PLANNED SHUTDOWN

Wed 14/02/24
PM3
ID Task Name Area Duration Start Finish Supervisor Resource Names Job No. % Complete Remarks Wed 14 Feb
5 6 7 8 9 10 11 12 13
0 QCS,DCS,WIS Task PM3 5,67 hrs? 7:00 12:40 100%

1 1 QCS Task list 5,5 hrs 7:00 12:30 Oki DP 100%

2 1.1 Singlepoint sizepress QCS 45 mins 7:00 7:45 Oki DP Abdul G, Fajar HP 3000148936 100% QCS

3 1.2 Body and Inner head scanner Size QCS 1 hr 7:45 8:45 Oki DP Abdul G, Fajar HP 3000149152 100% QCS
Inspection
4 1.3 Filter Air Blower Scanner Size Replacement QCS 15 mins 8:45 9:00 Oki DP Abdul G, Fajar HP 3000149134 100% QCS

5 1.4 Air & Water Condenser Chiller Size QCS 15 mins 9:00 9:15 Oki DP Abdul G, Fajar HP 3000149153 100% QCS
Inspention
6 1.5 Sensor BW scanner reel background and QCS 30 mins 9:15 9:45 Oki DP Abdul G, Fajar HP 3000149154 100% QCS
reference
7 1.6 Sensor Ash scanner reel background and QCS 30 mins 9:45 10:15 Oki DP Abdul G, Fajar HP 3000149155 100% QCS
reference
8 1.7 Sensor Moi scanner reel background and QCS 30 mins 10:15 10:45 Oki DP Abdul G, Fajar HP 3000149156 100% QCS
reference
9 1.8 Sensor Opa scanner reel background and QCS 30 mins 10:45 11:15 Oki DP Abdul G, Fajar HP 3000149157 100% QCS
reference
10 1.9 Sensor Moi scanner Size background and QCS 30 mins 11:15 11:45 Oki DP Abdul G, Fajar HP 3000149158 100% QCS
reference
11 1.10 Kapton Window Ash Scanner Reel QCS 15 mins 11:45 12:00 Oki DP Rahadyan CCS, 3000149159 100% QCS
Inspection Catur S
12 1.11 Kapton Window BW Scanner Reel QCS 15 mins 12:00 12:15 Oki DP Rahadyan CCS, 3000149160 100% QCS
Inspection Catur S
13 1.12 Air & Water Condenser Chiller Reel QCS 15 mins 12:15 12:30 Oki DP Rahadyan CCS, 3000149162 100% QCS
Inspention Catur S
14 2 DCS Task List 10 mins? 12:30 12:40 Dian H 100%

15 2.1 Backup Variable FCE DCS 10 mins 12:30 12:40 Dian H Rahadyan CCS, 3000149163 100% DCS
Catur S
16 3 Tambahan 0,5 hrs 7:00 7:30 100%

17 3.1 1. Motor drive belt scanner inspection QCS 30 mins 7:00 7:30 Oki DP Abdul G, Fajar HP 100% QCS

18 3.2 2. Head separation clutch scanner reel QCS 30 mins 7:00 7:30 Oki DP Abdul G, Fajar HP 100% QCS
inspection

Inactive Task Manual Task Manual Summary


PM3 2023-02-14 PS - QCS, Page
DCS &1 WI
-1 Inactive Milestone Duration-only Start-only
Inactive Summary Manual Summary Rollup Finish-only