PLTU LONTAR EXTENTION

REVIEW OF TEST PROCEDURE DOCUMENTS


Transmittal No : CONS-PLN-6064 Submittal Date : 28 July, 2020
DOCUMENT NUMBER DOCUMENT TITLE
PLN REV CONTRACTOR REV STATUS
Bonafide Test Procedure for Boiler Maximum Continuous Rating
1 0 C
No. PUSERTIF<>LMK<>PLN COMMENTS Contractor Response

1 [General] Please change transmital letter from "for information" to "for review and comment". Noted.

(General) This document outlines the procedure for overall plant test requirement and condition at BMCR load condition
- Boiler Performance Test Procedure shall include at least Boiler Efficiency at BMCR, 100%, 75%, 50%. Boiler Maximum Flow Capacity, of the plant.
Excess Air & Furnace Leakage as per schedule 6 subsection NO.7 - 11 can include in this procedure or in separate document, We
suggest to merge those items in one procedure to minimize Or avoid formula repetition in each procedure. Please note that Boiler Performance Test Procedure (Document No: K097-021) includes all the test
3 requirement and calculation for Boiler as per schedule 6 subsection NO.7 - 11.

This Boiler Performance Test Procedure is not attached herewith in this document to avoid repetition of
documents.

Noted.
The main steam flow in MFMSG is 4tph higher than BMCR. As the flow difference is minor we agree with PLN
(Generall to mearge BMCR and MFMSGC test.
4 • What the different basis condition or parameter to be reach between BMCR test and Maximum Flow Main Steam Generator
Capability Test? If it Will be reach same parameter or condition, we suggest to merge those test. We will include note in both the procedures that a common test would be conducted.

- JHA checklist verification has been added into Section 3.3 Test Prerequisition for safety precaution.
3.3 Test Prerequisition
5 - for any sistem test procedure, please add and submit JSA (Job Safety Analysis) first as an attachment for safety precaution. - Calibration certificate for any temporary instruments, if used will be provided prior to the test.
- For any instrument calibrated sertificate should be attached in this procedure.

3.4 Test Condition


- Valve isolation list already provided in Appendix B and is updated to include sign-off for EPC and Owner to
6 - 3.4.2 Valve Position Lineup ....Please provide checklist form for visual check for isolation valve that will be visually check and witnesses
visually check, witness and sign-off the valve isolation before performance test.
by EPC and Owner before performance test.

4.0 Division of Responsibility


7 - Table 5 Division of Responsibility The Contractor side will be provide personel for taking any sample data, witnessed and supervised by Noted. The same is updated in Table 6. Division of Responsibility.
PLN during the test.

5.1 Boiler Efficiency Calculation... - Noted. Please note that losses such as "heat loss due to formation of CO" & "heat loss due to sensible heat of
- Item of losses have explained in contract (Chapter 12 / schedule 7.2.2 - Technical data). Please add the losses item and delete ash" are negligble and hence not considered. The same can be included if required. Also note that sorbents are
unnecessary losses refer to the Contract not applicable in this project. Hence, heat loss due to calcination and desulfurization are not applicable.

8 - Noted. All necessary losses items are considered.


- Please Describe for any detail losses and credit formula that will be used in this procedure.

- Refer to ASME PTC 4, the symbol for Losses, Heat Credit and Heat input is QpL, Qro and QrF - The symbol for losses and credit is as per the boiler performance test procedure to avoid ambiguity in the
respectively . Please revise this items include each losses symbol. calculation. It is not manadatory to use the same symbol as PTC 4.
PLTU LONTAR EXTENTION
REVIEW OF TEST PROCEDURE DOCUMENTS
Transmittal No : CONS-PLN-6064 Submittal Date : 28 July, 2020
DOCUMENT NUMBER DOCUMENT TITLE
PLN REV CONTRACTOR REV STATUS
Bonafide Test Procedure for Boiler Maximum Continuous Rating
1 0 C
No. PUSERTIF<>LMK<>PLN COMMENTS Contractor Response
(Appendix J
- Please attach clear and approved heat balance for BMCR. - Noted. Latest Heat balance for BMCR are attached in this procedure. Refer Appendix H.
Appendix F. Sample Performance test witness sign off form.....
- Please revise manual data recording sheet as actual required parameter. - This is a sample data recording sheet for those data/measurements which cannot be recorded from DCS or
9
DAS and requires manual/handwritten entries. This sample data recording sheet will be modified during the
test as per requirement.
- Please add two column for sign PLN , PLN Pusertif and PIN upp I - Noted.