MAIN BARS (TOP BARS)

SPAN, L
EXTRA BARS (TOP BARS)
L/4 L/4

COLUMN CLEAR SPAN, L COLUMN TOP BARS DIS-CONTINOUS


TOP BARS CONTINOUS
L/4 L/4
SPLICE LENGTH THK.
200mm HOOK

BOTTOM BARS

L/6 L/6
1@50; @100 @100 1@50; @100

MAIN BARS (BOTTOM BARS)

EXTRA BARS (BOTTOM BARS)

TYPICAL BEAM DETAILS 200 200 200 200


SCALE: NTS 5-#16 2-#16 4-#16 2-#16

400 STP 2L-#10 400 STP 2L-#10 400 STP 2L-#10 400 STP 2L-#10

2-#16 3-#16 2-#16 3-#16

BEAM/GIRDER SCHEDULE B1 @ SUPPORT B1 @ MIDSPAN CB @ SUPPORT CB @ MIDSPAN

200 200 200 200


3-#16 2-#16 3-#16 2-#16

300 STP 2L-#10 300 STP 2L-#10 300 STP 2L-#10 300 STP 2L-#10
2-#16 3-#16 2-#16 3-#16

B2 @ SUPPORT B2 @ MIDSPAN RB @ SUPPORT RB @ MIDSPAN

200 200
4-#16 2-#16

400 STP 2L-#10 400 STP 2L-#10


2-#16 3-#16

FTB @ SUPPORT FTB @ MIDSPAN

BEAM SECTIONS
SCALE: NTS

CLIENT'S GOVERNMENT
CONSTRUCTION
APPROVAL APPROVAL

S-4