 31-22 ( t )
Breaker 63 Ampere
30-22 (a) Ground Floor 4 Each 4,566.85 18267.40
30-22 a+30-
First Floor 4 Each 5,023.54 20094.14
127 a

Supply ,Installing ,Connection of 4 Pole Circuit


45 31-22 ( zc) 4 Each 9,148.20 36592.80
Breaker 100-160 Ampere (70KV)

Supply ,Installing ,Connection 4 Pole Circuit Breaker


46 31-22 ( zi) 1 Each 76,596.00 76596.00
160-250 Ampere (70KV)

TOTAL 5973617.17

Page 51 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
UNDER GROUND WATER TANK (CAPACITY 5000 GALLONS)
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QTY UNIT
(Pak Rs) (Pak Rs)

U.G.W.TANK 14'-0" x 10'-0" x6'-0" (5000 Glns)

1 Excavation in foundation of buildings and bridges


including layout, dressing, refilling around structures with
excavated earth, watering & ramming lead upto 100 ft.
(30m) & lift upto 5 ft. (1.5m)
(S.I No. 3-21 A iv)
Under Ground excavation 1.00 15.50 11.50 7.70 1372.53 Cft

1372.53 Cft 9.20 12627.23

2 Providing and laying cement concrete using approved


coarse sand and crushed aggregate 3/4" (19mm) & down
gauge in foundation including leveling, compacting and
curing.
(S.I No. 5 - 8 e) 1.00 15.50 11.50 0.28 49.02 Cft

49.02 Cft 200.85 9845.42

3 Providing and laying 1:2:4 cement concrete using approved


coarse sand and crushed aggregate 3/4" (19mm) and down
gauge in underground tank, septic tank and underground drain
including formwork and its removal, compacting and curing.
(S.I No. 5-22 a+b+c)
a Floor slab 1.00 15.50 11.50 0.75 133.69 Cft 232.05 31022.18
b walls L/w 2.00 15.50 0.75 7.18 167.00 Cft 277.75 46385.57
b walls S/w 2.00 10.00 0.75 7.18 107.75 Cft 277.75 29926.17
c Top Slab 1.00 15.50 11.50 0.50 89.13 Cft 327.30 29170.61

4 Providing, fabricating and laying deformed Grade 60 steel


reinforcement (deformed bar) for all kinds of R.C.C work
in foundation, plinth and ground floor including the cost of
straightening, removal of rust, cutting, bending, binding,
wastage and providing such over-laps as are not shown
on the drawings. The cost of binding wire and cement
concrete spacer blocks or chairs for binding and holding
the reinforcement in position is inclusive upto 15 ft. (5m)
height

(S.I.NO 5-65-a)
Columns + walls + slabs 498 1985 1.98 Tonne

1.98 Tonne 128365.80 254762.87

5 3/4 inch (19mm) thick cement plaster using Coarse Sand


on walls and columns in basement, plinth and ground
floor including making edges, corners and curing.

(S.I No. 15-4iii )


L/W 2.00 14.00 7.00 196.00 Sft
S/W 2.00 10.00 7.00 140.00 Sft
2.00 14.00 10.00 280.00 Sft

677.60 Sft 27.45 18600.12

6
Providing and fixing iron bars of required dia at required
spacing with horizontal flat iron as per approved design
including making holes fixing with sunk iron screws,
painting with two coats of red oxide paint.
38 mm x 4.8 (1.5² x 1/6²) flat iron ladder.
(S.I No. 28-29 )

Page 52 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
UNDER GROUND WATER TANK (CAPACITY 5000 GALLONS)
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QTY UNIT
(Pak Rs) (Pak Rs)
1.00 9.00 1.50 13.50 Sft

13.50 Sft 163.05 2201.18

7
Providing and fixing 22" dia. manhole cover in 3" (75 mm)
thick RCC 1:2:4, with steel at 5 lbs per cu.ft of concrete
with tee shaped C.I. frame of 20" clear inner dia. frame
weighing 37.5 kg. including cost of fixing material.
(S.I No. 25-14-1)
1.00 1.00 Each

1.00 Each 5939.8 5939.80

8 Providing and fixing at Site Electric Motor of KSB, Grandfos,


Siemens or approved equivalent (similar specifications),
complete in all respects including all taxes.

