Fri 23/02/24
PM3
ID Task Name Area Duration Start Finish Supervisor Resource Names Job No. Remarks Fri 23 Feb
9 10 11 12 13 14 15 16 17
0 QCS,DCS,WIS Task PM3 6 hrs 11:00 17:00
2 1.1 Overhaul Porosity Scanner Reel QCS 6 hrs 11:00 17:00 Oki DP Group A & Group B 3000149511 QCS
3 1.2 Belt Idler pulley Scanner Reel Inspection QCS 30 mins 11:00 11:30 Oki DP Rahadyan CCS, Catur 3000149512 QCS
S
4 1.3 Electrostatic bar scanner reel inspection QCS 30 mins 11:30 12:00 Oki DP Rahadyan CCS, Catur 3000149513 QCS
S
5 1.4 Water filter chiller reel inspection QCS 30 mins 15:00 15:30 Oki DP Dony R, Rafi F 3000149514 QCS
6 1.5 Water filter chiller size inspection QCS 30 mins 15:30 16:00 Oki DP Dony R, Rafi F 3000149516 QCS
8 2.1 Lens Camera and beam WIS Inspection QCS 15 mins 16:00 16:15 Deni Ep Dony R, Rafi F 3000149517 QCS
10 3.1 Backup Variable FCE DCS 15 mins 12:45 13:00 Dian H Rahadyan CCS, Catur DCS
S
11 3.2 Ganti relay Doctor Blade 1 Central Roll DCS 15 mins 13:00 13:15 Dian H Rahadyan CCS, Catur 3000149506 DCS
(G0YH005) S
12 3.3 Ganti relay Doctor Blade 2 Central Roll DCS 15 mins 13:15 13:30 Dian H Rahadyan CCS, Catur 3000149508 DCS
(G0YH006) S
13 3.4 Peremajaan Module I/O PM3-CR-09 2 hrs 13:30 15:30 Dian H
14 3.4.1 MODULE 3N3035AO33 DCS 30 mins 13:30 14:00 Dian H 3000149518 DCS
15 3.4.2 MODULE 3N3036AO34 DCS 30 mins 14:00 14:30 Dian H 3000149518 DCS
16 3.4.3 MODULE 3N3045DI43 DCS 30 mins 14:30 15:00 Dian H 3000149518 DCS
17 3.4.4 MODULE 3N3065DI44 DCS 30 mins 15:00 15:30 Dian H 3000149518 DCS
18 4 Persiapan Start Up ALL 1 hr 16:00 17:00 ALL SPV Dony R, Rafi F 3000149519 ALL