You are on page 1of 11

LOGO

SPECIFICATIONS
(PROJECT TITLE)

SPECIFICATIONS

PERSPECTIVE

(PROJECT TITLE)
(ADDRESS/LOCATION)

(OWNER)

Prepared by:

_______________________________
Architecture Student
Student Number

P a g e 1 | 11
LOGO
SPECIFICATIONS
(PROJECT TITLE)

SPECIFICATION

Project : ___________________________________
Location: ___________________________________
Owner: ___________________________________

I. GENERAL CONDITIONS
All parts of the construction shall be finished with first class workmanship,
to the fullest talent and meaning of the plans and these Specifications, and to
the entire satisfaction of the Architect and the Owner.
The construction shall conform to all the requirements of the National
Building Code, as well as the local rules and regulations of the Municipality/City
of ______________, Philippines.

II. CLEARING OF THE SITE


The building site shall be leveled according to the plans and cleared of
rubbish, roots and other perishable and objectionable matters to a suitable
subgrade.
All such unsuitable materials shall be removed from the building site and
spread uniformly over the areas adjacent to the proposed building, or
otherwise disposed of as may be directed by the Architect or Engineer in
charge of the construction.

III. STAKING OUT OF THE BUILDING LINES


The building lines shall be staked out and all lines and grades shown in
the drawing established before any excavation is started. Batterboards and
reference marks shall be erected at such places where they will not be
disturbed during the excavation of the building.

IV. EXCAVATION
All excavation must be protected when unattended on site for safety
purposes.
P a g e 2 | 11
LOGO
SPECIFICATIONS
(PROJECT TITLE)

All excavations shall be made to grade indicated in the drawings. Where


the building site is covered with any kind of fill, the excavation for footings
should be made deeper until the stratum for safe bearing capacity of the soil
is reached.
Whenever water is encountered in the excavation process, it shall be
removed by bailing or pumping, care being taken that the surrounding soil
particles are not disturbed or removed.
All excavated areas shall be applied with Termite Control to prevent
termite infestation on the said areas. Use Type 1 Termite Control for Foundation
areas.

V. BACKFILLS
After concrete for foundations is hard enough to withstand pressure
resulting from fills, the materials removed from excavations shall be used for
backfill around them.
Backfills and fills shall be placed in layers not exceeding 150mm in
thickness, and each layer shall be thoroughly compacted by wetting, tamping
and rolling.

VI. CONRETE WORKS


All concrete shall be mixed thoroughly until there is a uniform distribution
of the cement and aggregates, and should be deposited as nearly as
practicable in its final position, care being taken to avoid segregation of the
aggregates.

Water to be used for mixing concrete shall be clean and free from
injurious amount of oil, acids, alkalis, salts and other organic materials.
Each batch of concrete pouring should have concrete samples for
testing and should pass the required workability and strength. All concrete
must be subjected for both slump and compression test.

P a g e 3 | 11
LOGO
SPECIFICATIONS
(PROJECT TITLE)

VII. PROPORTIONING OF CONCRETE


All concrete works shall be done in accordance with the standard
specification for plain and reinforced concrete as adopted by the
Government. Cement to be used shall be Lafarge cement, Republic cement
or any other equivalent brands more readily available in the locality.
Alternative cements so selected must meet the requirements of Portland
and pozzolan cements, and approved by Architect or Engineer in charge of
construction.
The following proportions of concrete mixtures shall be used for the
various parts of the building:
Columns and Footings - Class A (1:2:4)
Concrete Hollow Blocks Footings - Class A (1:2:4)
Reinforced Conc. Beams and Slab - Class B (1:2.5:5)
Concrete Slab Floor on Fill - Class B (1:2.5:5)
Septic Vault Cover - Class A (1:2:4)
Concrete Plant box and Walkway - Class C (1:3:6)

Class A concrete shall be a mixture of 1-part cement, 2 parts fine


aggregate and 4 parts coarse aggregate by volume, plus enough clean water
to make the mixture into a pliable paste.
Class B concrete shall be a mixture of 1-part cement, 2-1/2 parts fine
aggregate and 5 parts coarse aggregate by volume, plus enough clean water
to make the mixture into a pliable paste.
Class C concrete shall be a mixture of 1-part cement, 3 parts fine
aggregate and 6 parts coarse aggregate by volume, plus enough clean water
to make the mixture into a pliable paste.
The fine aggregate for concrete shall consist of natural sand, or of inert
materials with similar characteristics, having clean, hard and durable grains,
free from organic matter or loam.

P a g e 4 | 11
LOGO
SPECIFICATIONS
(PROJECT TITLE)

The coarse aggregate for concrete shall consist of crushed rock of


durable and strong qualities, or clean and hard gravel. Size of the coarse
aggregate to be used shall vary from 20mm to 40mm (3/4” TO 1-1/2”).

