You are on page 1of 141

SAUDI ARAMCO

THERMAX LIMITED WELDING PROCEDURE SPECIFICATIONS


BOILER & HEATER GROUP

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P01
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER DRUMS DATE : 28-05-2011
PAGE : 1

1.0 JOB SPECIFIC DATA : -

CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

CONSULTANT : - PROJECT NO:

INSP. AGENCY: DESIGN CODE :

2.0 QUALITY STAGES & INSPECTION :

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
CHARACTERISTICS METHOD EXTENT TL CLI

1 MATERIAL IDENTIFICATION H H

Review & Verification of Material Test Certs. & Drawing Review 100% Drawing, ASME Sec-II

Correlation of MTC with Material Visual 100% Mill Test


Certificate

Dimensional Inspection Measurement 5% Drawing/ Mill Test


Certificate

Identification-Boiler/Heat/Plate/ Part/Shell No.& Mat.Specs. Visual 100% Identification


Punching

IA Stamp Transfer Verify 100% Stamp Transfer

Verify UT Testing for Plate & Nozzle Forgings in MTC Review 100% Material Spec.

HOT ROLLED DRUM:Simulated Heat Treatment & PWHT test coupon Review 1 Sample HT Cycle & Material
/Heat Specs./Code

Identification & Dimensional Inspection of Dished Ends Measurement 100% Drawing

Document review for Dished Ends & Manhole Rims Review 100% Drawing & Code

Identification & Dimensional Inspection of Manhole Rims Measurement 100% Drawing

2 SETUP OF L-SEAMS OF SHELL ALONGWITH TEST COUPON H H

Production Test Coupon with L-Seam Verify One PTC / IBR-1950


Heat/Drum

Intermediate SR (if D/T<20 for CS & <18 for AS) Review of 100% IBR-1950/HT
HT chart Procedure

Ovality, (Inside dia. Min & Max.) Measurement 100% 1% of Nominal ID or


5mm max.

*INSP.BY -THERMAX LI IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
THERMAX LIMITED WELDING PROCEDURE SPECIFICATIONS
BOILER & HEATER GROUP

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P01
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER DRUMS DATE : 28-05-2011
PAGE : 2

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

Shell length, Outside circumference Measurement 100% Drawing

Profile D/4 100% Drawing, IBR 1950


Template

Weld Preparation Template 100% Drawing

Offset / Mismatch Measurement 100% 10%of Nominal plate


thickness or 3mm max

Flaw detection on weld edges PT/MT 100% Free from


Lamination, Crack &
Liner Indications

Tack Weld Soundness PT 100% Procedure PT(Refer


Note No.3)

Shell identification/IA Stamp Visual 100% Drawing, IA Stamp

3 L-SEAM WELDING H R

Backgauging after 1st side welding PT/MT 100% Procedure PT/MT

Inspection after both side welding Visual 100% Procedure VT

Weld reinforcement - Flush ground from Outside Visual 100% IBR-1950

Inspection after Re-rolling of shell:

Profile D/4 100% Within 0.3% of ID


Tempelate

Ovality Measurement 100% 1%of ID or 5mm Max.

Welder/Welding Operator ID Visual 100% Qualified welder


list/IBR Certificate

Weld soundness RT & MT 100% Procedure RT, MT

NDE for CS Drum thk. >&= 100 mm & AS Drum thk. >&=50mm UT 100% Procedure UT

4 PWHT & TESTING OF PTC H H

Heat-Treatment Cycle Review 100% IBR-1950

Heat-Treatment Compliance to Code Review of 100% IBR-1950

*INSP.BY -THERMAX LI IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
THERMAX LIMITED WELDING PROCEDURE SPECIFICATIONS
BOILER & HEATER GROUP

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P01
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER DRUMS DATE : 28-05-2011
PAGE : 3

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

HT chart

Mech. Properties of PTC Mechanical One PTC / Material


Testing Heat /Dru Specifications

5 C-SEAM SETUP H H

Orientation Visual 100% Drawing

Total length Measurement 100% Drawing

Alignment of shell courses Visual & 100% 1mm/mtr, 5mm max.


Measureme

Weld preparation Template 100% Drawing

Alignment / Root offset. Measurement 100% 10% of Nominal plate


thickness + 1mm or
4mm max.

Flaw detection on weld edges. PT/MT 100% Free from


Lamination, Crack &
Liner Indications

Tack Weld Soundness PT 100% Procedure PT(Refer


Note No.3)

IF WELD PROCESS & HT IS DIFFERENT THAN L-SEAM WELDING :

Production Test Coupon with C-seam Verify One PTC / IBR-1950


Heat/Drum

6 C-SEAM WELDING H R

Backgauging after 1st side welding PT/MT 100% Procedure PT/MT

Inspection after both side welding Visual 100% Procedure VT

Weld reinforcement -Flush ground from outside Visual 100% IBR-1950

Welder/Welding Operator ID Verify 100% Qualified welder


list / IBR Certifica
te

Weld soundness RT & MT 100% Procedure RT, MT

*INSP.BY /TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
THERMAX LIMITED WELDING PROCEDURE SPECIFICATIONS
BOILER & HEATER GROUP

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P01
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER DRUMS DATE : 28-05-2011
PAGE : 4

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

NDE for CS Drum thk. >&= 100 mm & AS Drum thk. >&=50mm UT 100% Procedure UT

7 BUTT WELD SETUPS FOR NOZZLES/STUBS H H

Alignment Measurement 10% Drawing

Orientation Visual 100% Drawing

Setup Dimensions Measurement 10% Drawing

Tackweld Soundness by PT PT 100% Procedure PT(Refer


Note No.3)

8 WELDING OF BUTT WELDS OF NOZZLES/STUBS H R

Weld Soundness RT 100% Procedure RT

9 NOZZLES,STUBS,MH RIM & OTHER OPENINGS ON SHELL/D'END H -

MARKING ON SHELL :

Four Quadrant distribution & Punching Combination 100% Within 2 mm


set, W.L

Drum Centreline punching Measurement 100% Equidistant within 1


mm

-No. & size of holes Count & 100% Drawing


Visual

-Distance from reference, Tangential Distance Measurement 100% Drawing

-Orientation Visual 100% Drawing

MARKING ON D'END :

-Four Quadrant distribution & Punching Measurement 100% Within 2 mm

- No. & size of holes Count & 100% Drawing


Visual

- Distance from reference, Tangential Distance Measurement 100% Drawing

- Orientation Visual 100% Drawing

*INSP.BY -THERMAX LI IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
THERMAX LIMITED WELDING PROCEDURE SPECIFICATIONS
BOILER & HEATER GROUP

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P01
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER DRUMS DATE : 28-05-2011
PAGE : 5

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

10 INSPECTION OF OPENINGS H -

1) Opening on shell

Number of holes count 100% Drawing

Distance from reference Measurement 100% Drawing

Orientation Visual 100% Drawing

Size of holes Measurement 100% Drawing

Visual Inspection Visual 100% No surface


defects(Refer Note N
o.3)

- Nozzle Openings >&=10NPS PT/MT 100% Procedure PT/MT

2) Opening on D'end

Number of holes Count 100% Drawing

Distance from reference Measurement 100% Drawing

Orientation. Visual 100% Drawing

Size of holes Measurement 100% Drawing

Visual Inspection Visual 100% No surface


defects(Refer Note N
o.3)

Flaw detection on M/H Opening PT/MT 100% Procedure PT/MT

11 SETUP OF NOZZLES,STUBS,MH RIM & OTHER BRANCH CONNECTIONS ON SHELL/D'END H H

SETUP OF MH RIM WITH D'END

-Projection from shell Measurement 100% Drawing

-Alignment & Squareness. Measurement 100% Within 1 Degree/ 3mm


max.

-Weld preparation. Template 100% Drawing

-Tackweld soundness. PT 100% Procedure PT(Refer

*INSP.BY -THERMAX LI IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
THERMAX LIMITED WELDING PROCEDURE SPECIFICATIONS
BOILER & HEATER GROUP

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P01
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER DRUMS DATE : 28-05-2011
PAGE : 6

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

Note No.3)

SETUP OF NOZZLES WITH D'END

- Identification & Orientation. Visual 100% Drawing

- Alignment & Squareness. Measurement 100% Within 1 Degree/ 3mm


max.

- CTC distance/Projection Measurement 100% Drawing

- Weld preparation Template 100% Drawing

- Tackweld soundness PT 100% Procedure PT(Refer


Note No.3)

SETUP OF NOZZLES WITH SHELL:

-Identification & Orientaion Visual 100% Drawing

-Alignment & Squareness Measurement 100% Within 1 Degree/ 3mm


max.

-CTC distance/Projection Measurement 100% Drawing

-Weld preparation Template 100% Drawing

-Tackweld soundness PT 100% Procedure PT(Refer


Note No.3)

12 WELDING OF NOZZLES,STUBS,MH RIM & OTHER BRANCH CONNECTIONS ON SHELL/D'END H R

I) WELDING OF MANHOLE RIM WITH D'END

-Backgauging after 1st side welding PT 100% Procedure PT

-Weld visual Inspection Visual 100% Procedure VT(Refer


Note No.3)

-Weld size Measurement 100% Drawing

-Weld soundness UT & MT 100% Procedure UT, MT

-Welder ID. Verify 100% Qualified welder


list

*INSP.BY -THERMAX LI IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
THERMAX LIMITED WELDING PROCEDURE SPECIFICATIONS
BOILER & HEATER GROUP

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P01
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER DRUMS DATE : 28-05-2011
PAGE : 7

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

II) WELDING OF NOZZLES WITH D'END

- Weld visual inspection Visual 100% Procedure VT(Refer


Note No.3)

- Weld size Measurement 100% Drawing

- Welder ID. Verify 100% Qualified welder


list

- MT of all Nozzle Welds MT 100% Procedure MT

Full penetration welds >=10 NPS or above 25 thk UT/RT 100% Procedure UT/RT

Full penetration set through nozzle welds UT/RT 100% Procedure UT/RT

III) WELDING OF NOZZLES WITH SHELL:

-Weld Visual inspection Visual 100% Procedure VT(Refer


Note No.3)

-Weld Size Measurement 100% Drawing

-Welder ID Verify 100% Qualified welder


list

-Full penetration Nozzle welds>=10NPS & Safety valve nozzle UT/RT 100% Procedure UT/RT

& Full penetration Nozzle welds> 25mm thick UT/RT 100% Procedure UT/RT

-Full penetration set through nozzle welds UT/RT 100% Procedure UT

-MT of All Nozzle welds MT 100% Procedure MT

13 IDENTIFICATION AND DIMENSIONS OF MANHOLE COVER PLATE & PLACING INSIDE THE DRUM H R

Identification Visual 100% Drawing

Dimensions Measurement 100% Drawing

14 SETUP OF DISHED END TO SHELL H H

Orientation & Alignment of shells Visual & 100% Drawing


Measureme

Weld preparation Template 100% Drawing

*INSP.BY -THERMAX LI IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
THERMAX LIMITED WELDING PROCEDURE SPECIFICATIONS
BOILER & HEATER GROUP

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P01
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER DRUMS DATE : 28-05-2011
PAGE : 8

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

Alignment / Root offset Measurement 100% 10% of Nominal plate


thickness + 1mm or
4mm max.

Flaw detection on weld edges PT/MT 100% Free from


Lamination, Crack &
Liner Indications

Tack Weld Soundness PT 100% Procedure PT(Refer


Note No.3)

Performance Qualification for Welding Operator Verify 100% Qualified welder


list

15 WELDING OF DISHED END TO SHELL H R

Backgauging after 1st side welding PT/MT 100% Procedure PT/MT

Inspection after both side welding Visual 100% Procedure VT

Weld reinforcement- Flush ground from outside Measurement 100% Drawing, IBR-1950

Welding Operator ID Visual 100% Qualified welder


list

Weld soundness RT & MT 100% Procedure RT, MT

NDE for CS Drum thk. >&= 100 mm & AS Drum thk. >&=50mm UT 100% Procedure UT

16 CLEARANCE FOR PWHT H H

Compliance of all Welding,including Ext./Inetrnal attachment Verify 100% Drawing

Overall Major Dimensions Measurement 100% Drawing

NDE Clearance Verify 100% NDT Reports

Nozzle Butt Welds RT 100% Procedure RT

Lifting Lug UT 100% Procedure UT

**NDE of all accessible Pressure Retaining Welds MT 100% Procedure MT

**If not covered earlier

*INSP.BY -THERMAX LI IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
THERMAX LIMITED WELDING PROCEDURE SPECIFICATIONS
BOILER & HEATER GROUP

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P01
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER DRUMS DATE : 28-05-2011
PAGE : 9

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

All attachment Welds MT/PT 100% Procedure MT/PT

Removal of all temporory attachment Welds MT/PT 100% Procedure MT/PT

Traceability of weld joints Review 100% Completed weldmap

17 PWHT H R

Heat-Treatment Cycle Review 100% Heat Treatment


Procedure

Heat-Treatment Compliance to Code Review of 100% Heat Treatment


HT chart Procedure

18 INSPECTION & NDE AFTER PWHT H R

Major Dimensions Measurement 100% Drawing

Flange facing Visual 100% Drawing

LSeam, CSeam, Nozzle Welds PT/MT 10% Procedure PT/MT

All T-joints PT/MT 100% Procedure PT/MT

MT of MH rim to D'end welds, accessible area MT 100% Procedure MT

Safety valve nozzle welds MT 100% Procedure MT

Nozzle Welds >=10NPS or above 25thk MT 100% Procedure MT

NDE for CS Plate thk >&= 100mm & AS Plate thk. >&=50mm **

**UT/RT of Shell seams (L & C Seams) UT/RT 100% Procedure UT/RT

**All accesible pressure retaining welds(LS,CS,Nozzle Welds) PT/MT 100% Procedure PT/MT

19 HYDROSTATIC TEST H H

Hydro Test Verify 100% Drawing, Hydrostatic


test Procedure

Recording Deformation : Measurement Every Shell No Permenant


Deformation

Outside Circumference at 0 Kg/SqCm

*INSP.BY -THERMAX LI IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
THERMAX LIMITED WELDING PROCEDURE SPECIFICATIONS
BOILER & HEATER GROUP

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P01
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER DRUMS DATE : 28-05-2011
PAGE : 10

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

Outside Circumference at MAWP

Outside Circumference at HTP

Outside Circumference at 0 Kg/SqCm

Pressure test result Record 100% Satisfactory

IA Stamp/Code punching on satisfactory Pressure test Visual / 100% IBR-1950, Legible


Rub-off Stamping & Rub-off

20 DRAINING & DRYING AFTER HYDRO TEST H -

Draining, Drying & Cleaning Visual 100% Inside surface shall


be Dry & Clean

21 MARKING FOR DRILLING H -

Distance from reference Measurement 100% Drawing

Orientation of rows Measurement 100% Drawing

No.of rows count 100% Drawing

No.of Openings/Holes per row Count 100% Drawing

Pitch Measurement 100% Drawing

Hole size Visual 100% Drawing

22 DRILLING INSPECTION H -

Orientation of rows Visual 100% Drawing

No.of rows count 100% Drawing

No.of Holes per row Count 100% Drawing

Distances from refernce lines Measurement 100% Drawing

Linear Ligament (minimum) Measurement 100% Drawing

Circumferencial Ligament (minimum) Measurement 100% Drawing

Hole Diameter Plug gauge 100% Drawing

*INSP.BY -THERMAX LI IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
THERMAX LIMITED WELDING PROCEDURE SPECIFICATIONS
BOILER & HEATER GROUP

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P01
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER DRUMS DATE : 28-05-2011
PAGE : 11

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

Groove dimensions Measurement 100% Drawing

Surface Finish of Drilled Holes Visual 10% 125 to 250 RMS

Quadrant Line Punching for Reference Measurement 100% Drawing

NDE on Holes coming on shell welds ** PT/MT 100% Procedure PT/MT

** Note :Both side flush grinding to be done before NDT

23 FINAL INSPECTION H H

Fitment of Drum Internals Verify 100% Drawing

Attachments of all non pr.parts internal/exteral Visual 100% Drawing

Compliance to Drg for Scope Verify 100% Drawing BOM

Traceability of weld joints Review 100% Completed Weldmap

Centreline punching Visual 100% Drawing

Code Compliance Certificati 100% Compillation of


on / Docum stage IR's & MTC's,
Code

24 PAINTING INSPECTION H -

Surface Preparation Visual 100% Drawing, Painting


Specs.

Paint Shade, Make, Batch No. Visual 100% Drawing, Painting


Specs.

Visual Inspection after painting Visual 100% Complete coverage of


area, No rundowns,
Peel-offs, Cracks

Paint-Dry Film Thickness (DFT) Measurement Random Drawing, Painting


Specs.

Application of rust prevention oil on inside surface Visual 100% Drawing/Specs.

