The document discusses issues caused by excessive voltage drops during startup of a large compressor motor. Measurements showed voltage drops over 10% when a neighboring compressor started up. This was damaging other compressors. The high voltage drop was due to the auto-transformer starter's high tap setting and abnormal supply configurations. Changing the tap setting and ensuring the normal supply configuration was used reduced voltage drops to acceptable levels and resolved the issues.
Original Description:
Original Title
Voltage dips during start-up of large compressor motors
The document discusses issues caused by excessive voltage drops during startup of a large compressor motor. Measurements showed voltage drops over 10% when a neighboring compressor started up. This was damaging other compressors. The high voltage drop was due to the auto-transformer starter's high tap setting and abnormal supply configurations. Changing the tap setting and ensuring the normal supply configuration was used reduced voltage drops to acceptable levels and resolved the issues.
The document discusses issues caused by excessive voltage drops during startup of a large compressor motor. Measurements showed voltage drops over 10% when a neighboring compressor started up. This was damaging other compressors. The high voltage drop was due to the auto-transformer starter's high tap setting and abnormal supply configurations. Changing the tap setting and ensuring the normal supply configuration was used reduced voltage drops to acceptable levels and resolved the issues.
compressor motors by Bernhard Cronjé; - DRPA Consulting
Th
Voltage, current and speed measurements
showed that during start-up of the neighboring compressor, the voltage drop on the bus was excessive and that the motor was running up too fast. Further measurements and supply system modeling revealed that it was caused by the combination of a high tap setting on the neighboring compressors auto starting transformer and certain abnormal supply system configurations.
Background
A mine was experiencing problems with Fig. 2: Korndorffer starter arrangement.
Fig. 1: Normal supply configuration for compressor damage to the impellors and pinions of sub station. two 4,8 MW compressors (type A). It was noticed that the levels of vibration on the compressor increased progressively each time the neighboring 4,5 MW compressor (type B) was started. This led to the suspicion that the machines were being damaged by deceleration and acceleration torques resulting from excessive voltage drops during the start-up of the type B compressor. The manufacturers of the type A compressors specified maximum allowable voltage drop of 10%. DRPA were requested to conduct a voltage dip investigation and to evaluate the severity of the dips under various system conditions.
The single line diagram in Fig. 1 shows
the normal supply configuration for the compressor sub station. Under normal Fig. 3: 11 kV bus voltage during compressor type B start-up. operating conditions the compressor sub station is supplied with power from two 88/11 kV 20 MVA transformers operating in full speed, the “star” contactor is opened 20 ms intervals were produced. Another parallel via two 11 kV overhead line (OHL) effectively converting the auto transformer recorder was set up on the motor coupling to feeders. starter into a primary reactance starter. Next record the speed during start-up. The results the “run” contactor is closed to bridge the are shown in Fig. 3, Fig. 4 and Fig. 5. The type B compressor drive is an 11 kV, reactance and apply full voltage to the 4,5 MW, BBC synchronous motor and is The average measured voltage drop was motor. equipped with an auto transformer starter 6,7%. During this start-up the supply network panel. It is also known as a Korndorffer starter Measurements conducted was not in its normal configuration. The bus and it reduces the stator voltage during start- section to the third transformer was also Two high speed power quality recorders up. It also has the effect of reducing the start- closed resulting in three 20 MVA supply were used to make current and voltage up current by the same ratio as the voltage measurements simultaneously on the type transformers being in parallel. The average reduction. A simplified diagram of the motor A and B compressor feeders. The recorders start-up current of 1174 A or 4,4 p.u. of rated and starter is shown in Fig. 2. were set up to measure and record the full load current (270 A) was higher than To start the motor, the “star ” and “start” current and voltage for the duration of the expected. The motor run-up time of 9 to 10 contactors are closed applying the reduced start-up at high resolution (sampling rate s was also slightly faster than the expected voltage to the motor. The run contactor >25 kHz). RMS voltage and current values 12 s for this machine. (The manufacturers, is open. When the motor has reached were calculated and graphs with data at ABB Switzerland quoted 12 s for 83%
energize - December 2006 - Page 38
APPLICATION higher than the maximum allowable voltage drop of 10% specified for the type A compressors.
Starter auto transformer inspection and
tests
The high start-up currents prompted further
investigation into the tap settings of the auto transformer. The transformer taps are internal boltable links and cannot be inspected without draining some of the oil, disconnecting power cables and then opening the top cover. By injecting 525 V on the supply of the auto transformer and measuring the voltage on the motor side it Fig. 4: RMS current of compressor type B during start-up. was established that the transformer was on its maximum tap of 90%. A recommendation was made to change to the 82% tap in order to reduce the magnitude of the voltage dip during start-up.
Supply system modeling
An accurate model of the system was
constructed in ETAP. The start-up of the motor was then modeled with various supply configurations. It was found that with the existing tap settings, the voltage drop was excessive (i.e. >10%) under certain conditions e.g. with only one or two supply transformers in circuit or if one of the overhead lines trip.
Simulation results for one, two and three
supply transformers gave voltage drops Fig. 5: Motor speed of compressor type B during start-up. during start-up of 12%, 10% and 7% respectively. The simulated bus voltage during start-up with three supply transformers is shown in Fig. 6.
The simulated value of 7% correlated well with
the measured value of 6,7%. It is therefore important to monitor the supply configuration and to ensure that the compressors are not started when fault levels are too low.
Conclusions
The correct application of starter circuits
on large medium voltage motors is critical to avoid power quality problems that can result in costly damage to other equipment. Accurate measurement of voltage, current and speed during start-up can reveal a lot about the motor and the starter circuit. Fig. 6: Simulated 11 kV bus voltage during start-up of type B compressor. The ETAP model accurately reproduced the measurement results and it could be seen that it is very important to model various supply and equipment configurations as starting voltage). These measurement results On a second occasion the voltage dip only certain combinations may result in corresponded to that of a DOL starter or a measurements were repeated and this time problems. very high tap on the starting transformer. a voltage drop of 10,7% was recorded. The oscillations observed are due to the This time the supply network was in its Contact Bernhard Cronje, non-sinusoidal MMF of the machine and are normal configuration i.e. two 20 MVA supply DRPA Consulting, Tel (011) 202-8734, considered normal. transformers in parallel. The volt drop was b.cronje@drasa.co.za