BEAM SCHEDULE (C28:Fy415) (LEVEL: 5.

28m)

BEAM SIZE BOTTOM REINFORCEMENT TOP REINFORCEMENT SHEAR STIRRUPS


SFR DIAGONAL REMARKS
NUMBERS B D LEFT MID SPAN RIGHT LEFT MID SPAN RIGHT LEFT MID SPAN RIGHT
B1,B2,B3,B4 200 300 2-#16 2-#16 2-#16 2-#16 2-#16 2-#16 8-2L-#10@125 C/C 6-2L-#10@125 C/C 8-2L-#10@125 C/C - - -

B5,B6,B7,B8,B9 200 300 2-#16 2-#16 2-#16 2-#16 2-#16 2-#16 5-2L-#10@125 C/C 3-2L-#10@125 C/C 5-2L-#10@125 C/C - - -
,B10,B11,B12,B13
,B14,B16,B17,B18
,B19,B20
B15 200 300 2-#16 2-#16 2-#16 2-#16 2-#16 2-#16 6-2L-#10@125 C/C 4-2L-#10@125 C/C 6-2L-#10@125 C/C - - -

BEAM SCHEDULE (C28:Fy415) (LEVEL: 3.04m)

BEAM SIZE BOTTOM REINFORCEMENT TOP REINFORCEMENT SHEAR STIRRUPS


SFR DIAGONAL REMARKS
NUMBERS B D LEFT MID SPAN RIGHT LEFT MID SPAN RIGHT LEFT MID SPAN RIGHT
B1,B2,B3,B4 200 300 2-#16 2-#16 2-#16 2-#16 2-#16 2-#16 8-2L-#10@125 C/C 6-2L-#10@125 C/C 8-2L-#10@125 C/C - - -

B5,B6,B7,B8,B9 200 300 2-#16 2-#16 2-#16 2-#16 2-#16 2-#16 5-2L-#10@125 C/C 3-2L-#10@125 C/C 5-2L-#10@125 C/C - - -
,B10,B11,B12,B13
,B14,B16,B17,B18
,B19,B20
B15 200 300 2-#16 2-#16 2-#16 2-#16 2-#16 2-#16 6-2L-#10@125 C/C 4-2L-#10@125 C/C 6-2L-#10@125 C/C - - -

BEAM SCHEDULE (C28:Fy415) (LEVEL: 0m)

BEAM SIZE BOTTOM REINFORCEMENT TOP REINFORCEMENT SHEAR STIRRUPS


SFR DIAGONAL REMARKS
NUMBERS B D LEFT MID SPAN RIGHT LEFT MID SPAN RIGHT LEFT MID SPAN RIGHT
B1,B2,B3,B4 200 300 2-#16 2-#16 2-#16 2-#16 2-#16 2-#16 8-2L-#10@125 C/C 6-2L-#10@125 C/C 8-2L-#10@125 C/C - - -

B5,B6,B7,B8,B9 200 300 2-#16 2-#16 2-#16 2-#16 2-#16 2-#16 5-2L-#10@125 C/C 3-2L-#10@125 C/C 5-2L-#10@125 C/C - - -
,B10,B11,B12,B13
,B14,B16,B17,B18
,B19,B20
B15 200 300 2-#16 2-#16 2-#16 2-#16 2-#16 2-#16 6-2L-#10@125 C/C 4-2L-#10@125 C/C 6-2L-#10@125 C/C - - -

A C

300 300

2400

200

2-#16
2-#16
STP 2L-#10
300

2-#16
2-#16

21-2L-#10
B1
@125 C/C

(SCALE 1:25)

B1:200x300
(SCALE: H = 1:50 / V = 1:50)
C1 C2

BEAM SCHEDULE AND DETAILS