Capping / Blanking of all Openings Visual 100% All Openings Shall


be Covered /Capped

*INSP.BY -THERMAX LI IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
THERMAX LIMITED WELDING PROCEDURE SPECIFICATIONS
BOILER & HEATER GROUP

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P01
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER DRUMS DATE : 28-05-2011
PAGE : 12

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

Identification Visual 100% Drawing

Marking of C/L punching Visual 100% All drum centreline


marked

25 INSPECTION RELEASE NOTE H -

Final Document Review Review 100% Drawing, Compilation


of document

Inspection Release Note Issuance of


IRN

3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.

1. WPS,PQR,WPQ and Welding Technology sheet(WTS)


2. Material Test Certificates
3. Manufacturing Records
4. All the required Inspection Records.

Following Documents shall be referred for this QAP (As Applicable) :

1) NDE Procedures

+---+-----------+-------------------------------------------+
|Sr.|Control No.|Procedure Description |
+---+-----------+-------------------------------------------+
|1) |RT12 |Radiographic Examination of Welded Joints |
+---+-----------+-------------------------------------------+
|2) |PT1 |Liquid Penetrant Examination |
+---+-----------+-------------------------------------------+
|3) |MT3 |Magnetic Particle Examination |
+---+-----------+-------------------------------------------+
|4) |UT2 |Ultrasonic Examination Of Butt Welds |
+---+-----------+-------------------------------------------+
|5) |UT4 |Straight Beam Ultrasonic Examination of |
| | |Rolled Steel Plates |
+---+-----------+-------------------------------------------+

2) RECORD NOT REQUIRED TO GENERATE FOR VISUAL INSPECTION AND


TACK WELD SOUNDNESS AS MENTIONED IN THIS ITP.

*INSP.BY -THERMAX LI IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
THERMAX LIMITED WELDING PROCEDURE SPECIFICATIONS
BOILER & HEATER GROUP

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P01
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER DRUMS DATE : 28-05-2011
PAGE : 13

4.0 INSPECTION POINTS


INSPECTION POINTS ARE INDICATED BY :

R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production
cycle marked by the AI/Customer/TPI. Record of inspection is maintained
and will be made available to AI/Customer/TPI for review during next
HOLD/WITNESS stage Inspection,as applicable.

W Witness Point WITNESS POINT is defined as a notification operation in operation / production


cycle marked by the AI/Customer/TPI to excercise their option to witness
and verify a specific operation. Further processing shall proceed where the
AI/Customer/TPI do not validate their option. The notification shall be
documented in a manner acceptable to AI/Customer/TPI, as applicable.

H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.

- - Inspection option will not be exercised

5.0 RECORD OF REVISIONS :

REV NO. DATE CHANGES

PREPARED BY CHECKED BY APPROVED BY ACCEPTED BY CLIENT/CONSULTANT/TPI

*INSP.BY TL -THERMAX LI IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN)


SAUDI ARAMCO
THERMAX LIMITED WELDING PROCEDURE SPECIFICATIONS
BOILER & HEATER GROUP

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P02
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
DISHED ENDS FOR BOILER DRUM DATE : 15-09-2011
PAGE : 1

1.0 JOB SPECIFIC DATA : -

CUSTOMER :

CONSULTANT : - PROJECT NO:

INSP. AGENCY: DESIGN CODE :

2.0 QUALITY STAGES & INSPECTION :

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
CHARACTERISTICS METHOD EXTENT TL CLI

1 MATERIAL IDENTIFICATION H H

Material Test Certificates Review 100% Drawing, ASME Sec-II

Correlation of MTC with Material Visual 100% Mill Test


Certificate

Dimensional Inspection Measurement 5% Drawing/Mill Test


Certificate

Identification & Stamp Transfer Visual 100% Identification


Punching & Stamp Tra
nsfer

UT of Plates UT 100% ASTM A578 Level B

2 INSPECTION OF DISHED ENDS AFTER FORMING H R

Surface Finish Visual 100% Spinning/Die Marks


to be ground smooth

Inspection of template on layout Measurement 100% Proper matching

Inside Circumference Measurement 100% Drawing

Inside Circumference-For a Pair of Dished End Measurement 100% Within +/- 5mm

Ovality Measurement 100% 1% of ID or 5mm max.

Thinning Measurement 5Spots Min. Drawing, IBR-1950

Profile-Increase in Depth, Decrease in Depth Template 100% Drawing, IBR-1950

Height Measurement 100% Drawing

Knuckle Radius Template 100% Decrease not


Permissible

*INSP.BY -THERMAX LI IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
THERMAX LIMITED WELDING PROCEDURE SPECIFICATIONS
BOILER & HEATER GROUP

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P02
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
DISHED ENDS FOR BOILER DRUM DATE : 15-09-2011
PAGE : 2

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

Straight Face(Lesser of Inside & Outside readings) Measurement 100% Drawing

PT from Inside,Outside on Knuckle Portion & On Edge PT 100% Procedure PT

Heat-Treatment (As Applicable) Review of 100% Drawing, IBR-1950


HT chart

Lamination Check UT 100% No Laminations


/Procedure UT

Identification & Stamping on D/E Visual 100% Legible

3 INSPECTION RELEASE NOTE H -

Final Document Review Review 100% Drawing, Compilation


of document

Inspection Release Note Issuance of 100%


IRN

3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.

1. WPS,PQR,WPQ and Welding Technology sheet(WTS)


2. Material Test Certificates
3. Manufacturing Records
4. All the required Inspection Records.

Following Documents shall be referred for this QAP (As Applicable) :

1) NDE Procedures

+---+-----------+-------------------------------------------+
|Sr.|Control No.|Procedure Description |
+---+-----------+-------------------------------------------+
|1) |RT12 |Radiographic Examination of Welded Joints |
+---+-----------+-------------------------------------------+
|2) |PT1 |Liquid Penetrant Examination |
+---+-----------+-------------------------------------------+
|3) |MT3 |Magnetic Particle Examination |
+---+-----------+-------------------------------------------+
|4) |UT2 |Ultrasonic Examination Of Butt Welds |

*INSP.BY TL -THERMAX LI IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
THERMAX LIMITED WELDING PROCEDURE SPECIFICATIONS
BOILER & HEATER GROUP

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P02
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
DISHED ENDS FOR BOILER DRUM DATE : 15-09-2011
PAGE : 3

+---+-----------+-------------------------------------------+
|5) |UT4 |Straight Beam Ultrasonic Examination of |
| | |Rolled Steel Plates |
SAUDI ARAMCO

+---+-----------+-------------------------------------------+ WELDING PROCEDURE SPECIFICATIONS

2) RECORD NOT REQUIRED TO GENERATE FOR VISUAL INSPECTION AND


TACK WELD SOUNDNESS AS MENTIONED IN THIS ITP.

4.0 INSPECTION POINTS


INSPECTION POINTS ARE INDICATED BY :

R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production
cycle marked by the AI/Customer/TPI. Record of inspection is maintained
and will be made available to AI/Customer/TPI for review during next
HOLD/WITNESS stage Inspection,as applicable.

W Witness Point WITNESS POINT is defined as a notification operation in operation / production


cycle marked by the AI/Customer/TPI to excercise their option to witness
and verify a specific operation. Further processing shall proceed where the
AI/Customer/TPI do not validate their option. The notification shall be
documented in a manner acceptable to AI/Customer/TPI, as applicable.

H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.

- - Inspection option will not be exercised

5.0 RECORD OF REVISIONS :

REV NO. DATE CHANGES

PREPARED BY CHECKED BY APPROVED BY ACCEPTED BY CLIENT/CONSULTANT/TPI

*INSP.BY TL -THERMAX LI IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN)


SAUDI ARAMCO
THERMAX LIMITED WELDING PROCEDURE SPECIFICATIONS
BOILER & HEATER GROUP

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P03
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
MEMBRANE PANELS DATE : 15-09-2011
PAGE : 1

1.0 JOB SPECIFIC DATA : -

CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

CONSULTANT : - PROJECT NO:

INSP. AGENCY: DESIGN CODE :

2.0 QUALITY STAGES & INSPECTION :

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
CHARACTERISTICS METHOD EXTENT TL CLI

1 MATERIAL IDENTIFICATION H H

Material Test Certificates Review 100% Drawing, Material


Spec.

Correlation of MTC with Material Visual 100% Mill Test


Certificate

Dimensional Inspection Measurement 5% Drawing/Mill Test


Certificate

Identification Visual 100% Punching/Stencilling

2 PREPRODUCTION SAMPLE OF SWAGED TUBE ENDS H R

Surface Defects PT 100% Procedure PT

Normalising of swage tube ends Review of 100% HT Procedure /


HT Chart IBR-1950

Dimensional Insp - Ovality, Thickness, Concentricity, Length Measurement 100% Drawing

Hardness after Normalising Measurement 100% Drawing / Specs.

Physical Testing :(Flattening-1, Flaring-1) Mech. 1Set of IBR-1950


Testing Test/Heat

3 INSPECTION OF SWAGED TUBE ENDS H -

Inspection after Swaging Visual 2% Drawing

Surface Defects PT 2% Procedure PT

Dimensional Insp -Ovality, Thickness, Concentricity, Length Measurement 2% Drawing

Hardness after Normalising Measurement 5% Drawing / Specs.

*INSP.BY TL -THERMAX IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P03
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
MEMBRANE PANELS DATE : 15-09-2011
PAGE : 2

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

4 HEAT-TREATMENT OF SWAGED TUBE ENDS H R

Heat-Treatment Cycle Review 100% HT Procedure /


IBR-1950

Heat-Treatment Compliance to Code Review of 100% HT Procedure /


HT Chart IBR-1950

5 WELDING OF MEMBRANE STRIP TO TUBE H -

Cleaning of Tubes Shot 100% Free from Mill Scale


Blasting & Clean from Inside

Pitches of Tubes Measurement 1st Panel Drawing


Segment

Weld Inspection Visual & 100% Drawing


Measureme

6 INSPECTION OF PANEL AFTER PACK BENDING H -

Inspection for Layout On layout *1Segment / Within 3mm


Boiler

*Most Restricted Bend of Total Panels

Ovality on Outer Tubes Measurement 2% Within 10%

Thinning on Outer Tubes Measurement 2% Drawing/


100/(4R/D+2) max.

Flow Area O.D less than 3" * Ball Test 100% Ball Size= {(0.9
OD-2.3SWT)-1.6mm}

*Note:Not applicable for Single & Both end swaging

7 SETUP OF BUTT JOINTS H H

Panel tube,Spools,Opening tubes & Loose tube joints

Orientation Visual 100% Drawing

Setup Dimensions Measurement 10% Drawing

Alignment Measurement 10% Drawing

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P03
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
MEMBRANE PANELS DATE : 15-09-2011
PAGE : 3

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

8 WELDING OF BUTT WELD JOINTS H R

Visual Inspection Visual 100% Procedure VT

Panel Tube Butt Welds for Length Built-up RT 5% per Procedure RT


welder

Spool Butt Welds RT 5% per Procedure RT


welder

Opening Tubes Butt Welds RT 5% per Procedure RT


welder

Loose Tubes Butt Welds RT 5% per Procedure RT


welder

9 SAMPLE/FIRST PRODUCTION BEND FOR PANEL OPENING/LOOSE TUBES H R

Identification Visual 100% Drawing

Dimensions on Layout Layout 100% Within 3mm


Matching

Ovality Measurement 100% 10% Max.

Minimum Thickness Measurement 100% Drawing/


100/(4R/D+2) max.

Flow Area for Tubes O.D less than 3" Ball Test 100% Ball Size(Cold Bend)
={(0.9 OD-2.3SWT)-
1.6mm}

Bore Inspection Visual 100% No Score Marks, if


Mandrel is used

10 INSPECTION OF PANEL OPENING/LOOSE TUBES AFTER BENDING H R

Orientation Visual 100% Drawing

Dimensions on Layout Layout 5% Within 3mm


Matching

Flow Area for Tubes O.D less than 3" Ball Test 100% Ball Size(Cold Bend)
={(0.9 OD-2.3SWT)-
1.6mm}

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P03
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
MEMBRANE PANELS DATE : 15-09-2011
PAGE : 4

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

11 FINAL INSPECTION OF LOOSE TUBES H H

Identification Marking Visual 5% Drawing

Site Weld Preperation (If Applicable) Visual 5% Drawing

End Identification Visual 5% Drawing

Document Review Review 100% Compillation of


stage IR's & MTC's,
Code

12 SETUP OF PANEL TUBES TO HEADER/S H H

Cleaning of Tubes from inside Air blowing 100% Free from foreign
material

Cleaning of header from inside Air blowing 100% Free from foreign
material

Orientation Visual 100% Drawing

Setup Inspection Measurement 100% Drawing

Alignment & Squareness Measurement 10% Drawing

13 WELDING OF PANEL TUBES TO HEADER/S H -

Squareness of Header with Panel Measurement 100% Drawing

Straightness of Header Measurement 100% 1mm/mtr or 5mm max.

Weld Inspection Visual & 100% Drawing & Procedure


Measureme

NDE after full welding PT/MT 10% Procedure PT/MT

14 STRUCTURALS & ATTACHMENTS H -

Identification & Orientaion Visual 100% Drawing

Dimensional Inspection Measurement 100% Drawing

Alignment & Squareness Measurement 100% Drawing

Inspection of Strip cutout with Template/ Gauge as appl. Verify 100% Drawing

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P03
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
MEMBRANE PANELS DATE : 15-09-2011
PAGE : 5

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

Weld Inspection Visual 100% Drawing

Stud Welding on Tubes Stud Layout 100% Drawing

Stud Weld Soundness Torque Test 10 Studs 2 Breakage in 10


min. Studs for 30ftlb Tor
que is Acceptable

15 MOCK UP OF PANEL WITH RESPECTIVE HEADER-FOR SITE ASSEMBLED HEADER ONLY

Orientation Visual 100% Drawing

Alignment & overall major Dimensions Measurement 100% Drawing

Identification Punching / Marking of Header Verify 100% Drawing

16 CLEARANCE FOR PWHT OF PANEL TO HEADER JOINTS H -

Overall Dimensions Measurement 100% Drawing

Distortion / Flatness Visual 100% Drawing

Weld Inspection (Size & Finish) Measurement 100% Drawing


& Visual

NDE Clearance Review of 100% NDE Procedures


NDE Repor

Completion of all Welding Visual 100% Drawing

Identification Punching Rub-off 100% Drawing

17 PWHT OF PANEL TO HEADER JOINTS H R

Heat-Treatment Cycle Review 100% HT Procedure /


IBR-1950

Heat-Treatment Compliance to Code Review of 100% HT Procedure /


HT Chart IBR-1950

18 FINAL INSPECTION H H

Compliance to Drawing for Scope Review 100% Drawing-BOM

Major Dimensions Measurement Critical Drawing

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P03
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
MEMBRANE PANELS DATE : 15-09-2011
PAGE : 6

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

Dimension

IA Stamp & Final Rub off Visual 100% IBR-1950, Legibility


of Stamp & Rub off

19 PAINTING INSPECTION H -

Surface Preparation Visual 100% Drawing, Painting


Specs.

Paint Shade, Make, Batch No. Visual 100% Drawing, Painting


Specs.

Visual Inspection after painting Visual 100% Complete coverage of


area, No rundowns,
Peel-offs, Cracks

Paint-DFT Measurement Random Drawing, Painting


Specs.

Cleaning of headers from inside Air blowing 100% Free from foreign
material

Capping / Blanking of all Openings Visual 100% All Openings Shall


be Covered /Capped

Identification Marking Visual 100% Drawing

20 INSPECTION RELEASE NOTE H -

Final Document Review Review 100% Drawing, Compilation


of document

Inspection Release Note Issuance of


IRN

3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.

1. WPS,PQR,WPQ and Welding Technology sheet(WTS)


2. Material Test Certificates
3. Manufacturing Records
4. All the required Inspection Records.

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P03
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
MEMBRANE PANELS DATE : 15-09-2011
PAGE : 7

Following Documents shall be referred for this QAP (As Applicable) :


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

1) NDE Procedures

+---+-----------+-------------------------------------------+
|Sr.|Control No.|Procedure Description |
+---+-----------+-------------------------------------------+
|1) |RT12 |Radiographic Examination of Welded Joints |
+---+-----------+-------------------------------------------+
|2) |PT1 |Liquid Penetrant Examination |
+---+-----------+-------------------------------------------+
|3) |MT3 |Magnetic Particle Examination |
+---+-----------+-------------------------------------------+
|4) |UT2 |Ultrasonic Examination Of Butt Welds |
+---+-----------+-------------------------------------------+
|5) |UT4 |Straight Beam Ultrasonic Examination of |
| | |Rolled Steel Plates |
+---+-----------+-------------------------------------------+

2) RECORD NOT REQUIRED TO GENERATE FOR VISUAL INSPECTION AND


TACK WELD SOUNDNESS AS MENTIONED IN THIS ITP.

