CORPORATION LTD.
GUWAHATI REFINERY
System. ALL THE SYSTEM AS PER PGTR PROCEDURE OF SR KERO -I PUMP (P-031 A)
Sub System. AS PER DCS LOG DATA / HARD COPY OF LOG SHT
EPCM hereby certifies that the above System has been completely commissioned and stabilized in accordance with the
requirements of the CONTRACT, with the exception of the outstanding items listed upon the attached Punch list.
The system has been checked for Operability of 72 Hours and has been satisfactorily taken over by COMPANY for Regular
Operations.
Attachments:
1. Commissioning Certificates
2. PGTR DCS signed Log Sheets / Hard Copy of Log Sheet
3. Master Punch List
Remarks:
Name
Signature
Date
INDIAN OIL
CORPORATION LTD.
GUWAHATI REFINERY
System. ALL THE SYSTEM AS PER PGTR PROCEDURE OF SR KERO -I PUMP (P-031 B)
Sub System. AS PER DCS LOG DATA / HARD COPY OF LOG SHT
EPCM hereby certifies that the above System has been completely commissioned and stabilized in accordance with
the requirements of the CONTRACT, with the exception of the outstanding items listed upon the attached Punch list.
The system has been checked for Operability of 72 Hours and has been satisfactorily taken over by COMPANY for
Regular Operations.
Attachments:
1. Commissioning Certificates
2. PGTR DCS signed Log Sheets / Hard Copy of Log Sheet
3. Master Punch List
Remarks:
Name
Signatur
e
Date
INDIAN OIL
CORPORATION LTD.
GUWAHATI REFINERY
EPCM Work for Revamp of 1.2 PGTR Client Contract No.:
MMTPA CDU,NSF and NSU at IOCL GC21EST136/27311004
GUWAHATI REFINERY CERTIFICATE
System. ALL THE SYSTEM AS PER PGTR PROCEDURE OF SPLITTER-I RECIRCULATION PUMP P-32 A
Sub System. AS PER DCS LOG DATA / HARD COPY OF LOG SHT
EPCM hereby certifies that the above System has been completely commissioned and stabilized in accordance with the
requirements of the CONTRACT, with the exception of the outstanding items listed upon the attached Punch list.
The system has been checked for Operability of 72 Hours and has been satisfactorily taken over by COMPANY for Regular
Operations.
Attachments:
1. Commissioning Certificates
2. PGTR DCS signed Log Sheets / Hard Copy of Log Sheet
3. Master Punch List
Remarks:
Signature
Date
INDIAN OIL
CORPORATION LTD.
GUWAHATI REFINERY
EPCM Work for Revamp of 1.2 PGTR Client Contract No.:
MMTPA CDU,NSF and NSU at IOCL GC21EST136/27311004
GUWAHATI REFINERY CERTIFICATE
System. ALL THE SYSTEM AS PER PGTR PROCEDURE OF SPLITTER-I RECIRCULATION PUMP P-32 B
Sub System. AS PER DCS LOG DATA / HARD COPY OF LOG SHT
EPCM hereby certifies that the above System has been completely commissioned and stabilized in accordance with the
requirements of the CONTRACT, with the exception of the outstanding items listed upon the attached Punch list.
The system has been checked for Operability of 72 Hours and has been satisfactorily taken over by COMPANY for Regular
Operations.
Attachments:
1. Commissioning Certificates
2. PGTR DCS signed Log Sheets / Hard Copy of Log Sheet
3. Master Punch List
Remarks:
UPCEM IOCL UPCEM IOCL APPROVED &
PERFORMER WITNESSED APPROVED & CERTIFIED PROD DGM /
CERTIFIED SR. MANAGER
Name
Signature
Date
INDIAN OIL
CORPORATION LTD.
GUWAHATI REFINERY
EPCM Work for Revamp of 1.2 PGTR Client Contract No.:
MMTPA CDU,NSF and NSU at IOCL GC21EST136/27311004
GUWAHATI REFINERY CERTIFICATE
System. ALL THE SYSTEM AS PER PGTR PROCEDURE OF SPLITTER I REFLUX PUMPS (P-33 A)
Sub System. AS PER DCS LOG DATA / HARD COPY OF LOG SHT
EPCM hereby certifies that the above System has been completely commissioned and stabilized in accordance with the
requirements of the CONTRACT, with the exception of the outstanding items listed upon the attached Punch list.
The system has been checked for Operability of 72 Hours and has been satisfactorily taken over by COMPANY for Regular
Operations.
Attachments:
1. Commissioning Certificates
2. PGTR DCS signed Log Sheets / Hard Copy of Log Sheet
3. Master Punch List
Remarks:
Name
Signature
Date
INDIAN OIL
CORPORATION LTD.
GUWAHATI REFINERY
EPCM Work for Revamp of 1.2 PGTR Client Contract No.:
MMTPA CDU,NSF and NSU at IOCL GC21EST136/27311004
GUWAHATI REFINERY CERTIFICATE
System. ALL THE SYSTEM AS PER PGTR PROCEDURE OF SPLITTER I REFLUX PUMPS (P-33 B)
Sub System. AS PER DCS LOG DATA / HARD COPY OF LOG SHT
EPCM hereby certifies that the above System has been completely commissioned and stabilized in accordance with the
requirements of the CONTRACT, with the exception of the outstanding items listed upon the attached Punch list.
The system has been checked for Operability of 72 Hours and has been satisfactorily taken over by COMPANY for Regular
Operations.