(S.I No. 27-65-a)


1 1.00 1.00 Each 17382.8 17382.80

TOTAL 457,864
175 % Premium above steel items 445,835
90 % Premium above Concrete items 137,061
G-TOTAL 1,040,760

Page 53 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
OVER HEAD WATER TANK (CAPACITY 2000 GALLONS)
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)

O.H.W.TANK 11'-9" x7'-07.5" x4'-0" (2000 Glns)

1 Providing and laying in situ cement concrete using


approved coarse sand and crushed aggregate 3/4"
(19mm) and down gauge in pillars and columns of any
shape in super structure including compacting, curing,
cost of form-work & its removal in basement and ground
floor.
Extra for first floor
Extra for every additional floor above first floor
(S.I No. 5-15-b+e+f)
Columns 4 1.50 0.83 1.50 7.43 Cft

7.43 Cft 386.30 2871.75

2 Providing and laying 1:2:4 cement concrete using


approved coarse sand and crushed aggregate 3/4"
(19mm) and down gauge in slabs including formwork and
its removal, compacting and curing Upto 6" (150 mm)
thickness
Above 6" (150 mm) upto 12" (300 mm) thickness
Extra for first floor
Extra for every additional floor over first floor.
(S.I No. 5-17-b i+ii+iii)
Bottom Slab 1 13.50 9.85 0.75 99.73 Cft
Top Slab 1 13.50 9.85 0.50 66.49 Cft

166.22 Cft 322.05 53530.75

3 Providing & laying in situ cement concrete in wall and


piers etc, upto 12" (300 mm) in thickness using approved
coarse sand & crushed aggregate 3/4" (19mm) & down
gauge including compacting, curing, cost of formwork
and its removal in basement and ground floor

Extra for first floor


Extra for every additional floor above first floor
(S.I No. 5-13-c+f+g )
walls L/w 2 13.25 0.75 4.25 92.92 Cft
walls S/w 2 7.63 0.75 4.25 53.47 Cft

a 146.39 Cft 401.55 58781.27

4 Providing, fabricating and laying deformed Grade 60


steel reinforcement (deformed bar) for all kinds of R.C.C
work in foundation, plinth and ground floor including the
cost of straightening, removal of rust, cutting, bending,
binding, wastage and providing such over-laps as are not
shown on the drawings. The cost of binding wire and
cement concrete spacer blocks or chairs for binding and
holding the reinforcement in position is inclusive upto 15
ft. (5m) height

Extra for first floor on Item No.5-65(a)


Extra for every additional floor above first floor on item
No.5-65(f)
(S.I.NO 5-65-a+f+g)
Columns + walls + slabs 320 798.51 0.80

0.80 Tonne 131725.80 105184.56

5 1/2 inch (13mm) thick cement plaster using Coarse Sand


on walls and columns in basement, plinth and ground
floor including making edges, corners and curing.

Page 54 of 55
CONSTRUCTION OF MIR CHAKAR KHAN RIND UNIVERSITY AT SIBBI.
BACHELOR FACULTY / VISITING FACULTY / GUEST HOSTEL
OVER HEAD WATER TANK (CAPACITY 2000 GALLONS)
BILL OF QUANTITIES
BASED ON COMPOSITE SCHEDULE OF RATES 2018
RATE AMOUNT
S.NO DESCRIPTION NO L W D/H QUANTITY UNIT
(Pak Rs) (Pak Rs)
Extra over respective payable items of ground floor
For first floor
b) For every additional floor above first floor.
(S.I No. 15-3 iii +46.a+b)
L/W 4 13.25 6.00 318.00 Sft
S/W 4 9.13 6.00 219.00 Sft
1 13.25 14.09 186.70 Sft

723.70 Sft 26.97 19515.45

6
Providing and fixing iron bars of required dia at required
spacing with horizontal flat iron as per approved design
including making holes fixing with sunk iron screws,
painting with two coats of red oxide paint.
d) 38 mm x 4.8 (1.5² x 1/6²) flat iron ladder.
(S.I No. 28-29 )
1 6.00 1.50 9.00 Sft

9.00 Sft 163.05 1467.45

7 Providing and fixing 22" dia. manhole cover in 3" (75


mm) thick RCC 1:2:4, with steel at 5 lbs per cu.ft of
concrete with tee shaped C.I. frame of 20" clear inner
dia. frame weighing 37.5 kg. including cost of fixing
material.
(S.I No. 25-14-1)
1 1.00 1.00 Each

1.00 Each 5939.8 5939.80

TOTAL FOR ONE TANK 247,291


175 % Premium above steel items 184,073
90 % Premium above Concrete items 101,081
TOTAL FOR TWO TANK 0.00 1,064,890

Page 55 of 55

You might also like