VIII. FORMS FOR CONCRETE WORKS


All forms for concrete works shall be properly braced or connected
together so as to maintain the correct position and shapes of the concrete
members. Forms shall be constructed sufficiently tight to prevent bulging and
seepage of water.
All concrete forms shall be constructed and installed with ¾” thick
Phenolic Board with corresponding accessories.
Forms shall not be removed until the concrete has attained sufficient
strength to support its own weight and any loads that may be placed on it.
Side forms of beams and girders may beremoved earlier than the bottom forms
but additional posts or shoring must be placed under the beams or girders until
they have attained their strength.
For columns, 3 days after before the removal of its formworks and 21 days
after for stairs, beams and slab bottom formworks.

IX. CONCRETE SLAB FLOOR ON FILL


Concrete slab on fill shall be poured on a gravel bed not less than
100mm thick. Each concrete slab course to be poured shall not be more than
one-meter-wide, and each course shall be poured alternately to the indicated
floor finish.

X. BALCONY CONCRETE FLOOR SLABS


When preparing the concrete for upper floor slabs Toilet-Bath and
balcony it shall be made water proofing by adding ABC waterproofing
compound to the mixture or any other equivalent brands more readily
available in the locality.

P a g e 5 | 11
LOGO
SPECIFICATIONS
(PROJECT TITLE)

The proportion of the waterproofing compound to a given volume of


concrete mixture shall be as recommended by the product manufacturer.

XI. STEEL REINFORCING BARS


All steel reinforcing bars to be used in this construction shall consist of
round deformed bars with lugs or projections on their sides to provide a greater
bond between the concrete and the steel.
For this project, rebars should be atleast Grade 230 based on Philippine
National Standard. It is also advisable to use 6-to-7.5-meter commercial length
of steel rebars for easy and convenient delivery of purchased rebars.
All steel reinforcing bars shall be accurately placed and secured against
displacement by tying them together at each bar intersection with Gauge No.
16 galvanized iron wire.
The steel reinforcing bars indicated for footings, columns, slabs, beams,
girders and other concrete members shall all conform to the number, size and
spacing as indicated in the drawings or schedule of steel reinforcements.
No metal reinforcement shall be installed in place unless it is free from
rust, scale or other coatings, which will destroy or reduce the bond with
concrete.

XII. CONCRETE HOLLOW BLOCKS


All exterior concrete hollow blocks to be used for the first-floor walls shall
be at least 150mm thick, while concrete hollow blocks for interior walls unless
otherwise indicated, shall be100mm thick.
Concrete hollow block to be used for wall above the first floor, shall be
100mm thick for interior wall and 150mm for exterior wall.
All concrete hollow blocks to be used for Firewall must be 150mm thick.
The concrete hollow block walls shall be laid, and the cells filled with cement
mortar consisting of 1 part portland cement and 3 parts sand by volume. They
shall be reinforced with round deformed bars, 10mm diameter, spaced not
more than 0.80m on centers, bothways.

P a g e 6 | 11
LOGO
SPECIFICATIONS
(PROJECT TITLE)

All exposed surfaces of concrete hollow block walls shall be finished with
the specified materials indicated on the elevation drawings either plain finish
or sandblast finish for the exterior.
The mixture of cement plaster for concrete hollow block wall finishes
indicated in the drawings shall be 1-part cement, 1 part lime and 3 parts sand.

XIII. DRYWALL PARTITIONS


All drywall partitions must be installed with vertical studs screwed to
tracks with 400mm spacing on-center for fiber cement board and 600mm on-
center for gypsum board.
All partition must install C-Channel on center and bottom tracks must be
nailed to floor slab with the use of 2” concrete nails spaced at 200mm on-
center.
Drywall partitions must be Gypsum or Fiber Cement Board provided with
2-3mm spacing between boards for putty application.

XIV. FLOOR FINISHES


The materials to be used as floor finishes for the common area, Bedrooms
building shall be 200mm x 1200mm ceramic wood planks, for Lanai shall be
600mm x 600mm ceramic tiles and for balcony, a 200mm x 200mm unglazed
ceramic- heterogenous tiles shall be installed (verify color scheme) as per
owner’s approval.

XV. TILE WALL AND FLOOR FINISHES


All tiles for floor, walls, and mouldings shall be free from laminations,
serrated edges, chipped-off corners and other defects, which would adversely
affect their appearance and strength. All joints between tiles and mouldings
shall be filled with Tile Grout and then carefully wiped.
Before the tiles and mouldings are laid in place, they shall be thoroughly
soaked in water if recommended by the manufacturer. Mortar to be used in

P a g e 7 | 11
LOGO
SPECIFICATIONS
(PROJECT TITLE)

setting the tiles and mouldings shall be a mixture of 1-part cement and 2 parts
sand by volume.

