MEP’s OUTLINE

PROYEK :
FINISH GOOD & IPAL
DUA KELINCI - PATI
MEP OUTLINE

MEP OUTLINE’S SCOPE

I. MECHANICAL WORK
1. VAC
2. PLUMBING
3. FIRE PROTECTION

II. ELECTRICAL WORK


1. ELECTRICAL DISTRIBUTION
- Lightning Protection
2. FIRE ALARM
3. CCTV & SECURITY
4. DATA & VOICE

III. IPAL
PLUMBING

IV. VERTICAL TRANSPORTATION


1. LIFT BARANG

V. TESTING AND COMMISSIONING

ESKE - ME Page |2
MEP OUTLINE

I. MECHANICAL WORK
1. VAC (Ventilation and Air Conditioning)
a. Ventilation
- Mechanical Fan (Fresh Air & Exhaust)

b. Air Conditioning
- Split air conditioning
- Piping & Drain

2. PLUMBING
a. Clean water distribution
- Piping distribution

b. Waste water
- STP
- Piping distribution

3. FIRE PROTECTION
a. FIRE HYDRANT
- Pump & Accessories (By Existing)
- Piping distribution

b. FIRE SPRINKLER
- Tapping from hydrant line
- Piping distribution
- Control cable to JB-FA

c. FIRE EXTINGUISHER

ESKE - ME Page |3
MEP OUTLINE

II. ELECTRICAL WORK


1. ELECTRICAL DISTRIBUTION
- Electrical Panel
- Feeder cable (Tapping from Existing)
- Cable ladder and tray
- Grounding
- Lighting and receptacle
- Lightning Protection (existing)

2. FIRE ALARM
- Main Control
- Fire alarm detector installation
- JB-FA

3. CCTV & SECURITY


- Main Control
- CCTV installation
- Rack c/w Switch and acc.

4. DATA & VOICE


- Data & Voice Cabling installation.
- Data & Voice Outlet
- Access point
- Rack c/w Switch and acc.

III. IPAL
1. PLUMBING

IV. VERTICAL TRANSPORTATION


1. ELEVATOR

V. TESTING AND COMMISSIONING


- Conductivity test
- Resistance test
- Grounding test
- Hydrostatic test
- Test rendam

ESKE - ME Page |4
MEP OUTLINE

MEP Material On Site

I. MECHANICAL WORK
1. VAC : 0%
2. PLUMBING : 0%
3. FIRE PROTECTION : 0%

II. ELECTRICAL WORK


1. ELECTRICAL DISTRIBUTION : 0%
- Lightning Protection
2. FIRE ALARM : 0%
3. CCTV & SECURITY : 0%
4. DATA & VOICE : 0%

III. IPAL
1. PLUMBING
- Pompa : 50%
- Fan : 0%

2. VERTICAL TRANSPORTATION
1. LIFT BARANG : 0%

ESKE - ME Page |5