□ Interim
√ Final
Stage of inspection :
Before manufacturing Main Conclusions & Remarks:
During manufacturing
Final - See recommendation’s and perform corrective action
Packing accordingly.
Type of inspection:
Pre-inspection meeting
Document and QC record review
Visual examination, checks Next visit scheduled:
Witnessing tests
Manufacturing progress status Before 26 November-2024
Vendor assessment
Final inspection
Packing
(for details see continuation sheet)
Stamping :
No
□ Interim
√ Final
Introduction:
MAZADA Consortium Limited has signed Third Party Inspection contract with Bureau Veritas
(Bangladesh) Private limited, Bangladesh. BV Bangladesh conducted the inspection on 26/11/2023 at
Mazada equipment yard, Madanpur, Narayanganj and the attendee was as under:
Md. Ariful Islam, Industrial Surveyor, Bureau Veritas (Bangladesh) Private limited.
□ Interim
√ Final
□ Interim
√ Final
Load Calibration:
Actions Recommended:
1. Spark arrestor need to be attached.
2. Proper maintenance should be followed as per manufacturer schedule and record.
3. Based on thorough visual examination, functional and proof load test the equipment described
above was found satisfactory at the time of inspection.
The inspection results are valid at time and place of inspection. The above inspection has been carried out according to Bureau
Veritas general conditions of service, the issuance of this inspection report does not release the contractual parties from their
own responsibilities and the fulfilment of their obligations.
□ Interim
√ Final
Boom Hooks
□ Interim
√ Final