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P03
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
MEMBRANE PANELS DATE : 15-09-2011
PAGE : 8

4.0 INSPECTION POINTS


INSPECTION POINTS ARE INDICATED BY :

SAUDI ARAMCO

R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS

cycle marked by the AI/Customer/TPI. Record of inspection is maintained


and will be made available to AI/Customer/TPI for review during next
HOLD/WITNESS stage Inspection,as applicable.

W Witness Point WITNESS POINT is defined as a notification operation in operation / production


cycle marked by the AI/Customer/TPI to excercise their option to witness
and verify a specific operation. Further processing shall proceed where the
AI/Customer/TPI do not validate their option. The notification shall be
documented in a manner acceptable to AI/Customer/TPI, as applicable.

H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.

- - Inspection option will not be exercised

5.0 RECORD OF REVISIONS :

REV NO. DATE CHANGES

PREPARED BY CHECKED BY APPROVED BY ACCEPTED BY CLIENT/CONSULTANT/TPI

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN)


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P04
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER SIDE/BAFFLE/FURNACE SIDE/REAR WALL (FM) DATE : 11-06-2011
PAGE : 1

1.0 JOB SPECIFIC DATA : -

CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

CONSULTANT : - PROJECT NO:

INSP. AGENCY: DESIGN CODE :

2.0 QUALITY STAGES & INSPECTION :

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
CHARACTERISTICS METHOD EXTENT TL CLI

1 MATERIAL IDENTIFICATION H H

Material Test Certificates Review 100% Drawing, Material


Spec.

Correlation of MTC with Material Visual 100% Mill Test


Certificate

Dimensional Inspection Measurement 5% Drawing/Mill Test


Certificate

Identification Visual 100% Punching/Stencilling

2 PREPRODUCTION SAMPLE OF SWAGED TUBE ENDS H R

Surface Defects PT 100% Procedure PT

Normalising of swage tube ends Review of 100% HT Procedure /


HT Chart IBR-1950

Dimensional Insp - Ovality, Thickness, Concentricity, Length Measurement 100% Drawing

Hardness after Normalising Measurement 100% Drawing / Specs.

Physical Testing :(Flattening-1, Flaring-1) Mech. 1Set of IBR-1950


Testing Test/Heat

3 INSPECTION OF SWAGED TUBE ENDS H -

Inspection after Swaging Visual 2% Drawing

Surface Defects PT 2% Procedure PT

Dimensional Insp -Ovality, Thickness, Concentricity, Length Measurement 2% Drawing

Hardness Measurement 2% Drawing / Specs.

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P04
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER SIDE/BAFFLE/FURNACE SIDE/REAR WALL (FM) DATE : 11-06-2011
PAGE : 2

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

4 NORMALISING OF SWAGED TUBE ENDS H R

Heat-Treatment Cycle Review 100% HT Procedure/


IBR-1950

Heat-Treatment Compliance to Code Review of 100% HT Procedure /


HT Chart IBR-1950

Hardness Measurement 5% Drawing / Specs.

5 WELDING OF MEMBRANE STRIP TO TUBE H -

Cleaning of Tubes Shot 100% Free from Mill Scale


Blasting & Clean from Inside

Pitches of Tubes Measurement 1st Panel Drawing


Segment

Weld Inspection Visual & 100% Drawing


Measureme

6 INSPECTION OF PANEL AFTER PACK BENDING H -

Inspection for Layout On layout *1Segment / Within 3mm


Boiler

*Most Restricted Bend of Total Panels

Ovality on Outer Tubes Measurement 2% Within 10%

Thinning on Outer Tubes Measurement 2% 100/(4R/D+2) Max.

Flow Area O.D less than 3" * Ball Test 100% Ball Size= {(0.9
OD-2.3SWT)-1.6mm}

*Note:Not applicable for Single & Both end swaging

7 SETUP OF BUTT JOINTS H H

Panel tube joints, Spool joints & Opening tubes joints

Orientation Visual 100% Drawing

Setup Dimensions Measurement 10% Drawing

Alignment Measurement 10% Drawing

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P04
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER SIDE/BAFFLE/FURNACE SIDE/REAR WALL (FM) DATE : 11-06-2011
PAGE : 3

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

8 NDT SCHEDULE H R

Panel Tube Butt Welds for Length Built-up RT 5% per Procedure RT


welder

Spool Butt Welds RT 5% per Procedure RT


welder

Opening Tubes Butt Welds RT 5% per Procedure RT


welder

9 STRUCTURALS & ATTACHMENTS H -

Identification & Orientaion Visual 100% Drawing

Dimensional Inspection Measurement 100% Drawing

Alignment & Squareness Measurement 100% Drawing

Inspection of Strip cutout with Template/ Gauge as appl. Verify 100% Drawing

Weld Inspection Visual 100% Drawing

Stud Welding on Tubes Stud Layout 100% Drawing

Stud Weld Soundness Torque Test 10 Studs 2 Breakage in 10


min. Studs for 30ftlb Tor
que is Acceptable

10 FINAL INSPECTION H H

Compliance to Drawing for Scope Review 100% Drawing-BOM

Overall Dimensions Measurement Critical Drawing


Dimension

Site Weld Preparation (If Applicable) Template 10% Random Drawing

IA Stamp & Rub Off Visual 100% IBR-1950, Legibility

Document Review Review 100% Compillation of


stage IR's & MTC's,
Code

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P04
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER SIDE/BAFFLE/FURNACE SIDE/REAR WALL (FM) DATE : 11-06-2011
PAGE : 4

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

11 PAINTING INSPECTION H -

Surface Preparation Visual 100% Drg/Painting Specs.

Paint Shade Visual 100% Drawing, Painting


Specs.

Visual Inspection after painting Visual 100% Complete coverage of


area, No rundowns,
Peel-offs, Cracks

Paint-DFT Measurement random Drawing, Painting


Specs.

Cleaning of Tubes from Inside before capping Air blowing 100% Free from foreign
material

Capping / Blanking of all Openings Visual 100% All Openings Shall


be Covered /Capped

Identification Marking Visual 100% Drawing

12 INSPECTION RELEASE NOTE H -

Final Document Review Review 100% Drawing, Compilation


of document

Inspection Release Note Issuance of 100%


IRN

3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.

1. WPS,PQR,WPQ and Welding Technology sheet(WTS)


2. Material Test Certificates
3. Manufacturing Records
4. All the required Inspection Records.

Following Documents shall be referred for this QAP (As Applicable) :

1) NDE Procedures

+---+-----------+-------------------------------------------+

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P04
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER SIDE/BAFFLE/FURNACE SIDE/REAR WALL (FM) DATE : 11-06-2011
PAGE : 5

|Sr.|Control No.|Procedure Description |


+---+-----------+-------------------------------------------+
|1) |RT12 |Radiographic Examination of Welded Joints |
SAUDI ARAMCO

+---+-----------+-------------------------------------------+ WELDING PROCEDURE SPECIFICATIONS

|2) |PT1 |Liquid Penetrant Examination |


+---+-----------+-------------------------------------------+
|3) |MT3 |Magnetic Particle Examination |
+---+-----------+-------------------------------------------+
|4) |UT2 |Ultrasonic Examination Of Butt Welds |
+---+-----------+-------------------------------------------+
|5) |UT4 |Straight Beam Ultrasonic Examination of |
| | |Rolled Steel Plates |
+---+-----------+-------------------------------------------+

2) RECORD NOT REQUIRED TO GENERATE FOR VISUAL INSPECTION AND


TACK WELD SOUNDNESS AS MENTIONED IN THIS ITP.

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P04
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER SIDE/BAFFLE/FURNACE SIDE/REAR WALL (FM) DATE : 11-06-2011
PAGE : 6

4.0 INSPECTION POINTS


INSPECTION POINTS ARE INDICATED BY :

SAUDI ARAMCO

R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS

cycle marked by the AI/Customer/TPI. Record of inspection is maintained


and will be made available to AI/Customer/TPI for review during next
HOLD/WITNESS stage Inspection,as applicable.

W Witness Point WITNESS POINT is defined as a notification operation in operation / production


cycle marked by the AI/Customer/TPI to excercise their option to witness
and verify a specific operation. Further processing shall proceed where the
AI/Customer/TPI do not validate their option. The notification shall be
documented in a manner acceptable to AI/Customer/TPI, as applicable.

H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.

- - Inspection option will not be exercised

5.0 RECORD OF REVISIONS :

REV NO. DATE CHANGES

PREPARED BY CHECKED BY APPROVED BY ACCEPTED BY CLIENT/CONSULTANT/TPI

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN)


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P05
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER TUBES DATE : 28-05-2011
PAGE : 1

1.0 JOB SPECIFIC DATA : -

CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

CONSULTANT : - PROJECT NO:

INSP. AGENCY: DESIGN CODE :

2.0 QUALITY STAGES & INSPECTION :

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
CHARACTERISTICS METHOD EXTENT TL CLI

1 MATERIAL IDENTIFICATION H H

Material Test Certificates Review 100% Drawing, Material


Spec.

Correlation of MTC with Material Visual 100% Mill Test


Certificate

Dimensional Inspection Measurement 5% Drawing/Mill Test


Certificate

Identification Visual 100% Punching/Stencilling

2 PREPRODUCTION SAMPLE OF SWAGED TUBE ENDS H R

Surface Defects PT 100% Procedure PT

Normalising of swage tube ends Review of 100% HT Procedure /


HT Chart IBR-1950

Dimensional Insp - Ovality, Thickness, Concentricity, Length Measurement 100% Drawing

Hardness after Normalising Measurement 100% Matl. Specs.

Physical Testing :(Flattening-1, Flaring-1) Mech. 1Set of IBR-1950/Matl.


Testing Test/Heat Specs.

3 INSPECTION OF SWAGED TUBE ENDS H -

Inspection after Swaging Visual 2% Drawing

Surface Defects PT 2% Procedure PT

Dimensional Insp -Ovality, Thickness, Concentricity, Length Measurement 2% Drawing

Hardness after Normalising Measurement 2% Matl. Specs.

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P05
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER TUBES DATE : 28-05-2011
PAGE : 2

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

4 NORMALISING OF SWAGED TUBE ENDS H R

Heat-Treatment Cycle Review 100% HT Procedure /


IBR-1950

Heat-Treatment Compliance to Code Review of 100% HT Procedure /


HT Chart IBR-1950

5 FLAT STUD WELDING - PREPRODUCTION SAMPLE H -

Dimensions : Tube Size, Stud-Location, Spacing & Width Measurement 5% Drawing


& Visual

Stud Weld Soundness Torque Test 10 Studs 2 Breakage in 10


min. Studs for 30ftlb Tor
que is Acceptable

Concentricity Measurement 5% Drawing/Specs.

Bore Inspection Visual 100% Burnthrough Not


Acceptable

Undercut, Crack Visual 5% Procedure VT

Metal Splash Visual 5% Metal Splash upto


5mm Acceptable

6 FLAT STUD WELDING - INPROCESS INSPECTION H -

Undercut, Crack Visual 5% Procedure VT

Metal Splash Visual 5% Metal Splash 5mm Acc

Stud Weld Soundness Torque Test 10 Studs 2 Breakage in 10


min. Studs for 30ftlb Tor
que is Acceptable

Bore Inspection Visual 100% Burnthrough Not


Acceptable

7 TUBE BENDING-PREPRODUCTION SAMPLE (WITH MAX.DEGREE BEND) H R

Identification Visual 100% Drawing

Dimensions on Layout Layout 100% Within 3mm


Matching

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P05
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER TUBES DATE : 28-05-2011
PAGE : 3

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

Ovality Measurement 100% 10% Max.

Minimum Thickness Measurement 100% Drawing /


100/(4R/D+2) max.

Flow Area for Tubes O.D less than 3" Ball Test 100% Ball Size(Cold Bend)
={(0.9 OD-2.3SWT)-1
.6mm}

Bore Inspection Visual 100% No Score Marks, if


Mandrel is used

Surface defects, Die Marks Visual 100% 0.5 mm deep max.


without sharp notche
s

Cracks, Wrinkles Visual 100% No cracks, wrinkles

8 TUBE BENDING - INPROCESS/FINAL INSPECTION H -

Layout Inspection Measurement 100% Drawing


& Visual

Dimensions on Layout Layout 5% Within 3mm


Matching

Ovality Measurement 5% Within 10%

Thinning Measurement 5% Drawing,


100/(4R/D+2) Max.

Surface defects, Die Marks Visual 100% 0.5 mm deep max


without sharp notche
s

Cracks, Wrinkles Visual 100% No Cracks, Wrinkles

9 SETUP OF BUTT JOINTS (TUBE TO TUBE) H -

Set up dimensions Measurement 10% Drawing

Edge preparation Template 10% Drawing

Orientation Visual 100% Drawing

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P05
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER TUBES DATE : 28-05-2011
PAGE : 4

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

Alignment Measurement 10% Drawing

10 NDT SCHEDULE H R

Butt Welds RT 5% per Procedure RT


welder

11 STRUCTURALS & ATTACHMENTS H -

Identification & Orientaion Visual 100% Drawing

Dimensional Inspection Measurement 100% Drawing

Alignment & Squareness Measurement 100% Drawing

Weld Inspection Visual 100% Drawing

Stud Welding on Tubes Stud Layout 100% Drawing


& Orient

Stud Weld Soundness Torque Test 10 Studs 2 Breakage in 10


min. Studs for 30ftlb Tor
que is Acceptable

Mock up of mating tubes of soot blower attach. with jig rod Verify 100% Drawing.

12 FINAL INSPECTION H H

Identification Marking Visual 5% Drawing

Dimensions on Layout Layout 5% Within 3mm


Matching

Flow Area for Tubes O.D less than 3" Ball Test 100% Ball Size ={(0.9
OD-2.3SWT)-1.6mm}

Site Weld Preperation (If Applicable) Visual 5% Drawing

End Identification Visual 5% Drawing

Document Review Review 100% Drawing, Compilation


of stage IR's/ MTC

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P05
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER TUBES DATE : 28-05-2011
PAGE : 5

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

13 SURFACE PREPARATION H -

Surface Preparation Visual 100% Drawing, Painting


Specs.

14 PAINTING INSPECTION H -

Paint Shade Visual 100% Drawing, Painting


Specs.

Visual Inspection after painting Visual 100% Complete coverage of


area, No rundowns,
Peel-offs, Cracks

Paint-DFT Measurement Random Drawing, Painting


Specs.

Cleaning of tubes from inside before capping Air blowing 100% Free from foreign
material

Capping / Blanking of all Tubes Visual 100% All Tubes Shall be


Covered /Capped

ID Marking (Boiler No./Drawing No./Mark/ Part No.) Visual 100% Drawing

End Identification Visual 100% Drawing

15 INSPECTION RELEASE NOTE H -

Final Document Review Review 100% Drawing, Compilation


of document

Inspection Release Note Issuance of


IRN

3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.

1. WPS,PQR,WPQ and Welding Technology sheet(WTS)


2. Material Test Certificates
3. Manufacturing Records
4. All the required Inspection Records.

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P05
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER TUBES DATE : 28-05-2011
PAGE : 6

Following Documents shall be referred for this QAP (As Applicable) :

1) NDE Procedures
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

+---+-----------+-------------------------------------------+
|Sr.|Control No.|Procedure Description |
+---+-----------+-------------------------------------------+
|1) |RT12 |Radiographic Examination of Welded Joints |
+---+-----------+-------------------------------------------+
|2) |PT1 |Liquid Penetrant Examination |
+---+-----------+-------------------------------------------+
|3) |MT3 |Magnetic Particle Examination |
+---+-----------+-------------------------------------------+
|4) |UT2 |Ultrasonic Examination Of Butt Welds |
+---+-----------+-------------------------------------------+
|5) |UT4 |Straight Beam Ultrasonic Examination of |
| | |Rolled Steel Plates |
+---+-----------+-------------------------------------------+

2) RECORD NOT REQUIRED TO GENERATE FOR VISUAL INSPECTION AND


TACK WELD SOUNDNESS AS MENTIONED IN THIS ITP.

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P05
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER TUBES DATE : 28-05-2011
PAGE : 7

4.0 INSPECTION POINTS


INSPECTION POINTS ARE INDICATED BY :

SAUDI ARAMCO

R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS

cycle marked by the AI/Customer/TPI. Record of inspection is maintained


and will be made available to AI/Customer/TPI for review during next
HOLD/WITNESS stage Inspection,as applicable.

W Witness Point WITNESS POINT is defined as a notification operation in operation / production


cycle marked by the AI/Customer/TPI to excercise their option to witness
and verify a specific operation. Further processing shall proceed where the
AI/Customer/TPI do not validate their option. The notification shall be
documented in a manner acceptable to AI/Customer/TPI, as applicable.

