You are on page 1of 1

WEEKLY FORECAST

Work Schedule
Mon Tue Wed Thur Fri Sat
ITEM DESCRIPTION 18th Nov 19th Nov 20th Nov 21st Nov 22nd Nov 23rd Nov

A ROOF SLAB
Formwork to slab √ √ √
Reinforcement to roof slab √ √ √
Concrete casting to roof slab

B RETAINING WALL
Formwork to edge of slab √ √
Reinforcement to slab √ √
Concrete casting to slab √
Plumbing works √ √ √ √

C SEPTIC TANK
Excavation √ √ √ √
Blinding √
Reinforcement to slab

D SECURITY POST
Formwork to edge of slab √
Reinforcement to slab √
Concrete casting to slab √

E SWIMMING POOL
Setting out √
Blinding √

Requisitions

1 Concrete ( m3 ) 23

2 12mm Steel (tons) 3.80


3 16mm Steel (tons) 2.97

4 Marine Plywood ( pcs ) To be confirmed

5 Money ( Ghc ) 5,000.00