PROJECT SCHEDULE Project Start: Jan 18, 2024

HarmonyHorizon: Uniting for SDG 17 Work Week: Mon-Fri

ASSIGNED DUR
ACTIVITY PROGRESS START END
TO (days)

Initiating Phase
Initiate the project ET JT 2 0% 1-18-24 1-19-24

Initiating phase complete 0 0% 1-19-24 1-19-24

Planning Phase
Plan the project 3 0% 1-30-24 2-1-24

Planning phase complete 0 0% 2-1-24 2-1-24

Executing Phase
Event Documantation

Design event documentation template 2 2-2-24 2-5-24

Compile post-event reports ET 3 2-6-24 2-8-24

Activities Design

Brainstorm activity ideas 2 2-7-24 2-8-24


HarmonyHorizon: Uniting for SDG 17 Work Week: Mon-Fri

ASSIGNED DUR
ACTIVITY PROGRESS START END
TO (days)

Develop detailed activity plans ET 3 2-10-24 2-14-24

Test and refine activities ET 2 2-10-24 2-13-24

Vendor Engagement

Identify and contact vendors ET MR SM DW 2 2-13-24 2-14-24

Negotiate contracts and finalize agreements ET MR SM DW 4 2-17-24 2-22-24

Coordinate logistics with vendors ET MR DW 3 2-20-24 2-22-24

Speaker Coordination

Identify potential speakers ET JT MR SM OC 2 2-22-24 2-23-24

Confirm speaker availability and topics ET JT MR OC 3 2-25-24 2-28-24

Coordinate logistics for speakers ET JT MR OC 4 2-29-24 3-5-24

Marketing strategy

Define target audience and key messages ET MR SM 3 3-5-24 3-7-24

Page 2 of 6
HarmonyHorizon: Uniting for SDG 17 Work Week: Mon-Fri

ASSIGNED DUR
ACTIVITY PROGRESS START END
TO (days)

Create promotional materials ET MR SM 4 3-9-24 3-14-24

#REF! ET SM 5 3-11-24 3-15-24

Waste management

Develop waste reduction strategies 2 3-12-24 3-13-24

Provide recycling and composting bins ET 2 3-14-24 3-15-24

Event setup

Plan event layout and equipment needs ET MR DW 3 3-15-24 3-19-24

Decorate event space ET MR 2 3-17-24 3-19-24

Conduct final checks before the event ET MR 1 3-18-24 3-18-24

Post-Event Eval

Collect attendee feedback ET OC 2 3-19-24 3-20-24

Page 3 of 6
HarmonyHorizon: Uniting for SDG 17 Work Week: Mon-Fri

ASSIGNED DUR
ACTIVITY PROGRESS START END
TO (days)

Analyze feedback and evaluate event success ET OC 3 3-22-24 3-26-24

Document lessons learned for future events ET OC 2 3-22-24 3-25-24

Workshop Curriculum

Develop workshop topics and materials ET 4 3-20-24 3-25-24

Align workshops with event objectives ET 3 3-23-24 3-27-24


Review and update curriculum based on
ET 2 3-25-24 3-26-24
feedback

Project Charter

Establish communication channels 1 3-26-24 3-26-24

Timeline management

Develop project timeline with milestones ET DW 2 3-28-24 3-29-24

Page 4 of 6
HarmonyHorizon: Uniting for SDG 17 Work Week: Mon-Fri

ASSIGNED DUR
ACTIVITY PROGRESS START END
TO (days)

Page 5 of 6
HarmonyHorizon: Uniting for SDG 17 Work Week: Mon-Fri

ASSIGNED DUR
ACTIVITY PROGRESS START END
TO (days)

Executing phase complete 0 3-29-24 3-29-24

Closing Phase
Close the project 3

Project complete 0 3-29-24 3-29-24

Page 6 of 6