H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.

- - Inspection option will not be exercised

5.0 RECORD OF REVISIONS :

REV NO. DATE CHANGES

PREPARED BY CHECKED BY APPROVED BY ACCEPTED BY CLIENT/CONSULTANT/TPI

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN)


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P09
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
CONVECTION BANK MODULE ASSEMBLY DATE : 04-11-2011
PAGE : 1

1.0 JOB SPECIFIC DATA : -

CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

CONSULTANT : - PROJECT NO:

INSP. AGENCY: DESIGN CODE :

2.0 QUALITY STAGES & INSPECTION :

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
CHARACTERISTICS METHOD EXTENT TL CLI

1 GROUND INSPECTION OF PRESSURE PARTS H H

Identification of Tubes & Headers Visual 100% Drg

2 MATERIAL IDENTIFICATION H H

Review & Verification of Test Certificates & Drawing Review 100% Drawing, Material
Spec.

Correlation of MTC with Material Visual 100% Mill Test


Certificate

Dimensional Inspection Measurement 5% Drawing/Mill Test


Certificate

Identification Visual 100% Punching/Stencilling

3 WELDING OF BUTT JOINTS, (IF APPLICABLE) H R

Weld Inspection Visual 100% Drawing, Procedure


VT

Weld Soundness RT 100% Procedure RT

4 SETUP OF TUBES TO HEADER H H

Identification & Orientation Measurement 100% Drawing

Cleaning of tubes from inside Air blowing 100% free from foreign
material

Cleaning of Header from inside Air Blowing 100% free from foreign
material

Setup Dimensions Measurement 100% Drawing

Tube Alignment Measurement 100% Drawing

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P09
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
CONVECTION BANK MODULE ASSEMBLY DATE : 04-11-2011
PAGE : 2

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

Overall Dimensions Measurement 100% Drawing

5 WELDING OF TUBES TO HEADER H -

NDT on Root Run Weld PT/MT 100% Procedure PT/MT

Weld Inspection (Size & Finish) Measurement 100% Drawing / Procedure


& Visual VT

NDT after full weld PT/MT 100% Procedure PT/MT

6 CLEARANCE FOR PWHT H H

Overall Major Critical Dimensions Measurement 100% Drawing

Welding Insp.of Pressure Parts & Structural Attachments Visual 100% Drawing

NDE Clearance Review of 100% NDE Procedure


NDE Repor

7 PWHT H R

Heat-Treatment Compliance to Code Review of 100% IBR-1950


HT chart

8 HYDROSTATIC TEST, (IF APPLICABLE) H H

Hydro Test Verify 100% Drawing, Procedure

Pressure test result Record 100% Satisfactory

9 DRAINING & DRYING AFTER HYDRO TEST H -

Draining, Drying & Cleaning Visual 100% Inside surface shall


be Dry & Clean

10 FINAL INSPECTION H H

Overall Major Critical Dimensions Measurement 100% Drawing

Overall Assembly Inspection Visual 100% Drawing

Cleaning of header from inside before capping Air blowing 100% free from foreign
material

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P09
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
CONVECTION BANK MODULE ASSEMBLY DATE : 04-11-2011
PAGE : 3

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

Code Stamping Visual 100% IBR-1950

I.A.Stamp, Date & Rub-off Visual 100% IBR-1950, Legibility

Document Review Review 100% Compillation of


stage IR's & MTC's,
Code

11 PAINTING INSPECTION H -

Surface Preparation Visual 100% Drawing, Painting


Specs.

Paint Shade, Make, Batch No. Visual 100% Drawing, Painting


Specs.

Visual Inspection after painting Visual 100% Complete coverage of


area, No rundowns,
Peel-offs, Cracks

Paint-DFT Measurement Random Drawing, Painting


Specs.

Cleaning of header from inside before capping Air blowing 100% free from foreign
material

Capping / Blanking of all Tubes, Pipes, Openings Visual 100% All Tubes, Pipes,
Openings Shall be Co
vered /Capped

Identification Marking Visual 100% Drawing

12 INSPECTION RELEASE NOTE H -

Final Document Review Review 100% Drawing, Compilation


of document

Inspection Release Note Issuance of


IRN

3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.

1. WPS,PQR,WPQ and Welding Technology sheet(WTS)


2. Material Test Certificates

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P09
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
CONVECTION BANK MODULE ASSEMBLY DATE : 04-11-2011
PAGE : 4

3. Manufacturing Records
4. All the required Inspection Records.

SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

Following Documents shall be referred for this QAP (As Applicable) :

1) NDE Procedures

+---+-----------+-------------------------------------------+
|Sr.|Control No.|Procedure Description |
+---+-----------+-------------------------------------------+
|1) |RT12 |Radiographic Examination of Welded Joints |
+---+-----------+-------------------------------------------+
|2) |PT1 |Liquid Penetrant Examination |
+---+-----------+-------------------------------------------+
|3) |MT3 |Magnetic Particle Examination |
+---+-----------+-------------------------------------------+
|4) |UT2 |Ultrasonic Examination Of Butt Welds |
+---+-----------+-------------------------------------------+
|5) |UT4 |Straight Beam Ultrasonic Examination of |
| | |Rolled Steel Plates |
+---+-----------+-------------------------------------------+

2) RECORD NOT REQUIRED TO GENERATE FOR VISUAL INSPECTION AND


TACK WELD SOUNDNESS AS MENTIONED IN THIS ITP.

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P09
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
CONVECTION BANK MODULE ASSEMBLY DATE : 04-11-2011
PAGE : 5

4.0 INSPECTION POINTS


INSPECTION POINTS ARE INDICATED BY :

SAUDI ARAMCO

R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS

cycle marked by the AI/Customer/TPI. Record of inspection is maintained


and will be made available to AI/Customer/TPI for review during next
HOLD/WITNESS stage Inspection,as applicable.

W Witness Point WITNESS POINT is defined as a notification operation in operation / production


cycle marked by the AI/Customer/TPI to excercise their option to witness
and verify a specific operation. Further processing shall proceed where the
AI/Customer/TPI do not validate their option. The notification shall be
documented in a manner acceptable to AI/Customer/TPI, as applicable.

H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.

- - Inspection option will not be exercised

5.0 RECORD OF REVISIONS :

REV NO. DATE CHANGES

PREPARED BY CHECKED BY APPROVED BY ACCEPTED BY CLIENT/CONSULTANT/TPI

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN)


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P10
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
FINNED ECONOMISER ASSLY(FM) DATE : 09-09-2011
PAGE : 1

1.0 JOB SPECIFIC DATA : -

CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

CONSULTANT : - PROJECT NO:

INSP. AGENCY: DESIGN CODE :

2.0 QUALITY STAGES & INSPECTION :

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
CHARACTERISTICS METHOD EXTENT TL CLI

1 GROUND INSPECTION OF PRESSURE PARTS H H

Identification of Coils/Headers Visual 100% Drg

2 MATERIAL IDENTIFICATION H H

Review & Verification of Test Certificates & Drawing Review 100% Drawing, Material
Spec.

Correlation of MTC with Material Visual 100% Mill Test


Certificate

Dimensional Inspection Measurement 5% Drawing/Mill Test


Certificate

Identification Visual 100% Punching/Stencilling

3 GROUND INSPECTION OF ECONOMISER CASING & STRUCTURE H -

Identification Visual 100% Drawing

Visual Inspection Visual Random Drawing

Overall Assembly Inspection Measurement Random Drawing, free from


damage

Overall Dimensions , Diagonal Measurement Random Drawing

4 STRUCTURE & CASING H -

Compliance to Drg/ITP Review of 100% Drg/ITP No.N56 or


Insp.reco N59

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P10
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
FINNED ECONOMISER ASSLY(FM) DATE : 09-09-2011
PAGE : 2

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

5 INSPECTION OF COIL BENDS H -

Identification Visual 10% Drawing

Dimensions on Layout On layout 10% Within 2mm

Ovality Measurement 10% Max.10%

Thinning Measurement 10% Drawing,


100/(4R/D+2) Max.

Flow Area, (Cold Bending) Ball Test 100% Ball Size(Cold Bend)
(0.9OD-2.3SWT)-1.6mm

Flow Area, (Hot Bending) Ball Test 100% Ball Size(Hot Bend)(
0.85OD-2.3SWT)-3.2mm

Surface Defects, Die Marks VIsual 100% 0.5mm deep max.


(merge sharp notches
if any

Cracks, Wrinkles VIsual 100% No Cracks, Wrinkles

Post Bend Heat-Treatment If applicable Review of 100% Procedure


HT Chart Heat-Treatment

6 SETUP OF COIL BENDS TO FIN TUBES H H

Inspection Clearance of Coil Bends Verify 100% Drawing/IR

Alignment Measurement 100% Drawing

Dimensions on Layout Layout 100% Within 1mm


Matching

Setup Dimensions Measurement 100% Drawing

Tackweld Soundness PT 10% Procedure/Code

7 WELDING OF BUTT JOINTS H R

Weld Inspection (Size & Finish) Visual 100% Drawing & Procedure
VT

Excess Penetration (Flow area- Cold bending) Ball Test 100% Ball Size(0.9OD-2.3S
WT)-1.6mm

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P10
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
FINNED ECONOMISER ASSLY(FM) DATE : 09-09-2011
PAGE : 3

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

Excess Penetration (Flow area- hot bending) Ball Test 100% Ball Size(0.85OD-2.3
SWT)-3.2mm

Weld Soundness RT Code or Procedure RT


Min.5% **

** Min. 5% per Welder

8 ALIGNMENT OF HEADERS ON STRUCTURE H -

Identification & Orientaion Visual 100% Drawing

Alignment Water level 100% Within 2mm


, Plumb

Dimensions Measurement 100% Drawing

9 SETUP OF HEADER STUBS TO COILS H H

Cleaning of coils from inside Air blowing 100% free from foreign
material

Cleaning of Header from inside Air blowing 100% free from foreign
material

Setup Dimensions, Alignment Measurement 100% Drawing

10 WELDING OF HEADER STUBS TO COILS H R

Weld Inspection (Size & Finish) Visual 100% Drawing & Procedure
VT

Weld Soundness RT Code or Procedure RT


Min.5% **

** Min. 5% per Welder

11 HYDROSTATIC TESTING H H

Hydro Test pressure Verify 100% Drawing

Pressure gauges range Verify 100% 1.5 to 2.5 times of


test pressure

Calibration validity of Pressure gauges Verify 100% Calibration report &

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P10
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
FINNED ECONOMISER ASSLY(FM) DATE : 09-09-2011
PAGE : 4

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

due date

Pressure Gauges Verify 100% Record id.numbers

Cleaning of weld joints Visual 100% No rust or


extraneous mat.

Test pressure (on Pressure gauge) Visual 100% Test Pressure Shall
not exceed more than
6% at any time

Test Duration (Holding time) Measurement 100% Min.30 Minutes

Leakage Visual 100% No leakages

Pressure drop Visual 100% No Pressure drop

Pressure test result Record 100% Satisfactory

12 DRAINING & DRYING AFTER HYDRO TEST H -

Draining, Drying & Cleaning Visual 100% Inside surface shall


be Dry & Clean

13 FITMENT OF CASING & OTHER ATTACHMENTS H -

Identification & Orientaion Visual 100% Drawing

Overall Assembly Inspection Measurement 100% Drawing


& Visual

Weld Inspection (Size & Finish) Visual 100% Drawing & Procedure
VT

14 AIR LEAK TEST H -

Sealing of Eco.Casing by Air Test 70mm WC/ 100% Drawing/specs.


Drawing

15 FINAL INSPECTION H H

Overall Dimensions Measurement 10% Drawing

Overall Assembly Inspection Visual 100% Drawing

Overall Construction/ Fitment/ Alignment/ Appearance Measurement 100% Drawing

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P10
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
FINNED ECONOMISER ASSLY(FM) DATE : 09-09-2011
PAGE : 5

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

& Visual

Compliance to Drawing for Scope Verify 100% Drawing

Code Stamping Visual 100% Design Code

I.A.Stamp, Date & Rub off Visual 100% Design Code,


Legibility

Document Review Review 100% Drawing, Design


Code, Technical Spec
ifications

16 PAINTING INSPECTION H -

Surface Preparation Visual 100% Drawing, Painting


Specs.

Paint Shade Visual 100% Drawing, Painting


Specs.

Visual Inspection after painting Visual 100% Complete coverage of


area, No rundowns,
Peel-offs, Cracks

Paint-DFT Measurement Random Drawing, Painting


Specs.

Capping / Blanking of all Tubes, Pipes, Openings Visual 100% All Tubes, Pipes,
Openings Shall be Co
vered /Capped

Identification Marking Visual 100% Drawing

17 INSPECTION RELEASE NOTE H -

Final Document Review Review 100% Drawing, Compilation


of document

Inspection Release Note Issuance of


IRN

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P10
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
FINNED ECONOMISER ASSLY(FM) DATE : 09-09-2011
PAGE : 6

3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.

SAUDI ARAMCO

1. WPS,PQR,WPQ and Welding Technology sheet(WTS) WELDING PROCEDURE SPECIFICATIONS

2. Material Test Certificates


3. Manufacturing Records
4. All the required Inspection Records.

Following Documents shall be referred for this QAP (As Applicable) :

1) NDE Procedures

+---+-----------+-------------------------------------------+
|Sr.|Control No.|Procedure Description |
+---+-----------+-------------------------------------------+
|1) |RT12 |Radiographic Examination of Welded Joints |
+---+-----------+-------------------------------------------+
|2) |PT1 |Liquid Penetrant Examination |
+---+-----------+-------------------------------------------+
|3) |MT3 |Magnetic Particle Examination |
+---+-----------+-------------------------------------------+
|4) |UT2 |Ultrasonic Examination Of Butt Welds |
+---+-----------+-------------------------------------------+
|5) |UT4 |Straight Beam Ultrasonic Examination of |
| | |Rolled Steel Plates |
+---+-----------+-------------------------------------------+

2) RECORD NOT REQUIRED TO GENERATE FOR VISUAL INSPECTION AND


TACK WELD SOUNDNESS AS MENTIONED IN THIS ITP.

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P10
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
FINNED ECONOMISER ASSLY(FM) DATE : 09-09-2011
PAGE : 7

4.0 INSPECTION POINTS


INSPECTION POINTS ARE INDICATED BY :

SAUDI ARAMCO

R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS

cycle marked by the AI/Customer/TPI. Record of inspection is maintained


and will be made available to AI/Customer/TPI for review during next
HOLD/WITNESS stage Inspection,as applicable.

W Witness Point WITNESS POINT is defined as a notification operation in operation / production


cycle marked by the AI/Customer/TPI to excercise their option to witness
and verify a specific operation. Further processing shall proceed where the
AI/Customer/TPI do not validate their option. The notification shall be
documented in a manner acceptable to AI/Customer/TPI, as applicable.

H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.

- - Inspection option will not be exercised

5.0 RECORD OF REVISIONS :

REV NO. DATE CHANGES

PREPARED BY CHECKED BY APPROVED BY ACCEPTED BY CLIENT/CONSULTANT/TPI

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN)


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P11
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BARE TUBE ECONOMISER ASSLY(MODULAR TYPE) DATE : 04-11-2011
PAGE : 1

1.0 JOB SPECIFIC DATA : -

CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

CONSULTANT : - PROJECT NO:

INSP. AGENCY: DESIGN CODE :

2.0 QUALITY STAGES & INSPECTION :

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
CHARACTERISTICS METHOD EXTENT TL CLI

1 GROUND INSPECTION OF PRESSURE PARTS H H

Identification of Coils/Headers Visual 100% Drg/Shop Transfer


Note/IR

2 MATERIAL IDENTIFICATION H H

Review & Verification of Test Certificates & Drawing Review 100% Drawing, Material
Spec.

Correlation of MTC with Material Visual 100% Mill Test


Certificate

Dimensional Inspection Measurement 5% Drawing/Mill Test


Certificate

Identification Visual 100% Punching/Stencilling

3 GROUND INSPECTION OF CASING BEFORE COIL INSERTION H -

Identification Visual 100% Drawing

Visual Inspection Visual Random Drawing

Overall Assembly Inspection Measurement Random Drawing,free from


damage

Overall Dimensions , Diagonal Measurement Random Drawing

4 ALIGNMENT OF HEADERS ON STRUCTURE H -

Identification & Orientaion Visual 100% Drawing

Alignment Water level 100% Within 2mm


, Plumb

Dimensions Measurement 100% Drawing

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P11
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BARE TUBE ECONOMISER ASSLY(MODULAR TYPE) DATE : 04-11-2011
PAGE : 2

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

5 SETUP OF COILS WITH HEADER/S H H

No blockage/obstacles inside the coil Ball Test 100% Free from foreign
Material

Cleaning of Header from inside Air Blowing 100% Free from foreign
Material

Alignment Measurement 100% Drawing

Setup Dimensions Measurement 100% Drawing

Tackweld Soundness PT 10% Procedure/Code

6 WELDING OF COILS WITH HEADER/S H R

** NDT on Root Run Weld PT/MT 100% Procedure PT/MT

** if items Fabricated at Sub-vendors

Weld Inspection (Size & Finish) Visual 100% Drawing & Procedure
VT

NDT after full welding PT/MT 10% Procedure PT/MT

7 PWHT H R

Heat-Treatment Compliance to Code Review of 100% IBR-1950


HT chart

8 HYDROSTATIC TESTING H H

Hydro Test pressure Verify 100% Drawing

Pressure gauges range Verify 100% 1.5 to 2.5 times of


test pressure

Calibration validity of Pressure gauges Verify 100% Calibration report &


due date

Pressure Gauges Verify 100% Record id.numbers

Cleaning of weld joints Visual 100% No rust or


extraneous mat.

