Professional Documents
Culture Documents
1 bolts and tamplet s bolt ,stool plate levels has to be checked foundation out let H w R/S SEE THE ATTACHMENTS
Alignment before concreting drawing -
DOCUMENT ID:
MF00527572
2 Foundation / Padding / a) foundation dimentinal check before foundation out let H w R/S SEE THE ATTACHMENTS
Structure Release concret drawing -
b) foundation Released equipment for DOCUMENT ID:
erection if foundation curing period is MF00527572
over
c) Dimensions
d) Positions(center marking)and height(level
marking)
3 Shim Pads Installation a) Verify layout dimension spacing and dth protocol H w R/S SEE THE ATTACHMENTS
quantity
b) Verify elevation and levelness
Grout gap,Firmly anchor to foundation,
grouted and cured , clean and non-grease
4 Installation And a) correct marking, location and orientation AS PER THE H w R/S SEE THE ATTACHMENTS
Erection finally damage LIFTING
b) elevation bearing on shim pads, clean PROCEDURE AND
bottom of equipment ,grout gap
c) adequate projection of bolts for main
nuts, lock nut, washer plate
5 Grouting of base plate Completion of grouting activity H w R/S SEE THE ATTACHMENTS
6 Alignment of stacked a. correct the flange gap, gasket, bolts H w R/S SEE THE ATTACHMENTS
units fully tighten
b. completeness of assemble
c. level ness of flanges man hole covers
7 Final tighten of anchor a. correct washers, lock nuts and H w R/S SEE THE ATTACHMENTS
bolts fulltightening / torqueing as require this
one to be done after curing of grouting
only
b. washer plate welding
8 Installation Of correct alignment of bolts, safety gates H w R/S SEE THE ATTACHMENTS
BRASSING SUPPORTS
Effect
MF-
4 building
00527572
foundation B) EA,EB,ECB-
1,ECB-
2,ECB-
3,ECB-4
foundation
and anchor
bolt
distance
and level H w R/S
checking
After
concrete
HE ATTACHMENTS
HE ATTACHMENTS
HE ATTACHMENTS
HE ATTACHMENTS
HE ATTACHMENTS
HE ATTACHMENTS
INSPECTION TEST PLAN
Andhra Paper Limited APL EVAPORATOR REBUILD-280 TPH
Document #:QCP-APL-PRO-ITP-0002 H: HOLD POINTS
W: WITNESS POINTS
Issue Date: 07-AUG-2023
Drawing #:317-C-LAY-2519,MF00527573,MF0052572,MF00506710,MF-00499252 R: REVIEWS
PHASE-1
Issued by#: D.CHINNI KRISHNA S: SURVELLANCE
Reference SIGN/ SIGN/ SIGN/
S.No Activity/ Description Inspection / Test Requirements characteristic Documents REE DATE QA/QC DATE APL TEAM DATE Comments
Bolts and template Alignment bolt ,stool plate levels has to be checked before
concreting foundation out let drawing -
1 H w R/S SEE THE ATTACHMENTS
DOCUMENT ID: MF00527572
REE SITE ENGG. REE SITE INCHARGE APL QA/QC ENGINEER VALMET ENGG APL MECHANICAL
DATE - SIGN DATE - SIGN DATE - SIGN DATE - SIGN DATE - SIGN
INSPECTION TEST PLAN
Andhra Paper Limited APL EVAPORATOR REBUILD-280 TPH
Document #:QCP-APL-PRO-ITP-0002 H: HOLD POINTS
W: WITNESS POINTS
Issue Date: 07-AUG-2023
Drawing #:317-C-LAY-2519,MF00527573,MF0052572,MF00506710,MF-00499252 R: REVIEWS
PHASE-2
Issued by#: D.CHINNI KRISHNA S: SURVELLANCE
Reference SIGN/ SIGN/ SIGN/
S.No Activity/ Description Inspection / Test Requirements characteristic Documents REE DATE QA/QC DATE APL TEAM DATE Comments
Gritting installation
Gritting to be installed and welded as per the SEE THE
7 drawing MF00551873 H w R/S ATTACHMENTS
REE SITE ENGG. REE SITE INCHARGE APL QA/QC ENGINEER VALMET ENGG APL MECHANICAL
DATE - SIGN DATE - SIGN DATE - SIGN DATE - SIGN DATE - SIGN
INSPECTION TEST PLAN
Andhra Paper Limited APL EVAPORATOR REBUILD-280 TPH
Document #:QCP-APL-PRO-ITP-0002 H: HOLD POINTS
W: WITNESS POINTS
Issue Date: 07-AUG-2023
Drawing #:317-C-LAY-2519,MF00527573,MF0052572,MF00506710,MF-00499252 R: REVIEWS
PHASE-3
Issued by#: D.CHINNI KRISHNA S: SURVELLANCE
Reference SIGN/ SIGN/ SIGN/
S.No Activity/ Description Documents REE DATE QA/QC DATE APL TEAM DATE Comments
REE SITE ENGG. REE SITE INCHARGE APL QA/QC ENGINEER VALMET ENGG APL MECHANICAL
DATE - SIGN DATE - SIGN DATE - SIGN DATE - SIGN DATE - SIGN