You are on page 1of 7

PRESENTATION

SHUTDOWN VIA TEMPORARY


COMPACT SUBSTATION

1
EXISTING

EMSB1 EMSB2
MSB1 MSB1
MSB2 ANNEX MAIN MSB2
BLOCK AMF AMF
BLOCK

TX.2 TX.1 TX.1 TX.2


1600KVA 1600KVA G GENSET 1 G GENSET 2
650KVA
2000KVA 2000KVA
450KVA

HV.1 HV.3

HT.2 SW.GEAR
HV.2

HV.1 HV.2 HV.6

HT.1 SW.GEAR

TNB SSU
2
EXISTING

TEMP.
MSB EMSB1 EMSB2
MSB1 MSB1
MSB2 ANNEX MAIN MSB2
BLOCK AMF AMF
BLOCK

TX.2 TX.1 TX.1 TX.2


COMPACT TEMP. 1600KVA 1600KVA G GENSET 1 G GENSET 2
650KVA
2000KVA 2000KVA
450KVA
SUBSTATION 1000KVA
1000KVA GENSET HV.1 HV.3

HT.2 SW.GEAR
HV.2

HV.1 HV.2 HV.6 INSTALLATION WORKS


HT.1 SW.GEAR 1. Install Temp. Compact Substation , Temp. Genset and
Temp. MSB

TNB SSU
3
EXISTING

TEMP.
MSB EMSB1 EMSB2
MSB1 MSB1
MSB2 ANNEX MAIN MSB2
BLOCK AMF AMF
BLOCK

TX.2 TX.1 TX.1 TX.2


COMPACT TEMP. 1600KVA 1600KVA G GENSET 1 G GENSET 2
650KVA
2000KVA 2000KVA
450KVA
SUBSTATION 1000KVA
1000KVA GENSET HV.1 HV.3

HT.2 SW.GEAR
HV.2

HV.1 HV.2 HV.6 SHUTDOWN FOR ANNEX BLOCK – HT.1 SW.GEAR


HT.1 SW.GEAR 1. Liaise with TNB for shutdown
2. Shutdown of HT.1 SW.GEAR panels
3. Dismantle
4. Dismantle HT1.SW gear
5. Install and commissioning new HT.1 SW gear
TNB SSU 6. Commission Temp. Genset & Temp. MSB as back up
4
EXISTING

TEMP.
MSB EMSB1 EMSB2
MSB1 MSB1
MSB2 ANNEX MAIN MSB2
BLOCK AMF AMF
BLOCK

TX.2 TX.1 TX.1 TX.2


COMPACT TEMP. 1600KVA 1600KVA G GENSET 1 G GENSET 2
650KVA
2000KVA 2000KVA
450KVA
SUBSTATION 1000KVA
1000KVA GENSET HV.1 HV.3

HT.2 SW.GEAR
HV.2

HV.1 HV.2 HV.6 SHUTDOWN FOR ANNEX BLOCK – TRANSFORMERS


HT.1 SW.GEAR 1. Shutdown of HT.1 SW.GEAR panels
2. Dismantle Transformers
3. Install and commissioning new Transformers
4. Commission Temp. Compact Substation, Temp. Genset & Temp.
MSB as back up
TNB SSU
5
MSB OUTGOING
CABLES

TEMP.
MSB EMSB1 EMSB2
MSB2 MSB1 MSB1
ANNEX MAIN MSB2
BLOCK AMF AMF
BLOCK

TX.2 TX.1 TX.1 TX.2


COMPACT TEMP. 1600KVA 1600KVA G GENSET 1 G GENSET 2
650KVA
2000KVA 2000KVA
450KVA
SUBSTATION 1000KVA
1000KVA GENSET HV.1 HV.3

HT.2 SW.GEAR
HV.2

HV.1 HV.2 HV.6 SHUTDOWN FOR ANNEX BLOCK – MAIN SWITCHBOARD


HT.1 SW.GEAR 1. Switch off VCB breaker of HV.1 and HV.2
2. Transfer outgoing MSB to Temp. MSB
3. Dismantle MSB / EMSB
4. Install new MSB / EMSB
5. Transfer outgoing Temp. MSB cables to new MSB
TNB SSU 6. Resume HV.1 and HV.2 power supply
6
COMPARISON OF BACK UP POWER SUPPLY

TEMP. TEMP.
MSB MSB

COMPACT TEMP. TEMP.


SUBSTATION 1000KVA 1000KVA
1000KVA GENSET GENSET

1. Back up power supply is 2000kVA 1. Back up power supply is 1000kVA


• Annex block 63% Transformer load • Annex block 31% of Transformer load
• Main Block 50% of Transformer load • Main Block 25% of Transformer load
2. Duration of back up 2. Duration of back up
• Compact substation no limit • Temp. Genset 3 days
• Temp. Genset 3 days