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P11
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BARE TUBE ECONOMISER ASSLY(MODULAR TYPE) DATE : 04-11-2011
PAGE : 3

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

Test pressure (on Pressure gauge) Visual 100% Test Pressure Shall
not exceed more than
6% at any time

Test Duration (Holding time) Measurement 100% Min.30 Minutes

Leakage Visual 100% No leakages

Pressure drop Visual 100% No Pressure drop

Pressure test result Record 100% Satisfactory

9 DRAINING & DRYING AFTER HYDRO TEST H -

Draining, Drying & Cleaning Visual 100% Inside surface shall


be Dry & Clean

10 FITMENT OF CASING & OTHER ATTACHMENTS H -

Identification & Orientaion Visual 100% Drawing

Overall Assembly Inspection Measurement 100% Drawing


& Visual

Weld Inspection (Size & Finish) Visual 100% Drawing & Procedure
VT

11 FINAL INSPECTION H H

Overall Dimensions Measurement 10% Drawing

Overall Assembly Inspection Visual 100% Drawing

Overall Construction/ Fitment/ Alignment/ Appearance Measurement 100% Drawing


& Visual

Compliance to Drawing for Scope Verify 100% Drawing

Code Stamping Visual 100% Design Code

I.A.Stamp, Date & Rub-off Visual 100% Design Code,


Legibility

Document Review Review 100% Drawing, Design


Code, Technical Spec
ifications

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P11
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BARE TUBE ECONOMISER ASSLY(MODULAR TYPE) DATE : 04-11-2011
PAGE : 4

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

12 PAINTING INSPECTION H -

Surface Preparation Visual 100% Drawing, Painting


Specs.

Visual Inspection after painting Visual 100% Complete coverage of


area, No rundowns,
Peel-offs, Cracks

Paint-DFT Measurement Random Drawing, Painting


Specs.

Capping / Blanking of all Tubes, Pipes, Openings Visual 100% All Tubes, Pipes,
Openings Shall be Co
vered /Capped

Identification Marking Visual 100% Drawing

13 INSPECTION RELEASE NOTE H -

Final Document Review Review 100% Drawing, Code,


Technical Specificat
ions

Inspection Release & Certification Issuance of 100% Drawing, Code,


IRN Technical Specificat
ions

3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.

1. WPS,PQR,WPQ and Welding Technology sheet(WTS)


2. Material Test Certificates
3. Manufacturing Records
4. All the required Inspection Records.

Following Documents shall be referred for this QAP (As Applicable) :

1) NDE Procedures

+---+-----------+-------------------------------------------+
|Sr.|Control No.|Procedure Description |

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P11
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BARE TUBE ECONOMISER ASSLY(MODULAR TYPE) DATE : 04-11-2011
PAGE : 5

+---+-----------+-------------------------------------------+
|1) |RT12 |Radiographic Examination of Welded Joints |
+---+-----------+-------------------------------------------+
SAUDI ARAMCO

|2) |PT1 |Liquid Penetrant Examination | WELDING PROCEDURE SPECIFICATIONS

+---+-----------+-------------------------------------------+
|3) |MT3 |Magnetic Particle Examination |
+---+-----------+-------------------------------------------+
|4) |UT2 |Ultrasonic Examination Of Butt Welds |
+---+-----------+-------------------------------------------+
|5) |UT4 |Straight Beam Ultrasonic Examination of |
| | |Rolled Steel Plates |
+---+-----------+-------------------------------------------+

2) RECORD NOT REQUIRED TO GENERATE FOR VISUAL INSPECTION AND


TACK WELD SOUNDNESS AS MENTIONED IN THIS ITP.

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P11
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BARE TUBE ECONOMISER ASSLY(MODULAR TYPE) DATE : 04-11-2011
PAGE : 6

4.0 INSPECTION POINTS


INSPECTION POINTS ARE INDICATED BY :

SAUDI ARAMCO

R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS

cycle marked by the AI/Customer/TPI. Record of inspection is maintained


and will be made available to AI/Customer/TPI for review during next
HOLD/WITNESS stage Inspection,as applicable.

W Witness Point WITNESS POINT is defined as a notification operation in operation / production


cycle marked by the AI/Customer/TPI to excercise their option to witness
and verify a specific operation. Further processing shall proceed where the
AI/Customer/TPI do not validate their option. The notification shall be
documented in a manner acceptable to AI/Customer/TPI, as applicable.

H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.

- - Inspection option will not be exercised

5.0 RECORD OF REVISIONS :

REV NO. DATE CHANGES

PREPARED BY CHECKED BY APPROVED BY ACCEPTED BY CLIENT/CONSULTANT/TPI

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN)


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P12
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
RISERS,DOWN COMERS,SUPPLY TUBES/PIPES DATE : 19-09-2011
PAGE : 1

1.0 JOB SPECIFIC DATA : -

CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

CONSULTANT : - PROJECT NO:

INSP. AGENCY: DESIGN CODE :

2.0 QUALITY STAGES & INSPECTION :

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
CHARACTERISTICS METHOD EXTENT TL CLI

1 MATERIAL IDENTIFICATION H H

Review & Verification of Test Certificates & Drawing Review 100% Drawing, Material
Spec.

Correlation of MTC with Material Visual 100% Mill Test


Certificate

Dimensional Inspection Measurement 5% Drawing/Mill Test


Certificate

Identification Visual 100% Punching/Stencilling

2 INSPECTION OF SAMPLE/FIRST PRODUCTION BEND H R

Layout Inspection Measurement 100% Drawing


& Visual

Dimensions on Layout Layout 100% Within 3mm


Matching

Ovality of Tubes Measurement 100% Within 10%

Thinning of Tubes Measurement 100% Drawing,


100/(4R/D+2) Max.

Surface defects, Die Marks Visual 100% 0.5 mm (deep) max.


without sharp notche
s

Cracks, Wrinkles Visual 100% No Cracks, Wrinkles

3 INSPECTION OF TUBES AFTER BENDING H -

Layout Inspection Measurement 100% Drawing


& Visual

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P12
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
RISERS,DOWN COMERS,SUPPLY TUBES/PIPES DATE : 19-09-2011
PAGE : 2

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

Dimensions on Layout Layout 100% Within 3mm


Matching

Ovality of Tubes Measurement 5% Within 10%

Thinning of Tubes Measurement 5% Drawing,


100/(4R/D+2) Max.

Surface defects, Die Marks Visual 100% 0.5 mm deep max


without sharp notche
s

Cracks, Wrinkles Visual 100% No Cracks, Wrinkles

4 SETUP OF BUTT JOINTS H H

Orientation Visual 100% Drawing

Setup Dimensions Measurement 10% Drawing

Dimensions Measurement 100% Drawing

5 WELDING OF BUTT JOINTS H R

Weld Inspection Visual 100% Drawing, Procedure


VT

Risers,Downcomers,supply tubes/pipes <= 168.3 OD RT 10% Procedure RT

Risers,Downcomers,supply tubes/pipes > 168.3 OD RT 100% Procedure RT

Weld Soundness for Main DC RT 100% Procedure RT

Welder Identification Verify 100% Qualified Welder


List

6 SETUP OF BRANCH/FILLET WELD JOINTS H H

Orientation Visual 100% Drawing

Setup Dimensions Measurement 100% Drawing

Alignment/ Squareness Measurement 100% within 1 degree or 3


mm Max.

Projection from Hdr C/L Measurement 100% Drawing

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P12
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
RISERS,DOWN COMERS,SUPPLY TUBES/PIPES DATE : 19-09-2011
PAGE : 3

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

Tack weld soundness PT 100% Procedure PT

7 WELDING INSPECTION FOR BRANCH/FILLET WELD JOINTS H -

NDE after root run welding ** PT 100% Procedure PT

** If items are fabricated at sub-vendor

Visual Inspection after full welding Visual 100% Procedure VT

Weld Size & Finish After Full Welding Visual 100% Drawing

NDE of welds for Carban steel PT/MT 10%random Procedure PT/MT

NDE of welds for Alloy steel PT/MT 100% Procedure PT/MT

UT of Full penetration welds >=10 NPS or above 25 thk UT/RT 100% Procedure UT/RT

8 STRUCTURALS & ATTACHMENTS H -

Orientaion Visual 100% Drawing

Dimensions Measurement 100% Drawing

Weld Size & Finish Visual 100% Drawing

Weld Soundness PT 10% Procedure-PT

9 CLEARANCE FOR PWHT (IF APPLICABLE) H H

Overall Major Critical Dimensions Measurement 100% Drawing

NDE Clearance Review 100% NDE Procedure

Code Punching Visual 100% IBR-1950

10 PWHT (IF APPLICABLE) H R

Heat-Treatment Compliance to Code Review of 100% Design Code +


HT chart Thermax Std.

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P12
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
RISERS,DOWN COMERS,SUPPLY TUBES/PIPES DATE : 19-09-2011
PAGE : 4

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

11 FINAL INSPECTION H H

Compliance to Drawing for Scope Verify 100% Drawing-BOM

Overall Major Critical Dimensions Measurement 100% Drawing

Code Punching,(As Applicable) Visual 100% IBR-1950

I.A.Stamp & Date,(As Applicable) Rub-off 100% IBR-1950 /


Legibility

Document review Review 100% Compillation of


stage IR's & MTC's,
Code

12 PAINTING INSPECTION H -

Surface Preparation Visual 100% Drawing, Painting


Specs.

Paint Shade, Make, Batch No. Visual 100% Drawing, Painting


Specs.

Visual Inspection after painting Visual 100% Complete coverage of


area, No rundowns,
Peel-offs, Cracks

Paint-DFT Measurement Random Drawing, Painting


Specs.

Cleaning from inside before capping Air blowing 100% Free from foreign
material

Capping / Blanking of all Tubes, Pipes, Openings Visual 100% All Tubes, Pipes,
Openings Shall be Co
vered /Capped

ID Marking/Stenciling(Boiler No./Drg No./Mark/ Part No.) Visual 100% Drawing

13 INSPECTION RELEASE NOTE H -

Final Document Review Review 100% Drawing, Compilation


of document

Inspection Release & Certification Issuance of


IRN

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST L NO. : ITP/ERPLN /P12


SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
RISERS,DOWN COMERS,SUPPLY TUBES/PIPES DATE : 19-09-2011
PAGE : 5

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.

1. WPS,PQR,WPQ and Welding Technology sheet(WTS)


2. Material Test Certificates
3. Manufacturing Records
4. All the required Inspection Records.

Following Documents shall be referred for this QAP (As Applicable) :

1) NDE Procedures

+---+-----------+-------------------------------------------+
|Sr.|Control No.|Procedure Description |
+---+-----------+-------------------------------------------+
|1) |RT12 |Radiographic Examination of Welded Joints |
+---+-----------+-------------------------------------------+
|2) |PT1 |Liquid Penetrant Examination |
+---+-----------+-------------------------------------------+
|3) |MT3 |Magnetic Particle Examination |
+---+-----------+-------------------------------------------+
|4) |UT2 |Ultrasonic Examination Of Butt Welds |
+---+-----------+-------------------------------------------+
|5) |UT4 |Straight Beam Ultrasonic Examination of |
| | |Rolled Steel Plates |
+---+-----------+-------------------------------------------+

2) RECORD NOT REQUIRED TO GENERATE FOR VISUAL INSPECTION AND


TACK WELD SOUNDNESS AS MENTIONED IN THIS ITP.

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P12
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
RISERS,DOWN COMERS,SUPPLY TUBES/PIPES DATE : 19-09-2011
PAGE : 6

4.0 INSPECTION POINTS


INSPECTION POINTS ARE INDICATED BY :

SAUDI ARAMCO

R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS

cycle marked by the AI/Customer/TPI. Record of inspection is maintained


and will be made available to AI/Customer/TPI for review during next
HOLD/WITNESS stage Inspection,as applicable.

W Witness Point WITNESS POINT is defined as a notification operation in operation / production


cycle marked by the AI/Customer/TPI to excercise their option to witness
and verify a specific operation. Further processing shall proceed where the
AI/Customer/TPI do not validate their option. The notification shall be
documented in a manner acceptable to AI/Customer/TPI, as applicable.

H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.

- - Inspection option will not be exercised

5.0 RECORD OF REVISIONS :

REV NO. DATE CHANGES

PREPARED BY CHECKED BY APPROVED BY ACCEPTED BY CLIENT/CONSULTANT/TPI

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN)


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P13
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
COILS (ECO/SH COILS) DATE : 04-11-2011
PAGE : 1

1.0 JOB SPECIFIC DATA : -

CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

CONSULTANT : - PROJECT NO:

INSP. AGENCY: DESIGN CODE :

2.0 QUALITY STAGES & INSPECTION :

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
CHARACTERISTICS METHOD EXTENT TL CLI

1 MATERIAL IDENTIFICATION H H

Review & Verification of Test Certificates & Drawing Review 100% Drawing, Material
Spec.

Correlation of MTC with Material Visual 100% Mill Test


Certificate

Dimensional Inspection Measurement 5% Drawing/Mill Test


Certificate

Identification Visual 100% Punching/Stencilling

2 SAMPLE/FIRST PRODUCTION BEND (WITH MAX.BEND DEGREE) H R

Dimensions on Layout Layout 100% Within 3mm


Matching

Ovality Measurement 100% 10% Max.

Thinning Measurement 100% Drawing /


100/(4R/D+2) max.

Flow Area for Cold Bending* Ball Test 100% Ball Size=(0.9OD-2.3
SWT)-1.6mm

Flow Area for Hot bending* Ball Test 100% Ball Size=(0.85OD-2.
3SWT)-3.2mm

*for Tubes O.D less than 3"

Surafce defects Visual 100% 0.5 mm deep max.


without sharp notche
s

Wrinkles, Cracks, Die Marks Visual 100% Not Acceptable

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P13
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
COILS (ECO/SH COILS) DATE : 04-11-2011
PAGE : 2

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

3 INSPECTION OF TUBES AFTER BENDING H -

Layout Inspection Measurement 100% Drawing


& Visual

Dimensions on Layout Layout 5% Within 3mm


Matching

Ovality Measurement 1bend /coil Within 10%


on 5%

Thinning Measurement 1bend /coil Drawing,


on 5% 100/(4R/D+2) Max.

Surface defects, Die Marks Visual 100% 0.5 mm deep max


without sharp notche
s

Cracks, Wrinkles Visual 100% No Cracks, Wrinkles

4 SETUP OF BUTT JOINTS H H

Orientation Visual 100% Drawing

Setup Dimensions Measurement 10% random Drawing

Alignment Measurement 10% random Drawing

5 WELDING OF BUTT JOINTS H R

Visual Inspection Visual 100% Procedure VT

PMI on Alloy steel welds PMI 2% Random Procedure PMI

Weld Soundness after full welding except P15E materials RT Code or Min Procedure RT
5%*

*Minimum 5% per welder

Note :RT & PMI for P15E materials to be carried after PWHT.

6 INSPECTION & NDE AFTER PWHT FOR P15E MATERIAL H R

Butt Weld Soundness after Full Welding RT 100% Procedure RT

PMI for P15E materials PMI 10%Random Procedure PMI

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P13
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
COILS (ECO/SH COILS) DATE : 04-11-2011
PAGE : 3

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

7 STRUCTURALS & ATTACHMENTS H -

Overall Major Critical Dimensions Measurement 100% Drawing

Attachment welds Visual 100% Drawing

NDE PT/MT 2% Procedure PT/MT

8 POST BENDING HEAT TREATMENT-IF APPLICABLE H R

Heat-Treatment Compliance to Code for 180 degree bend only HT Chart 100% Drg/HT Procedure

9 FINAL INSPECTION OF COILS H H

Inspection of Floor Layout Measurement 100% Drawing

Identification Marking Visual 100% Drawing

Dimensions on Layout Layout 10%Random Within 3mm


Matching

Flow Area, (Cold Bending)* Ball Test 100% Ball Size(Cold Bend)
(0.9OD-2.3SWT)-1.6mm

Flow Area, (Hot Bending)* Ball Test 100% Ball Size(Hot Bend)(
0.85OD-2.3SWT)-3.2mm

*for Tubes O.D less than 3"

Site Weld Preperation Template Random Drawing

End Identification Visual 10% random Drawing

Document review Review 100% Compillation of


stage IR's & MTC's,
Code

10 PAINTING INSPECTION H -

Surface Preparation Visual 100% Drawing, Painting


Specs.

