29 JAN - 04 FEB, 2024 05 - 11 FEB, 2024 W6 12 - 18 FEB, 2024 W7 19 - 25 FEB, 2024 W8 26 FEB - 03 MAR, 2024 W9 04 - 10 MAR, 2024 W10 11 - 17 MAR, 2024 W11 18 - 24 MAR, 2024 W12 25 - 31 MAR, 2024 W13 01 - 07 APR, 2024 W14 08 - 14 APR, 2024 W15 15 - 21 APR, 2024 W16 22 - 28 APR, 2024 W17 29 APR - 05 MAY, 2024 W18 06 - 12 MAY, 2024 W19
# Task  Status  Start …  Due Date  Dura…  % Compl… UNSCHEDULED W5
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12

 PHASE 1 - Project Kickoff Active 02-01-2024 02-21-2024 14 days 100 %

 Product realization - Order release (2) 02-01-2024 02-08-2024 100 %

MD1-T25 Order release Closed 02-01-2024 02-02-2024 2 days 100 % 

MD1-T26 PO to Supplier Closed 02-02-2024 02-08-2024 5 days 100 % 

02-02-
 PHASE 1.1 - Planning and definition Active 02-12-2024 14 days 66 %
2024
02-05-
 planning and defining the progr… (3) 02-12-2024 66 %
2024

MD1-T22 Initial review and SOW Closed 02-05-2024 02-06-2024 2 days 100 % 

MD1-T24 Contract agreement with supplier Closed 02-06-2024 02-08-2024 3 days 100 % 

MD1-T30 APQP development Time line In Progress 02-08-2024 02-12-2024 0 3 days 80 %

02-05-
 PHASE 2 - Product & Process develo… Active 04-08-2024 96 days 11 %
2024
02-07-
 Product design - Final release (1) 02-08-2024 100 %
2024

MD1-T1 Product design release- for develo… Closed 02-07-2024 02-08-2024 2 days 100 % 

02-02-
 Mold development (17) 04-08-2024 5%
2024

MD1-T2 Feasibility & DFM Closed 02-02-2024 02-08-2024 5 days 100 % 

MD1-T3 Mold Design In Progress 02-09-2024 02-14-2024 0 4 days 40 %

MD1-T37 MFA In Progress 02-14-2024 02-16-2024 0 3 days 10 %

MD1-T4 Mold design Design approval Open 02-16-2024 02-19-2024 0 2 days 0%

MD1-T5 - Mold Manufacturing Open 02-15-2024 04-05-2024 37 days 0%

MD1-T6 Material procurement Open 02-15-2024 02-22-2024 0 6 days 0%

MD1-T7 Pre machining & Roughing Open 02-21-2024 02-27-2024 0 5 days 0%

MD1-T8 Heat treatment Open 02-27-2024 03-01-2024 0 4 days 0%

MD1-T9 Final machining Open 03-01-2024 03-20-2024 14 days 0%

MD1-T10 Inspection and Rework Open 03-20-2024 03-22-2024 0 3 days 0%

MD1-T11 Assembly and rework Open 03-20-2024 03-22-2024 0 3 days 0%

MD1-T12 Mold Final Assembly Open 03-20-2024 03-25-2024 4 days 0%

MD1-T13 Mold T0 Open 03-26-2024 03-29-2024 4 days 0%

MD1-T14 Part shipment to Customer Open - 0%

MD1-T15 Corrections and MOD Open 03-29-2024 04-03-2024 4 days 0%

MD1-T16 Mold T1 Open 04-04-2024 04-06-2024 3 days 0%

MD1-T17 Part shipment to customer Open 04-08-2024 04-08-2024 1 day 0%

 Gauges and testing Equipments 0%

 PHASE 3 - Pilot production & PPAP Active 04-15-2024 04-25-2024 0%

 PPAP (4) 04-15-2024 04-24-2024 0%

MD1-T38 PPAP-Pilot Production Open 04-15-2024 04-19-2024 0 5 days 0%

MD1-T39 PPAP Documentation Open 04-17-2024 04-24-2024 6 days 0%

MD1-T40 PPAP From Supplier Open 04-17-2024 04-24-2024 6 days 0%

MD1-T41 PPAP Submission to Customer Open - 0%

 PHASE 4 - Part & process validation … Active 04-19-2024 05-08-2024 0%

 Part and process validation (2) 04-19-2024 05-08-2024 0%

MD1-T42 DV testing and Part approval Open 04-29-2024 05-08-2024 8 days 0%

MD1-T43 PPAP approval and sign off Open 04-19-2024 05-08-2024 14 days 0%