Attachments:
1. Commissioning Certificates
2. PGTR DCS signed Log Sheets / Hard Copy of Log Sheet
3. Master Punch List
Remarks:
Name
Signature
Date
INDIAN OIL
CORPORATION LTD.
GUWAHATI REFINERY
EPCM Work for Revamp of 1.2 PGTR Client Contract No.:
MMTPA CDU,NSF and NSU at IOCL GC21EST136/27311004
GUWAHATI REFINERY CERTIFICATE
System. ALL THE SYSTEM AS PER PGTR PROCEDURE OF TOPPED CRUDE PUMP (P-34 A)
Sub System. AS PER DCS LOG DATA / HARD COPY OF LOG SHT
The system has been checked for Operability of 72 Hours and has been satisfactorily taken over by COMPANY for Regular
Operations.
Attachments:
1. Commissioning Certificates
2. PGTR DCS signed Log Sheets / Hard Copy of Log Sheet
3. Master Punch List
Remarks:
Name
Signature
Date
INDIAN OIL
CORPORATION LTD.
GUWAHATI REFINERY
EPCM Work for Revamp of 1.2 PGTR Client Contract No.:
MMTPA CDU,NSF and NSU at IOCL GC21EST136/27311004
GUWAHATI REFINERY CERTIFICATE
System. ALL THE SYSTEM AS PER PGTR PROCEDURE OF TOPPED CRUDE PUMP (P-34 B)
Sub System. AS PER DCS LOG DATA / HARD COPY OF LOG SHT
EPCM hereby certifies that the above System has been completely commissioned and stabilized in accordance with the
requirements of the CONTRACT, with the exception of the outstanding items listed upon the attached Punch list.
The system has been checked for Operability of 72 Hours and has been satisfactorily taken over by COMPANY for Regular
Operations.
Attachments:
1. Commissioning Certificates
2. PGTR DCS signed Log Sheets / Hard Copy of Log Sheet
3. Master Punch List
Remarks:
Name
Signature
Date
INDIAN OIL
CORPORATION LTD.
GUWAHATI REFINERY
EPCM Work for Revamp of 1.2 PGTR Client Contract No.:
MMTPA CDU,NSF and NSU at IOCL GC21EST136/27311004
GUWAHATI REFINERY CERTIFICATE
System. ALL THE SYSTEM AS PER PGTR PROCEDURE OF NAPTHA SPLITTER BOTTOM PUMP (P-51A)
Sub System. AS PER DCS LOG DATA / HARD COPY OF LOG SHT
EPCM hereby certifies that the above System has been completely commissioned and stabilized in accordance with the
requirements of the CONTRACT, with the exception of the outstanding items listed upon the attached Punch list.
The system has been checked for Operability of 72 Hours and has been satisfactorily taken over by COMPANY for Regular
Operations.
Attachments:
1. Commissioning Certificates
2. PGTR DCS signed Log Sheets / Hard Copy of Log Sheet
3. Master Punch List
Remarks:
Name
Signature
Date
INDIAN OIL
CORPORATION LTD.
GUWAHATI REFINERY
EPCM Work for Revamp of 1.2 PGTR Client Contract No.:
MMTPA CDU,NSF and NSU at IOCL GC21EST136/27311004
GUWAHATI REFINERY CERTIFICATE
System. ALL THE SYSTEM AS PER PGTR PROCEDURE OF NAPTHA SPLITTER BOTTOM PUMP (P-51B)
Sub System. AS PER DCS LOG DATA / HARD COPY OF LOG SHT
EPCM hereby certifies that the above System has been completely commissioned and stabilized in accordance with the
requirements of the CONTRACT, with the exception of the outstanding items listed upon the attached Punch list.
The system has been checked for Operability of 72 Hours and has been satisfactorily taken over by COMPANY for Regular
Operations.
Attachments:
1. Commissioning Certificates
2. PGTR DCS signed Log Sheets / Hard Copy of Log Sheet
3. Master Punch List
Remarks:
Name
Signature
Date
INDIAN OIL
CORPORATION LTD.
GUWAHATI REFINERY
EPCM Work for Revamp of 1.2 PGTR Client Contract No.:
MMTPA CDU,NSF and NSU at IOCL GC21EST136/27311004
GUWAHATI REFINERY CERTIFICATE
System. ALL THE SYSTEM AS PER PGTR PROCEDURE OF STABILIZER REBOILER (E-031)
Sub System. AS PER DCS LOG DATA / HARD COPY OF LOG SHT
EPCM hereby certifies that the above System has been completely commissioned and stabilized in accordance with the
requirements of the CONTRACT, with the exception of the outstanding items listed upon the attached Punch list.
The system has been checked for Operability of 72 Hours and has been satisfactorily taken over by COMPANY for Regular
Operations.
Attachments:
1. Commissioning Certificates
2. PGTR DCS signed Log Sheets / Hard Copy of Log Sheet
3. Master Punch List
Remarks:
Name
Signature
Date
INDIAN OIL
CORPORATION LTD.
GUWAHATI REFINERY
EPCM Work for Revamp of 1.2 PGTR Client Contract No.:
MMTPA CDU,NSF and NSU at IOCL GC21EST136/27311004
GUWAHATI REFINERY CERTIFICATE
EPCM hereby certifies that the above System has been completely commissioned and stabilized in accordance with the
requirements of the CONTRACT, with the exception of the outstanding items listed upon the attached Punch list.
The system has been checked for Operability of 72 Hours and has been satisfactorily taken over by COMPANY for Regular
Operations.
Attachments:
1. Commissioning Certificates
2. PGTR DCS signed Log Sheets / Hard Copy of Log Sheet
3. Master Punch List
Remarks:
Signature
Date