Visual Inspection after painting Visual 100% Complete coverage of


area, No rundowns,
Peel-offs, Cracks

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P13
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
COILS (ECO/SH COILS) DATE : 04-11-2011
PAGE : 4

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

Cleaning of coils from inside before capping Air Blowing 100% Free from foreign
material

Capping / Blanking of all Tubes Visual 100% All Tubes Shall be


Covered /Capped

ID Marking/Stenciling(Boiler No./Drg No./Mark/ Part No.) Visual 100% Drawing

11 INSPECTION RELEASE NOTE H -

Final Document Review Review 100% Drawing, Compilation


of document

Inspection Release Note Issuance of


IRN

3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.

1. WPS,PQR,WPQ and Welding Technology sheet(WTS)


2. Material Test Certificates
3. Manufacturing Records
4. All the required Inspection Records.

Following Documents shall be referred for this QAP (As Applicable) :

1) NDE Procedures

+---+-----------+-------------------------------------------+
|Sr.|Control No.|Procedure Description |
+---+-----------+-------------------------------------------+
|1) |RT12 |Radiographic Examination of Welded Joints |
+---+-----------+-------------------------------------------+
|2) |PT1 |Liquid Penetrant Examination |
+---+-----------+-------------------------------------------+
|3) |MT3 |Magnetic Particle Examination |
+---+-----------+-------------------------------------------+
|4) |UT2 |Ultrasonic Examination Of Butt Welds |
+---+-----------+-------------------------------------------+
|5) |UT4 |Straight Beam Ultrasonic Examination of |
| | |Rolled Steel Plates |
+---+-----------+-------------------------------------------+

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P13
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
COILS (ECO/SH COILS) DATE : 04-11-2011
PAGE : 5

2) RECORD NOT REQUIRED TO GENERATE FOR VISUAL INSPECTION AND


TACK WELD SOUNDNESS AS MENTIONED IN THIS ITP.
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

4.0 INSPECTION POINTS


INSPECTION POINTS ARE INDICATED BY :

R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production
cycle marked by the AI/Customer/TPI. Record of inspection is maintained
and will be made available to AI/Customer/TPI for review during next
HOLD/WITNESS stage Inspection,as applicable.

W Witness Point WITNESS POINT is defined as a notification operation in operation / production


cycle marked by the AI/Customer/TPI to excercise their option to witness
and verify a specific operation. Further processing shall proceed where the
AI/Customer/TPI do not validate their option. The notification shall be
documented in a manner acceptable to AI/Customer/TPI, as applicable.

H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.

- - Inspection option will not be exercised

5.0 RECORD OF REVISIONS :

REV NO. DATE CHANGES

PREPARED BY CHECKED BY APPROVED BY ACCEPTED BY CLIENT/CONSULTANT/TPI

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN)


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P15
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
HEADERS DATE : 04-11-2011
PAGE : 1

1.0 JOB SPECIFIC DATA : -

CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

CONSULTANT : - PROJECT NO:

INSP. AGENCY: DESIGN CODE :

2.0 QUALITY STAGES & INSPECTION :

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
CHARACTERISTICS METHOD EXTENT TL CLI

1 MATERIAL IDENTIFICATION H H

Review & Verification of Test Certificates & Drawing Review 100% Drawing, Material
Spec.

Correlation of MTC with Material Visual 100% Mill Test


Certificate

Dimensional Inspection Measurement 5% Drawing/Mill Test


Certificate

Identification & stamp transfer Visual 100% Punching/Stencilling

2 INSPECTION OF SAMPLE/FIRST PRODUCTION HEADER BENT STUB H W

Dimensions on Layout Layout 100% Within 3mm


Matching

Ovality of Tubes Measurement 100% 10% Max.

Thinning of Tubes Measurement 100% Drawing,


100/(4R/D+2) Max.

Flow Area for Cold Bending* Ball Test 100% Ball Size=(0.9OD-2.3
SWT)-1.6mm

Flow Area for Hot bending* Ball Test 100% Ball Size=(0.85OD-2.
3SWT)-3.2mm

*for Tubes O.D less than 3"

Surafce defects, Die marks Visual 100% 0.5 mm deep max.


without sharp notche
s

Cracks, Wrinkles Visual 100% No Cracks, Wrinkles

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P15
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
HEADERS DATE : 04-11-2011
PAGE : 2

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

3 INSPECTION OF HEADER BENT TUBES AFTER BENDING H W

Dimensions on Layout Layout 5%% Within 2mm


Matching

Ovality Measurement 5% 10% Max.

Thinning Measurement 5% Drawing,


100/(4R/D+2) Max.

Surafce defects, Die marks Visual 100% 0.5 mm deep max.


without sharp notche
s

Cracks, Wrinkles Visual 100% No Cracks, Wrinkles

4 SETUP & WELDING OF BAFFLE PLATES,(IF ANY) H -

Setup Dimensions & Locations Measurement 100% Drawing

Weld Size & Finish After Full Welding Visual 100% Drawing & Procedure
VT

5 BUTT WELD SETUP & WELDING FOR HDR PIPE, (IF ANY) H H

Setup Dimensions, Alignment Measurement 100% Drawing

Weld Visual Inspection Visual 100% Drawing & Procedure


VT

Weld Soundness RT 100% Procedure RT

6 DRILLING MARKING INSPECTION H -

Pipe Straightness By String 100% 1mm/Mtr, 3mm Max.

Quadrant Distribution & Marking Combination 100% Max.difference of


Set 1/2 Degree

Orientation Visual 100% Drawing

End Hole Location Measurement 100% Drawing

Hole Centre Punch Pitch Measurement 100% Drawing

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P15
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
HEADERS DATE : 04-11-2011
PAGE : 3

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

7 DRILLING INSPECTION H -

Orientation Visual 100% Drawing

Quadrant & LH/RH Marking Visual 100% Drawing

Drilled Hole Dimensions Measurement 100% Drawing

Ligament Measurement 100% Mark Min.Ligament

Hole Finish Visual 100% Free From Tool Marks


& Sharp Edges

8 INSP.OF MACHINED COMPONENTS H -

Identification & verification of stamp transfer Visual 100% Drawing

Dimensional Inspection Measurement 100% Drawing

Weld Preparation Measurement 100% Drawing

Visual inspection of weld preparation Visual 100% No


Cracks/Laminations

Peripheral edges of End cover if mfg.from plate** PT/MT 100% Procedure PT/MT

**for end cover as per IBR-Fig.No.365/2A

9 BRANCH WELD SETUP & WELDING H H

Orientation Visual 100% Drawing

Setup Dimensions Measurement 100% Drawing

Alignment/ Squareness Measurement 100% within 1 degree or 3


mm Max.

Projection from Hdr C/L Measurement 100% Drawing

Tack weld soundness PT 100% Procedure PT

** NDE after root run welding PT 100% Procedure PT

** If Headers are fabricated at sub-vendor

Visual Inspection after full welding Visual 100% Procedure VT

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P15
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
HEADERS DATE : 04-11-2011
PAGE : 4

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

Weld Size & Finish After Full Welding Visual 100% Drawing

NDE of welds for CS Hdr. PT/MT 10%random Procedure PT/MT

NDE of welds for AS Hdr. PT/MT 100% Procedure PT/MT

Note:For P15E materials NDE to be carried after PWHT

UT of Full penetration welds >=10 NPS or above 25 thk UT/RT 100% Procedure UT/RT

10 WELD SETUPS-HEADER PIPE/STUB TO REDUCER/FLANGE/END COVER; REDUCER TO FLANGE H W

Orientation Visual 100% Drawing

Setup Dimensions Measurement 100% Drawing

Visual Inspection Visual 100% Procedure VT

11 WELDING OF ABOVE H R

Visual Inspection Visual 100% Procedure VT

Butt Weld Soundness after Final Welding except P15 materials RT 100% Procedure RT

Note:For P15E materials RT to be carried after PWHT

Peripheral edges & remaining exposed surface of weld jt.** PT/MT 100% Procedure PT/MT

**for end cover as per IBR-Fig.No.365/2A

12 STRUCTURALS & ATTACHMENTS H -

Identification & Orientation Visual 100% Drawing

Dimensions Measurement 100% Drawing

Setup Dimensions Measurement 100% Drawing

Weld Inspection (Size & Finish) Measurement 100% Drawing & Procedure
& Visual VT

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P15
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
HEADERS DATE : 04-11-2011
PAGE : 5

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

13 INSPECTION BEFORE PWHT H -

Overall Major Critical Dimensions Measurement 100% Drawing

NDE Clearance Review 100% NDE Procedure

Code Punching Visual 100% IBR-1950

PMI for Alloy Verificaion of Accessible welds PMI Check 100% Procedure PMI/
Specs.

PMI for Alloy Verificaion of Parent Material PMI Check Random Procedure PMI/
Specs.

Note:For P15E materials PMI to be carried after PWHT

14 PWHT H R

Heat-Treatment Compliance Review of 100% IBR-1950, Thermax


HT chart Standard

15 INSPECTION AFTER PWHT H -

Straightness of header Measurement 100% 1 mm/Mtr / 6 mm max


(whichever is less)

NDE of all weld joints (for alloy steel hdr only) MT/PT 100% Procedure MT/PT

Butt Weld Soundness after Full Welding for P15E materials RT 100% Procedure RT

PMI for P15E materials PMI Per Procedure PMI


procedure

16 MOCK UP OF PANEL WITH RESPECTIVE HEADER-FOR SITE ASSEMBLED HEADER ONLY H -

Orientation Visual 100% Drawing

Alignment & overall major Dimensions Measurement 100% Drawing

Identification Punching/Marking of Header Verify 100% Drawing

17 FINAL INSPECTION H H

Identification & Orientation Visual 100% Drawing

Site Weld Preperation Visual 100% Drawing

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P15
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
HEADERS DATE : 04-11-2011
PAGE : 6

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

Cleaning of header from inside before capping Air blowing 100% free from foreign
material

I.A.Stamp & Date, (As Applicable) Final 100% IBR-1950 /


Rub-off Legibility

Document Review Review 100% Compillation of


stage IR's & MTC's,
Code

18 PAINTING INSPECTION H -

Surface Preparation Visual 100% Drawing, Painting


Specs.

Paint Shade, Make, Batch No. Visual 100% Drawing, Painting


Specs.

Visual Inspection after painting Visual 100% Complete coverage of


area, No rundowns,
Peel-offs, Cracks

Paint-DFT Measurement Random Drawing, Painting


Specs.

Cleaning of header from inside before capping Air blowing 100% free from foreign
material

Capping / Blanking of all Tubes, Pipes, Openings Visual 100% All Tubes, Pipes,
Openings Shall be Co
vered /Capped

Identification Marking Visual 100% Drawing

19 INSPECTION RELEASE NOTE H -

Final Document Review Review 100% Drawing, Compilation


of document

Inspection Release Note Issuance of


IRN

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P15
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
HEADERS DATE : 04-11-2011
PAGE : 7

3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.

SAUDI ARAMCO

1. WPS,PQR,WPQ and Welding Technology sheet(WTS) WELDING PROCEDURE SPECIFICATIONS

2. Material Test Certificates


3. Manufacturing Records
4. All the required Inspection Records.

Following Documents shall be referred for this QAP (As Applicable) :

1) NDE Procedures

+---+-----------+-------------------------------------------+
|Sr.|Control No.|Procedure Description |
+---+-----------+-------------------------------------------+
|1) |RT12 |Radiographic Examination of Welded Joints |
+---+-----------+-------------------------------------------+
|2) |PT1 |Liquid Penetrant Examination |
+---+-----------+-------------------------------------------+
|3) |MT3 |Magnetic Particle Examination |
+---+-----------+-------------------------------------------+
|4) |UT2 |Ultrasonic Examination Of Butt Welds |
+---+-----------+-------------------------------------------+
|5) |UT4 |Straight Beam Ultrasonic Examination of |
| | |Rolled Steel Plates |
+---+-----------+-------------------------------------------+

2) RECORD NOT REQUIRED TO GENERATE FOR VISUAL INSPECTION AND


TACK WELD SOUNDNESS AS MENTIONED IN THIS ITP.

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P15
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
HEADERS DATE : 04-11-2011
PAGE : 8

4.0 INSPECTION POINTS


INSPECTION POINTS ARE INDICATED BY :

SAUDI ARAMCO

R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS

cycle marked by the AI/Customer/TPI. Record of inspection is maintained


and will be made available to AI/Customer/TPI for review during next
HOLD/WITNESS stage Inspection,as applicable.

W Witness Point WITNESS POINT is defined as a notification operation in operation / production


cycle marked by the AI/Customer/TPI to excercise their option to witness
and verify a specific operation. Further processing shall proceed where the
AI/Customer/TPI do not validate their option. The notification shall be
documented in a manner acceptable to AI/Customer/TPI, as applicable.

H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.

- - Inspection option will not be exercised

5.0 RECORD OF REVISIONS :

REV NO. DATE CHANGES

PREPARED BY CHECKED BY APPROVED BY ACCEPTED BY CLIENT/CONSULTANT/TPI

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN)


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P16
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
HEADERS (SHOP ASSLY) DATE : 04-11-2011
PAGE : 1

1.0 JOB SPECIFIC DATA : -

CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

CONSULTANT : - PROJECT NO:

INSP. AGENCY: DESIGN CODE :

2.0 QUALITY STAGES & INSPECTION :

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
CHARACTERISTICS METHOD EXTENT TL CLI

1 MATERIAL IDENTIFICATION H H

Review & Verification of Test Certificates & Drawing Review 100% Drawing, Material
Spec.

Correlation of MTC with Material Visual 100% Mill Test


Certificate

Dimensional Inspection Measurement 5% Drawing/Mill Test


Certificate

Identification & stamp transfer Visual 100% Punching/Stencilling

2 SETUP & WELDING OF BAFFLE PLATES,(IF ANY) H -

Setup Dimensions & Locations Measurement 100% Drawing

Weld Size & Finish After Full Welding Visual 100% Drawing & Procedure
VT

3 BUTT WELD SETUP & WELDING FOR HDR PIPE, (IF ANY) H H

Setup Dimensions, Alignment Measurement 100% Drawing

Weld Visual Inspection Visual 100% Drawing & Procedure


VT

Weld Soundness RT 100% Procedure RT

4 INSP.OF MACHINED COMPONENTS H -

Identification & verification of stamp transfer Visual 100% Drawing

Dimensional Inspection Measurement 100% Drawing

Weld Preparation Measurement 100% Drawing

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P16
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
HEADERS (SHOP ASSLY) DATE : 04-11-2011
PAGE : 2

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

Visual inspection of weld preparation Visual 100% No


Cracks/Laminations

Peripheral edges of End cover if mfg.from plate** PT/MT 100% Procedure PT/MT

**for end cover as per IBR-Fig.No.365/2A

5 DRILLING MARKING INSPECTION H -

Pipe Straightness By String 100% 1mm/Mtr, 3mm Max.

Quadrant Distribution & Marking Combination 100% Max.difference of


Set 1/2 Degree

Orientation Visual 100% Drawing

End Hole Location Measurement 100% Drawing

Hole Centre Punch Pitch Measurement 100% Drawing

Centre Punching Inlinement By String 100% Within +/- 1mm

6 DRILLING INSPECTION H -

Orientation Visual 100% Drawing

Quadrant & LH/RH Marking Visual 100% Drawing

Quadrantwise Hole Locations from End Measurement 100% Within +/-1mm

Drilled Hole Dimensions Measurement 100% Drawing

Ligament Measurement 100% Mark Min.Ligament

Inlinement of Drilled Holes Measurement 100% Within +/- 1mm

Hole Finish Visual 100% Free From Tool Marks


& Sharp Edges & sur
face defects

7 BRANCH WELD SETUP & WELDING H H

Orientation Visual 100% Drawing

Setup Dimensions Measurement 100% Drawing

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P16
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
HEADERS (SHOP ASSLY) DATE : 04-11-2011
PAGE : 3

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

Alignment/ Squareness Measurement 100% within 1 degree or 3


mm Max.