XVI. CEILING
All ceiling works must be installed using steel frame or ceiling joist with
600mm spacing on-center, both-ways with ¼” thick cement board. Ceiling
shat be painted with matte paint.

XVII. LUMBER
Lumber to be used in this project shall be well seasoned, thoroughly dry
and free from loose or unsound knots, shakes or other imperfections impairing
their strength or appearances.
The kind of lumber to be used for the various parts of the building shall
be as follows:
Built-ins Cabinets………………………………..3/4” Thick Plywood

XVIII. ROOFING
The roofing to be used in the project shall be the same roof tiles from the
existing roof of the house to be extended.
All roofing adjacent to concrete hollow block and other masonry walls
such as the property line firewalls, shall be provided with Gauge No. 26 plain
GI flushing to extend up to the top and over to the other side of the wall.

XIX. ELECTRICAL WORKS


The electrical installation shall be done with accordance with the
approved plans and under the direct supervision and control of a licensed
Professional Electrical Engineer or Master Electrician.
All electric works and materials shall conform to the provisions of the
Specifications from Electrical Engineer based on the latest edition of the
Philippine or National Electrical Code.

P a g e 8 | 11
LOGO
SPECIFICATIONS
(PROJECT TITLE)

XX. PLUMBING WORKS


All plumbing works for this project shall be done in accordance with the
approved plans and under the direct supervision and control of a licensed
Sanitary Engineer and Master Plumber.
Piping shall be properly graded or pitched to ensure easy circulation,
drainage and prevent water hammer and noise.
The plumbing installation shall conform with the provisions of National
Plumbing Code of the Philippines and the rules and regulations enforced in the
locality.

XXI. DOORS AND DOOR FRAMES


Doors and door frames shall conform to the sizes, design and kind of
materials shown in the details of doors, schedule of doors or as per the bill of
materials.
All wooden doors shall be hung on at least 3 pieces of 102mm x 102mm
(4”x4”) loose-pin bearing template hinges.
Door locksets to be used shall be installed 1024mm from the finished floor
line.

XXII. STEEL WINDOWS


Steel windows to be used in this project shall conform to the size and
design shown in the detail drawings or schedule of steel windows, or as per the
bill of materials.
In the case of discrepancies on measurements, contractor/ supplier
must conduct actual site measurements to ensure the correct dimensions for
fabrication to lessen the actual discrepancy.

XXIII. STEEL WORKS


The materials to be used in this project shall conform to the size and
design shown in the detail drawings and details of balcony railings and gate
fence, or as per the bill of materials.

P a g e 9 | 11
LOGO
SPECIFICATIONS
(PROJECT TITLE)

XXIV. PAINTING
All painting works for this project, except as hereinafter specified, shall
be done with the used of Boysen paint products or any other equivalent brands
more readily available in the locality.
The use of latex paint is highly advisable for concrete surface to avoid
paint cracking and peeling. Painting works for steel works shall be applied with
red oxide to prevent steel from rusting.
The painting contractor shall supply all tabor, paint materials, tools,
staging and equipment necessary, and shal perform all painting and finishing
work as shown in the schedule of painting and finishing work for this project.
The painting contractor shall store his materials in one place in the
building to be kept neat and clean, care being taken in the storage of paints,
oils, etc. to prevent danger of fire.
Oily rags shall be kept in metal containers and shall be removed from
the building every end of the working day.
Upon completion of the painting works, the painting contractor shall
remove any paint spot from all finished work. He shall present his work to the
project owner or architect/engineer in charge of construction, free from
blemishes and rubbish generated by his workers.
It shall be the painting contractor’s responsibility to protect his work and
those of other contractors during the time his work is underway. He shall be
responsible for any damage to the work or property of others caused by his
employees or by himself.
Before any painting is done, all surfaces shall be cleaned, smoothed and
freed from dust, dirt, grease, mortar, rust and any other foreign substances. All
parts where the paint remover has been used shall be washed off with paint
or lacquer thinner. All paints shall be spread evenly and carefully,
All paint and paint materials shall be delivered to the building site in
unbroken packages, bearing the marks of the specified brand. No
adulteration of specified paints with other brands shall be allowed.

P a g e 10 | 11
LOGO
SPECIFICATIONS
(PROJECT TITLE)

XXV. WATERPROOFING
Wet areas such as Toilet and Bath located at Second Floor and Balcony
flooring shall be applied with 4mm thick waterproofing membrane using
blowtorch before installing floor finishing.
Waterproofing Testing must be performed to ensure the water tightness
of the areas. Water tightness should be monitored for atleast 2 days to ensure
that there is no water leakage.

Prepared by: Conforme’/ Approved

_____________________________ _____________________________
Architecture Student Owner
Student Number

P a g e 11 | 11

You might also like