Professional Documents
Culture Documents
Cash flow projection : The project of income and expense during the life of a project
can be developed from several time-scheduling aids used by the contractor
Elements of the Cash flow stream
Cash Inflow Cash outflow
Operating cash inflows : After tax cash inflows resulting from the operations of the project
during it’s economic life
Terminal Cash inflow : After tax cash flow resulting from the liquidation of the project at
the end of it’s economic life
Time horizon for cash flow : minimum of Physical life, Technological life , Product life of
a project & Investment planning horizon
Financial Analysis & Project Financing
Project Evaluation methods
• Discounting Criterion
• Net Present Value (NPV)
• Benefit Cost Ratio
• Internal Rate of return (IRR)
• Non-Discounting Criterion
• Payback period
• Accounting Rate of Return
Project Evaluation methods -
NPV
Project Evaluation methods -
NPV
Project Evaluation methods -
NPV
Project Evaluation methods -
NPV
Project Evaluation methods – NPV with
Time varying discount rate
$ Year Cash flow Discount
𝑪𝑭! Rate
NPV =! ! − 𝑖𝑛𝑖𝑡𝑖𝑎𝑙 𝑖𝑛𝑣𝑒𝑠𝑡𝑚𝑒𝑛𝑡
!"# #'(! 0 -40000 --
1 10000 14%
CFt = cash flow at the end of year t 2 12000 15%
kt = discount rate for a given year t 3 15000 16%
4 10000 18%
5 7000 20%
Project Evaluation methods – NPV with
Time varying discount rate
Year Cash flow Discount Rate Present Value (PV) of CFt
(t) (CFt) (kt)
NPV = 8771.9 +
0 -40000 -- --
9153.3+9863.4+5572.5
1 10000 14% 10000/1.14 = 8771.9 +3250.6 - 40000
2 12000 15% 12000/(1.14 x 1.15) = 9153.3 = -3388.3
3 15000 16% 15000/(1.14 x 1.15 x 1.16) = 9863.4 Since NPV is negative
4 10000 18% 10000 /(1.14 x 1.15 x 1.16 x 1.18) = 5572.5 project is rejected
5 7000 20% 7000 /(1.14 x 1.15 x 1.16 x 1.18 x 1.2) = 3250.6
Class discussion : In which situations NPV will be positive ? What it means in terms of business ?
Project Evaluation methods – Benefit
Cost ratio (profitability Index)
"#$ Year Cash flow Cost of Present value
BCR =
%
𝑤ℎ𝑒𝑟𝑒 capital
BCR = Benefit Cost ratio 0 -40000 --
PVB = present value of benefits
1 10000 10000/1.13 = 8849.55
I = initial investment
NBCR = Net Benefit cost ratio 2 12000 12000 / (1.132 ) = 9397.7
2 -10000
• If both the roots are positive then we will get 2 IRRs and both will be
valid & it will not be possible which IRR value is correct value
Project Evaluation methods –
Payback period
Payback period is length of time required to recover initial cash outlay on the project
Year Cash flow Cumulative
(t) (CFt) Cash flow
0 -40000 --
Payback period is simple for application but does not consider
1 10000 10000 time value of money
2 12000 22000
3 15000 37000
v Separation Principle
v Incremental Principle
v Post-Tax Principle
v Consistency Principle
Basic principles of Cash flow estimation
Separation Principle