You are on page 1of 1

SUMMARY FOR FREQUENCY TEST OF VARIOUS ITEMS

SIMPLEX-BCPL-PERFECTO (JV)
DOUBLING BETWEEN KOTA AND BINA ,PKG-III
Up to 31,May 2018
Total
BOQ No of Test Test report
Sl. No Description Unit Executed Frequency of Test Remarks
Item No req. submitted
Qty
1 1001 Earth work Cum. 414782.64
(a) MDD / OMC
(b) GSA
One test per 2000Cum 240 392
(c) LL,PL, & PI
(d)FSI
(e) CBR
One density measurement at
(f)FDD every 200 sqm surface area of 8488 8942
each compacted layer
2 1004 Blanketing Cum. 211192.94
(a) MDD / OMC
(b) GSA
One test per 500 Cum 512 665
(c) Cu,Cc
(d) LAA
(e) CBR
One density measurement at
(f)FDD every 200 sqm surface area of 4340 4924
each compacted layer

One test per batch or 1000 bags


3 8001 Cement Bag 60119.53 110 117
which ever is more frequent

4 2061 Steel (Reinforcement)


received Qty. as per
Up to 10 mm Dia Mt. 214.47 One test per 25 Mt 9 12 steel passing
register
Above 10 mm Dia Mt. 682.191 One test per 40 Mt 17 22
5 3001 Ballast Cum. 151176.595 One test per 2000 Cum 76 84
6 2004 M-20 Grade of Concrete Cum. 927.795 As per IS 456 (Comp.Strength) 159 159
7 2005 M-30 & M-35Grade of Concrete Cum. 5506.06 As per IS 456 (Comp.Strength) 1088 1088
8 2011 M-45 Grade of Concrete Cum. 252.69 As per IS 456 (Comp.Strength) 46 46