PM3
ID Task Name Area Duration Start Finish Supervisor Resource Names Job No. Remarks 27 Jan, 7 27 Jan, 8 27 Jan, 9 27 Jan, 10 27 Jan, 11 27 Jan, 12 27 Jan, 13
30 0 30 0 30 0 30 0 30 0 30 0
0 QCS,DCS,WIS Task PM3 4,92 hrs 8:00 12:55

1 1 QCS Task list 3 hrs 8:00 11:00 Oki DP

2 1.1 Singlepoint moisture scanner size QCS 30 mins 8:00 8:30 Oki DP Marhadi , Haries QCS

3 1.2 Scanner Track and Dust wiper Scanner Reel QCS 30 mins 8:30 9:00 Oki DP Marhadi , Haries QCS
Inspection
4 1.3 Static eliminator drain lines Scanner reel QCS 1,5 hrs 9:00 10:30 Oki DP Marhadi , Haries QCS
inspection
5 1.4 Air Condenser Chiller Reel Inspection QCS 15 mins 10:30 10:45 Oki DP Marhadi , Haries QCS

6 1.5 Air Condenser Chiller Size Inspection QCS 15 mins 10:45 11:00 Oki DP Marhadi , Haries QCS

7 2 WIS Task list WIS 1,75 hrs 11:00 12:45 Deni Ep

8 2.1 Lens Camera and beam WIS Inspection WIS 15 mins 11:00 11:15 Deni Ep Marhadi , Haries WIS

9 2.2 Cylinder lock/unlock Beam Wis Inspection WIS 30 mins 11:15 11:45 Deni Ep Marhadi , Haries WIS

10 2.3 Cylinder lifting Beam Wis Inspection WIS 30 mins 11:45 12:15 Deni Ep Marhadi , Haries WIS

11 2.4 Power Supply 12 VDC camera WIS WIS 30 mins 12:15 12:45 Deni Ep Marhadi , Haries WIS
inspection
12 3 DCS Task List 10 mins 12:45 12:55 Dian H

13 3.1 Backup Variable FCE DCS 10 mins 12:45 12:55 Dian H Abdul G, Fajar HP DCS

Inactive Task Manual Task Manual Summary


PM3 2023-01-27 PS - QCS, Page
DCS &1 WI
-1 Inactive Milestone Duration-only Start-only
Inactive Summary Manual Summary Rollup Finish-only

You might also like