Projection from Hdr C/L Measurement 100% Drawing

Tack weld soundness PT 100% Procedure PT

** NDE after root run welding PT 100% Procedure PT

** If Headers are fabricated at sub-vendor

Visual Inspection after full welding Visual 100% Procedure VT

Weld Size & Finish After Full Welding Visual 100% Drawing

NDE of welds for CS Hdr. PT/MT 10%random Procedure PT/MT

NDE of welds for AS Hdr. PT/MT 100% Procedure PT/MT

Note:For P15E materials NDE to be carried after PWHT

UT of Full penetration welds >=10 NPS or above 25 thk UT/RT 100% Procedure UT2/RT

8 WELD SETUPS-HEADER PIPE/STUB TO REDUCER/FLANGE/END COVER; REDUCER TO FLANGE H W

Orientation Visual 100% Drawing

Setup Dimensions Measurement 100% Drawing

Visual Inspection Visual 100% Procedure VT

9 WELDING OF ABOVE H R

Visual Inspection Visual 100% Procedure VT

Butt Weld Soundness after Final Welding RT 100% Procedure RT

Peripheral edges & remaining exposed surface of weld jt.** PT/MT 100% Procedure PT/MT

**for end cover as per IBR-Fig.No.365/2A

Note:For P15E materials NDE to be carried after PWHT

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P16
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
HEADERS (SHOP ASSLY) DATE : 04-11-2011
PAGE : 4

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

10 STRUCTURALS & ATTACHMENTS H -

Identification & Orientation Visual 100% Drawing

Dimensions Measurement 100% Drawing

Setup Dimensions Measurement 100% Drawing

Weld Inspection (Size & Finish) Measurement 100% Drawing & Procedure
& Visual VT

11 INSPECTION & NDE AFTER PWHT FOR P15E MATERIAL H R

Straightness of header Measurement 100% 1 mm/Mtr / 6 mm max


(whichever is less)

NDE of all weld joints MT/PT 100% Procedure MT/PT

Butt Weld Soundness after Full Welding RT 100% Procedure RT

12 CLEARANCE FOR ASSLY H R

Identification & Orientation Visual 100% Drawing

Dimensions Measurement 100% Drawing

Straightness Measurement 100% 1mm/Mtr, or 6mm Max.

PMI for Alloy Verificaion of Accessible welds PMI Check 100% Procedure PMI/
Specs.

PMI for Alloy Verificaion of Parent Material PMI Check Random Procedure PMI/
Specs.

Note:For P15E materials PMI to be carried after PWHT

Document Review Review 100% Compillation of


stage IR's & MTC's,
Code

3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.

1. WPS,PQR,WPQ and Welding Technology sheet(WTS)


2. Material Test Certificates

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P16
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
HEADERS (SHOP ASSLY) DATE : 04-11-2011
PAGE : 5

3. Manufacturing Records
4. All the required Inspection Records.

SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

Following Documents shall be referred for this QAP (As Applicable) :

1) NDE Procedures

+---+-----------+-------------------------------------------+
|Sr.|Control No.|Procedure Description |
+---+-----------+-------------------------------------------+
|1) |RT12 |Radiographic Examination of Welded Joints |
+---+-----------+-------------------------------------------+
|2) |PT1 |Liquid Penetrant Examination |
+---+-----------+-------------------------------------------+
|3) |MT3 |Magnetic Particle Examination |
+---+-----------+-------------------------------------------+
|4) |UT2 |Ultrasonic Examination Of Butt Welds |
+---+-----------+-------------------------------------------+
|5) |UT4 |Straight Beam Ultrasonic Examination of |
| | |Rolled Steel Plates |
+---+-----------+-------------------------------------------+

2) RECORD NOT REQUIRED TO GENERATE FOR VISUAL INSPECTION AND


TACK WELD SOUNDNESS AS MENTIONED IN THIS ITP.

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P16
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
HEADERS (SHOP ASSLY) DATE : 04-11-2011
PAGE : 6

4.0 INSPECTION POINTS


INSPECTION POINTS ARE INDICATED BY :

SAUDI ARAMCO

R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS

cycle marked by the AI/Customer/TPI. Record of inspection is maintained


and will be made available to AI/Customer/TPI for review during next
HOLD/WITNESS stage Inspection,as applicable.

W Witness Point WITNESS POINT is defined as a notification operation in operation / production


cycle marked by the AI/Customer/TPI to excercise their option to witness
and verify a specific operation. Further processing shall proceed where the
AI/Customer/TPI do not validate their option. The notification shall be
documented in a manner acceptable to AI/Customer/TPI, as applicable.

H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.

- - Inspection option will not be exercised

5.0 RECORD OF REVISIONS :

REV NO. DATE CHANGES

PREPARED BY CHECKED BY APPROVED BY ACCEPTED BY CLIENT/CONSULTANT/TPI

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN)


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P17
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
ATTEMPERATOR ASSLY DATE : 02-06-2011
PAGE : 1

1.0 JOB SPECIFIC DATA : -

CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

CONSULTANT : - PROJECT NO:

INSP. AGENCY: DESIGN CODE :

2.0 QUALITY STAGES & INSPECTION :

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
CHARACTERISTICS METHOD EXTENT TL CLI

1 MATERIAL IDENTIFICATION H H

Review & Verification of Test Certificates & Drawing Review 100% Drawing, Material
Spec.

Correlation of MTC with Material Visual 100% Mill Test


Certificate

Dimensional Inspection Measurement 5% Drawing/Mill Test


Certificate

Identification & stamp transfer Visual 100% Punching/Stencilling

2 INSP.OF MACHINED COMPONENTS H R

Identification & verification of stamp transfer Visual 100% Drawing

Dimensional Inspection Measurement 100% Drawing

Weld Preparation Template 100% Drawing

Weld Edge Inspection Visual 100% No


Cracks/Laminations

3 INSPECTION OF MARKING FOR DRILLING ON HEADER PIPE H -

Identification & Orientaion Visual 100% Drawing

Marking Dimensions Measurement 100% Drawing

No.of Holes Count 100% Drawing

Straightness Measurement 90 Deg. 1mm/Mtr, Max.3mm


apart

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P17
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
ATTEMPERATOR ASSLY DATE : 02-06-2011
PAGE : 2

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

4 INSPECTION OF DRILLING & EDGE PREPERATION H R

Orientation Visual 100% Drawing

Dimensions Measurement 100% Drawing

No.of Holes Count 100% Drawing

Weld Preparation Template 100% Drawing

Quadrant Line Punching for Reference Visual 100% Drawing

Surface Defects Visual 100% No


Cracks/Laminations

5 BUTT WELD SETUPS-SPRAY NOZZLE H H

Setup Dimensions Measurement 100% Drawing

6 WELDING OF ABOVE H R

Visual Inspection Visual 100% Procedure VT

Weld Soundness RT 100% Procedure RT

Note:For P15E materials NDE to be carried after PWHT

7 SETUP OF STUBS/STAND PIPES WITH HEADER PIPE H H

Orientation Visual 100% Drawing

Setup Dimensions Measurement 100% Drawing

8 WELDING OF STUBS/STAND PIPES WITH HEADER PIPE H R

Weld Visual Inspection Visual 100% Procedure VT

Weld Size Measurement 100% Drawing

NDE of fillet welds PT/MT 100% Procedure PT/MT

Note:For P15E materials NDE to be carried after PWHT

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P17
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
ATTEMPERATOR ASSLY DATE : 02-06-2011
PAGE : 3

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

9 SETUP & WELDING OF SLEEVE LOCKING PINS H -

Setup Dimensions Measurement 100% Drawing

Weld Inspection after full welding Visual 100% Drawing & Procedure
VT

10 STRUCTURALS & ATTACHMENTS H -

Orientaion Visual 100% Drawing

Dimensions Measurement 100% Drawing

Weld Size & Finish Visual 100% Drawing & Procedure


VT

Weld Soundness PT 10% Procedure-PT

Welder Identification Verify 100% Qualified Welder


List

11 INSPECTION BEFORE PWHT H H

Overall Major Critical Dimensions Measurement 100% Drawing

NDE Clearance Review 100% NDE Procedure

PMI for Alloy Verification of accessible welds PMI Check 100% Procedure PMI /
Specs.

PMI for Alloy Verification of Parent Material PMI Check Random Procedure PMI /
Specs.

Note:For P15E materials PMI to be carried after PWHT

12 PWHT H R

Heat-Treatment Compliance to Code Review of 100% IBR-1950


HT chart

13 NDE AFTER PWHT H R

NDT on all welds for Alloy steel PT/MT 100% Procedure PT/MT

Straightness Measurement 100% 1 mm/Mtr; 6 mm max


(whichever is less)

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P17
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
ATTEMPERATOR ASSLY DATE : 02-06-2011
PAGE : 4

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

14 FINAL INSPECTION H H

Identification & Orientation Visual 100% Drawing

Site Weld Preperation Visual 100% Drawing

Cleaning of header from inside before capping Air blowing 100% free from foreign
material

I.A.Stamp & Date, (As Applicable) Final 100% IBR-1950


Rub-off

Document review Review 100% Compillation of


stage IR's & MTC's,
Code

15 PAINTING INSPECTION H -

Surface Preparation Visual 100% Drawing, Painting


Specs.

Drawing, Painting Specs. Visual 100% Drawing, Painting


Specs.

Visual Inspection after painting Visual 100% Complete coverage of


area, No rundowns,
Peel-offs, Cracks

Paint-DFT Measurement Random Drawing, Painting


Specs.

Cleaning from inside before capping Air blowing 100% Free from foreign
material

Capping / Blanking of all Tubes, Pipes, Openings Visual 100% All Tubes, Pipes,
Openings Shall be Co
vered /Capped

Identification Marking Visual 100% Drawing

16 INSPECTION RELEASE NOTE H -

Final Document Review Review 100% Drawing, Compilation


of document

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P17
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
ATTEMPERATOR ASSLY DATE : 02-06-2011
PAGE : 5

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

Inspection Release Note Issuance of


IRN

3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.

1. WPS,PQR,WPQ and Welding Technology sheet(WTS)


2. Material Test Certificates
3. Manufacturing Records
4. All the required Inspection Records.

Following Documents shall be referred for this QAP (As Applicable) :

1) NDE Procedures

+---+-----------+-------------------------------------------+
|Sr.|Control No.|Procedure Description |
+---+-----------+-------------------------------------------+
|1) |RT12 |Radiographic Examination of Welded Joints |
+---+-----------+-------------------------------------------+
|2) |PT1 |Liquid Penetrant Examination |
+---+-----------+-------------------------------------------+
|3) |MT3 |Magnetic Particle Examination |
+---+-----------+-------------------------------------------+
|4) |UT2 |Ultrasonic Examination Of Butt Welds |
+---+-----------+-------------------------------------------+
|5) |UT4 |Straight Beam Ultrasonic Examination of |
| | |Rolled Steel Plates |
+---+-----------+-------------------------------------------+

2) RECORD NOT REQUIRED TO GENERATE FOR VISUAL INSPECTION AND


TACK WELD SOUNDNESS AS MENTIONED IN THIS ITP.

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P17
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
ATTEMPERATOR ASSLY DATE : 02-06-2011
PAGE : 6

4.0 INSPECTION POINTS


INSPECTION POINTS ARE INDICATED BY :

SAUDI ARAMCO

R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS

cycle marked by the AI/Customer/TPI. Record of inspection is maintained


and will be made available to AI/Customer/TPI for review during next
HOLD/WITNESS stage Inspection,as applicable.

W Witness Point WITNESS POINT is defined as a notification operation in operation / production


cycle marked by the AI/Customer/TPI to excercise their option to witness
and verify a specific operation. Further processing shall proceed where the
AI/Customer/TPI do not validate their option. The notification shall be
documented in a manner acceptable to AI/Customer/TPI, as applicable.

H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.

- - Inspection option will not be exercised

5.0 RECORD OF REVISIONS :

REV NO. DATE CHANGES

PREPARED BY CHECKED BY APPROVED BY ACCEPTED BY CLIENT/CONSULTANT/TPI

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN)


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P20
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
INTEGRAL& NON INTEGRAL PIPING - IBR DATE : 02-06-2011
PAGE : 1

1.0 JOB SPECIFIC DATA : -

CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

CONSULTANT : - PROJECT NO:

INSP. AGENCY: DESIGN CODE :

2.0 QUALITY STAGES & INSPECTION :

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
CHARACTERISTICS METHOD EXTENT TL CLI

1 MATERIAL IDENTIFICATION H H

Verification of MTC with Material Specs. & Drg Review 100% Drg / Matrl.Specs.

Correlation of MTC with Material Verify 100% TC

Dimensions Measurement 5% Drawing/TC

Hydrotest/NDE of Pipes at Makers Works Review 100% Drawing/TC

Identification & Stamp Transfer Visual 100% IA Stamp

2 INSPECTION OF SAMPLE/FIRST PRODUCTION BEND H R

Layout Inspection Measurement 100% Drawing


& Visual

Dimensions on Layout Layout 100% Within 3mm


Matching

Ovality of Tubes Measurement 100% Within 10%

Thinning of Tubes Measurement 100% Drawing,


100/(4R/D+2) Max.

Surface defects, Die Marks Visual 100% 0.5 mm (deep) max.


without sharp notche
s

Cracks, Wrinkles Visual 100% No Cracks, Wrinkles

3 INSPECTION OF TUBES AFTER BENDING H W

Layout Inspection Measurement 100% Drawing


& Visual

Dimensions on Layout Layout 5% Within 3mm

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P20
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
INTEGRAL& NON INTEGRAL PIPING - IBR DATE : 02-06-2011
PAGE : 2

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

Matching

Ovality of Tubes Measurement 5% Within 10%

Thinning of Tubes Measurement 5% Drawing,


100/(4R/D+2) Max.

Surface defects, Die Marks Visual 100% 0.5 mm deep max


without sharp notche
s

Cracks, Wrinkles Visual 100% No Cracks, Wrinkles

4 BUTT WELDS(PIPE TO PIPE,PIPE TO FLANGES/FITTINGS) H H

Identification & Orientation Visual 100% Drawing

Setup Dimensions Measurement 10% Drawing

Tackweld Soundness by PT except for P15E Material PT 100% Procedure/Code

5 WELDING OF BUTT JOINTS H R

Weld Inspection Visual 100% Procedure VT

Weld Soundness for size > 178mm OD RT 100% Procedure RT

Weld Soundness for size >102mm OD & <=178 mm OD RT 10% Procedure RT

Weld Soundness for size <=102mm OD RT 5% ** Procedure RT

** 5% per welder

Note :NDE for P15E materials to be carried after PWHT.

6 SETUP & WELDING OF SOCKET WELDS & OTHER BRANCH WELDS H H

Orientation Visual 100% Drawing

Setup Dimensions & Locations Visual 100% Drawing

Weld Visual Inspection Visual 100% Procedure VT

UT of Full penetration welds >=10 NPS or above 25 thk UT/RT 100% Procedure UT/RT

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P20
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
INTEGRAL& NON INTEGRAL PIPING - IBR DATE : 02-06-2011
PAGE : 3

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLIWELDING PROCEDURE SPECIFICATIONS

7 CLEARANCE FOR PWHT (IF APPLICABLE) H -

Overall Major Critical Dimensions Measurement 100% Drawing

Completion of all Welding Verify 100% Drawing

NDE Clearance Verify 100% Design Code

PMI for Alloy Verification of welds PMI Check 10% Random Procedure PMI/ Spec.

PMI for Alloy Verification of Parent Material PMI Check Random Procedure PMI/ Spec.

Note :PMI for P15E materials to be carried after PWHT.

8 PWHT (IF APPLICABLE) H R

Heat-Treatment Compliance to Code Review of 100% Design Code +


HT chart Thermax std.

9 NDE AFTER PWHT H -

PT on all alloy steel welds PT 100% Procedure PT

Weld Soundness of butt welds for 15E Materials RT 100% Procedure RT

10 FINAL INSPECTION H H

Compliance to Drawing for Scope Verify 100% Drawing-BOM

Overall Major Critical Dimensions Measurement 100% Drawing

Code Punching,(As Applicable) Visual 100% Design Code

I.A.Stamp & Date,(As Applicable) Rub-off 100% Design Code

Document review Review 100% Compillation of


stage IR's & MTC's,
Code

11 PAINTING INSPECTION H -

Surface Preparation . Visual 100% Drawing, Painting


Specs.

Site weld joints to be kept unpainted @1" portion Visual 100% Apply Packing tape
or Cap the ends afte

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P20
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
INTEGRAL& NON INTEGRAL PIPING - IBR DATE : 02-06-2011
PAGE : 4

SR. INSPECTION STAGES ACCEPTANCE * INSP. BY


NO. STANDARD
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT TL IBR CLI


WELDING PROCEDURE SPECIFICATIONS

r greasing

Drawing, Painting Specs. Visual 100% Drawing, Painting


Specs.

Visual Inspection after painting Visual 100% Complete coverage of


area, No rundowns,
Peel-offs, Cracks

Paint-DFT Measurement Random Drawing, Painting


Specs.

