04.1 Week-04 Preconstruction Planning, Site Layout, Mobilization, Site Team
04.1 Week-04 Preconstruction Planning, Site Layout, Mobilization, Site Team
Engineering Economics
CE-406
Spring 2024
Preconstruction planning, area and site investigation,
constructability review, site
layout planning, Contractor’s site (team) organization
chart & mobilization plan
Week # 04
2
Site Layout Planning
Introduction
❑ The layout of a construction site plays a major role in the
safety and productivity of operations, particularly when the
site space is restricted.
❖ maintenance shops,
❖ batch plant,
❖ food mess
❖ grocery shops,
❖ dispensary, and
4
Site Layout Planning
Objectives
❑ Site layout planning objectives are:
➢ Site must be designed to maximize efficiency of
operations in order to promote worker productivity, to
shorten project time and to reduce cost
➢ It must create a project with a good work environment
in order to attract and retain the best personnel and
thus contribute to better work quality and productivity
❑ A well planned site including all facilities and utilities lead
to:
➢ increasing productivity and safety
➢ reducing area(s) needed for temporary construction
➢ maximizing utilization
8
Site Layout Planning
Site Layout Elements
❑ The following elements which should be considered during
site layout planning
➢ Safety
➢ Site accessibility
➢ Information signs
➢ Security
➢ Accommodation
➢ Offices
➢ Water supply & sanitation
➢ Material Handling
➢ Storage & Site Cleaning
➢ Batch Plant and fabrication shops
13
Organization of Construction Company
(Small)
14
Organization of Construction Co. (Medium)
15
Organization of Construction Co. (Large)
16