Cleaning from inside before capping/blanking Air blowing 100% Free from foreign
material

Capping / Blanking of all Pipes, Openings Visual 100% All Pipes, Openings
Shall be Covered /Ca
pped

Identification Marking Visual 100% Drawing

12 INSPECTION RELEASE NOTE H -

Final Document Review Review 100% Drawing, Compilation


of document

Inspection Release Note Issuance of


IRN

3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.

1. WPS,PQR,WPQ and Welding Technology sheet(WTS)


2. Material Test Certificates
3. Manufacturing Records
4. All the required Inspection Records.

Following Documents shall be referred for this QAP (As Applicable) :

1) NDE Procedures

+---+-----------+-------------------------------------------+
|Sr.|Control No.|Procedure Description |

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN)


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P20
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
INTEGRAL& NON INTEGRAL PIPING - IBR DATE : 02-06-2011
PAGE : 5

+---+-----------+-------------------------------------------+
|1) |RT12 |Radiographic Examination of Welded Joints |
+---+-----------+-------------------------------------------+
SAUDI ARAMCO

|2) |PT1 |Liquid Penetrant Examination | WELDING PROCEDURE SPECIFICATIONS

+---+-----------+-------------------------------------------+
|3) |MT3 |Magnetic Particle Examination |
+---+-----------+-------------------------------------------+
|4) |UT2 |Ultrasonic Examination Of Butt Welds |
+---+-----------+-------------------------------------------+
|5) |UT4 |Straight Beam Ultrasonic Examination of |
| | |Rolled Steel Plates |
+---+-----------+-------------------------------------------+

2) RECORD NOT REQUIRED TO GENERATE FOR VISUAL INSPECTION AND


TACK WELD SOUNDNESS AS MENTIONED IN THIS ITP.

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN)


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P20
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
INTEGRAL& NON INTEGRAL PIPING - IBR DATE : 02-06-2011
PAGE : 6

4.0 INSPECTION POINTS


INSPECTION POINTS ARE INDICATED BY :

SAUDI ARAMCO

R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS

cycle marked by the AI/Customer/TPI. Record of inspection is maintained


and will be made available to AI/Customer/TPI for review during next
HOLD/WITNESS stage Inspection,as applicable.

W Witness Point WITNESS POINT is defined as a notification operation in operation / production


cycle marked by the AI/Customer/TPI to excercise their option to witness
and verify a specific operation. Further processing shall proceed where the
AI/Customer/TPI do not validate their option. The notification shall be
documented in a manner acceptable to AI/Customer/TPI, as applicable.

H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.

- - Inspection option will not be exercised

5.0 RECORD OF REVISIONS :

REV NO. DATE CHANGES

PREPARED BY CHECKED BY APPROVED BY ACCEPTED BY CLIENT/CONSULTANT/TPI

*INSP.BY IBR -IBR CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN)


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPASME /P21
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
NON-INTEGRAL PIPING DATE : 16-06-2011
PAGE : 1

1.0 JOB SPECIFIC DATA :

CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

CONSULTANT : - PROJECT NO:

INSP. AGENCY: DESIGN CODE :

2.0 QUALITY STAGES & INSPECTION :

SR. INSPECTION STAGES ACCEPTANCE STANDARD * INSP. BY


NO.
CHARACTERISTICS METHOD EXTENT REF.DOC./ PROCEDURE TL CLI

1 MATERIAL IDENTIFICATION H

Verification of MTC with Material Specs. & Drg Review 100% Drg / Matrl.Specs.

Correlation of MTC with Material Verify 100% TC

Dimensions Measurement 5% Drawing/TC

Hydrotest/NDE of Pipes at Makers Works Review 100% Drawing/TC

Identification & Stamp Transfer Visual 100% IA Stamp

2 BUTT WELDS(PIPE TO PIPE,PIPE TO FLANGES/FITTINGS) H

Identification & Orientation Visual 100% Drawing

Setup Dimensions Measurement 10% Drawing

Tackweld Soundness by PT except for P15E Material PT 100% Procedure/Code

3 WELDING OF BUTT JOINTS H

Welder ID Verify 100% Qualified Welder


List

Weld Inspection Visual 100% Drawing ,code

Weld Soundness RT code or ** Procedure RT12

Minimum 5% per Welder

PMI for Alloy Verification of welds PMI Check 10% Random Procedure PMI

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPASME /P21
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
NON-INTEGRAL PIPING DATE : 16-06-2011
PAGE : 2

SR. INSPECTION STAGES ACCEPTANCE STANDARD * INSP. BY


NO.
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT REF.DOC./ PROCEDURE TL CLI


WELDING PROCEDURE SPECIFICATIONS

4 SETUP & WELDING OF SOCKET WELDS & OTHER BRANCH WELDS H

Orientation Visual 100% Drawing

Setup Dimensions & Locations Visual 100% Drawing

Weld Visual Inspection Visual 100% Procedure VT

UT of Full penetration welds >=10 NPS or above 25 thk UT 100% Procedure UT

5 CLEARANCE FOR PWHT (IF APPLICABLE) H

Overall Major Critical Dimensions Measurement 100% Drawing

Completion of all Welding Verify 100% Drawing

NDE Clearance Verify 100% Design Code

PMI for Alloy Verification of welds PMI Check 10% Random Procedure PMI/ Spec.

PMI for Alloy Verification of Parent Material PMI Check Random Procedure PMI/ Spec.

Note :PMI for P15E materials to be carried after PWHT.

6 PWHT (IF APPLICABLE) H

Heat-Treatment Compliance Review of 100% PWHT Procedure


HT chart

7 NDE AFTER PWHT H

Weld Visual inspection Visual 100% Procedure VT,

PT/MT on all accessible alloy steel welds PT/MT 100% Procedure PT1/MT3

Weld soundness of Butt welds for P-Nos 3,4,5 materials if - RT Code ASME B31.3 Para
341.3

-required as per code

Hardness of production weld,hot bend & hot formed piping- Test Code ASME B31.3 para
331.1.7

-For P-Nos 3,4,5 materials

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPASME /P21
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
NON-INTEGRAL PIPING DATE : 16-06-2011
PAGE : 3

SR. INSPECTION STAGES ACCEPTANCE STANDARD * INSP. BY


NO.
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT REF.DOC./ PROCEDURE TL CLI


WELDING PROCEDURE SPECIFICATIONS

8 FINAL INSPECTION BEFORE PAINTING H

Compliance to Drawing for Scope Verify 100% Drawing-BOM

Visual Inspection Visual 100% Procedure VT

Identification Marking (Job no.,Drg.no.,Part no.) Visual 100% Drawing

9 PAINTING INSPECTION H

Surface Preparation for Painting Visual 100% Drawing/Specs.

Paint Shade, Make, Batch No., Expiry Date Visual 100% Drawing, Painting
Specs.,Application b
efore Expiry

Visual Inspection after painting Visual 100% Complete coverage of


area, No rundowns,
Peel-offs, Cracks

Paint-DFT Measurement Random Drawing/ Painting


Specs.

Identification Marking (Job no.,Drg.no.,Part no.) Visual 100% Drawing

10 INSPECTION RELEASE NOTE H

Final Document Review Review 100% Drawing, Compilation


of document

Inspection Release Note Issuance of


IRN

3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.

1. WPS,PQR,WPQ and Welding Technology sheet(WTS)


2. Material Test Certificates
3. Manufacturing Records
4. All the required Inspection Records.

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN)


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPASME /P21
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
NON-INTEGRAL PIPING DATE : 16-06-2011
PAGE : 4

4.0 INSPECTION POINTS


INSPECTION POINTS ARE INDICATED BY :

SAUDI ARAMCO

R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS

cycle marked by the AI/Customer/TPI. Record of inspection is maintained


and will be made available to AI/Customer/TPI for review during next
HOLD/WITNESS stage Inspection,as applicable.

W Witness Point WITNESS POINT is defined as a notification operation in operation / production


cycle marked by the AI/Customer/TPI to excercise their option to witness
and verify a specific operation. Further processing shall proceed where the
AI/Customer/TPI do not validate their option. The notification shall be
documented in a manner acceptable to AI/Customer/TPI, as applicable.

H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.

- - Inspection option will not be exercised

5.0 RECORD OF REVISIONS :

REV NO. DATE CHANGES

PREPARED BY CHECKED BY APPROVED BY ACCEPTED BY CLIENT/CONSULTANT/TPI

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN)


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N01
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
DUCTS / HOPPERS DATE : 28-07-2011
PAGE : 1

1.0 JOB SPECIFIC DATA : -

CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

CONSULTANT : - PROJECT NO:

INSP. AGENCY: DESIGN CODE :

2.0 QUALITY STAGES & INSPECTION :

SR. INSPECTION STAGES ACCEPTANCE STANDARD * INSP. BY


NO.
CHARACTERISTICS METHOD EXTENT REF.DOC./ PROCEDURE TL CLI

1 MATERIAL IDENTIFICATION H -

Material Specification Review 100% Drawing

Verification of Specification Review 100% MTC/Code

Check Test, if no MTC Check_Test As per Material Specs.


Code/ Spe

Dimensions Measurement 10% Drawing/Code

Surface Condition Visual 100% Free From Surface


Defects

2 FINAL INSPECTION OF PRE-FABRICATED PANELS(CORNER WELDING AT SITE) H -

Compliance to Drawing for Scope Verify 100% Drawing-BOM

Orientation Visual 100% Drawing

Overall Dimensions Measurement 100% Drawing

Match Marking Visual 100% Drawing

Weld Inspection (Size & Finish) Visual 100% Drawing

Site Weld Preperation Visual 100% Drawing

Distortion / Flatness Measurement 100% Within 5mm


& Visual

3 FINAL INSPECTION AFTER WELDING (FULLY SHOP WELDED) H -

Orientation Visual 100% Drawing

Overall Dimensions Measurement 100% Drawing

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N01
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
DUCTS / HOPPERS DATE : 28-07-2011
PAGE : 2

SR. INSPECTION STAGES ACCEPTANCE STANDARD * INSP. BY


NO.
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT REF.DOC./ PROCEDURE TL CLI


WELDING PROCEDURE SPECIFICATIONS

Ovality of round ducts Measurement 100% Within 1% & 10mm


max.

Compliance to Drawing for Scope Verify 100% Drawing-BOM

Completion of stiffner/ spider Welding (As applicable) Visual 100% Drawing/ Suitable
for Handling

Weld Inspection (Size & Finish) Visual 100% Drawing & Procedure
VT

Site Weld Preperation Visual 100% Drawing

Match Marking Visual 100% Drawing

Aesthetics-Weld tacks,Hammer/Dent/Surface Marks,Sharp Corner Visual 100% Free from Surface


Discontinuities

4 SURFACE PREPARATION H -

Surface Preparation for Painting Visual 100% Drawing/Specs.

5 PAINTING INSPECTION H -

Paint Shade, Make, Batch No., Expiry Date Verify 100% Drawing, Painting
Specs., Application
before Expiry

Visual Inspection after painting Visual 100% Complete coverage of


area, No rundowns,
Peel-offs, Cracks

Paint-DFT Measurement 2Spots/m2 Drawing/ Painting


Specs.

Centreline/ Match marking Visual 100% Drawing

Identification Marking (Job no.,Drg.no.,Part no., Weight*) Visual 100% Drawing

*- Marking of Weight on Item or DU Weighing >= 500kg. Visual

6 INSPECTION RELEASE NOTE H -

Final Document Review Review 100% Drawing, Compilation


of document

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N01
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
DUCTS / HOPPERS DATE : 28-07-2011
PAGE : 3

SR. INSPECTION STAGES ACCEPTANCE STANDARD * INSP. BY


NO.
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT REF.DOC./ PROCEDURE TL CLI


WELDING PROCEDURE SPECIFICATIONS

Inspection Release Note Issuance of


IRN

3.0 NOTES :
IT IS MANDATORY FOR MANUFACTURER'S QUALITY CONTROL TO CARRY OUT
INSPECTION OF ALL THE STAGES COVERED IN THIS ITP.

4.0 INSPECTION POINTS


INSPECTION POINTS ARE INDICATED BY :

R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production
cycle marked by the AI/Customer/TPI. Record of inspection is maintained
and will be made available to AI/Customer/TPI for review during next
HOLD/WITNESS stage Inspection,as applicable.

W Witness Point WITNESS POINT is defined as a notification operation in operation / production


cycle marked by the AI/Customer/TPI to excercise their option to witness
and verify a specific operation. Further processing shall proceed where the
AI/Customer/TPI do not validate their option. The notification shall be
documented in a manner acceptable to AI/Customer/TPI, as applicable.

H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.

- - Inspection option will not be exercised

5.0 RECORD OF REVISIONS :

REV NO. DATE CHANGES

PREPARED BY CHECKED BY APPROVED BY ACCEPTED BY CLIENT/CONSULTANT/TPI

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN)


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N02
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
DAMPER DATE : 28-07-2011
PAGE : 1

1.0 JOB SPECIFIC DATA : -

CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

CONSULTANT : - PROJECT NO:

INSP. AGENCY: - ---

2.0 QUALITY STAGES & INSPECTION :

SR. INSPECTION STAGES ACCEPTANCE STANDARD * INSP. BY


NO.
CHARACTERISTICS METHOD EXTENT REF.DOC./ PROCEDURE TL CLI

1 MATERIAL IDENTIFICATION H

Material Specification Review 100% Drawing

Verification of Specification Review 100% MTC/Code

Check Test, if no MTC Chem.&Mech. 1 Sample/ Material Specs.


Test Lot

Dimensions Measurement 10% Drawing/Code

Surface Condition Visual 100% Free From Surface


Defects

2 FINAL INSPECTION BEFORE PAINTING H

Orientation Visual 100% Drawing

Overall Assembly Dimensions Measurement 100% Drawing

Completion of all Welding Verify 100% Drawing

Weld Inspection Visual 100% Drawing

Open/Close Operation Verify 100% Drawing/Specs.

Compliance to Drawing to Scope Verify 100% Drawing-BOM

Aesthetics-Weld tacks,Hammer/Dent/Surface Marks,Sharp Corner Visual 100% Free from Surface


Discontinuities

3 PAINTING INSPECTION H

Surface Preparation for Painting Visual 100% Drawing/Specs.

Paint Shade, Make, Batch No., Expiry Date Visual 100% Drawing, Painting
Specs., Application

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N02
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
DAMPER DATE : 28-07-2011
PAGE : 2

SR. INSPECTION STAGES ACCEPTANCE STANDARD * INSP. BY


NO.
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT REF.DOC./ PROCEDURE TL CLI


WELDING PROCEDURE SPECIFICATIONS

Before Painting

Visual Inspection after painting Visual 100% Complete coverage of


area, No rundowns,
Peel-offs, Cracks

Paint-DFT Measurement 2Spots/pc Drawing/ Painting


Specs.

Centreline Marking Visual 100% Drawing

Identification Marking (Job no., Drg.no.,Part no.) Visual 100% Drawing

Open/Close Marking Visual 100% Drawing

4 INSPECTION RELEASE NOTE H

Final Document Review Review 100% Drawing, Technical


Specifications

Inspection Release & Certification Issuance of 100% Drawing, Technical


IRN Specifications

3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.

1. WPS,PQR,WPQ and Welding Technology sheet(WTS)


2. Material Test Certificates
3. Manufacturing Records
4. All the required Inspection Records.

IT IS MANDATORY FOR MANUFACTURER'S QUALITY CONTROL TO CARRY OUT


INSPECTION OF ALL THE STAGES COVERED IN THIS ITP.

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N02
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
DAMPER DATE : 28-07-2011
PAGE : 3

4.0 INSPECTION POINTS


INSPECTION POINTS ARE INDICATED BY :

SAUDI ARAMCO

R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS

cycle marked by the AI/Customer/TPI. Record of inspection is maintained


and will be made available to AI/Customer/TPI for review during next
HOLD/WITNESS stage Inspection,as applicable.

W Witness Point WITNESS POINT is defined as a notification operation in operation / production


cycle marked by the AI/Customer/TPI to excercise their option to witness
and verify a specific operation. Further processing shall proceed where the
AI/Customer/TPI do not validate their option. The notification shall be
documented in a manner acceptable to AI/Customer/TPI, as applicable.

H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.

- - Inspection option will not be exercised

5.0 RECORD OF REVISIONS :

REV NO. DATE CHANGES

PREPARED BY CHECKED BY APPROVED BY ACCEPTED BY CLIENT/CONSULTANT/TPI

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN)


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N03
SAUDI ARAMCO
REVISION NO.: 1
WELDING PROCEDURE SPECIFIC
EXPANSION JOINTS DATE : 22-10-2011
PAGE : 1

1.0 JOB SPECIFIC DATA : -

CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

CONSULTANT : - PROJECT NO:

INSP. AGENCY: - ---

2.0 QUALITY STAGES & INSPECTION :

SR. INSPECTION STAGES ACCEPTANCE STANDARD * INSP. BY


NO.
CHARACTERISTICS METHOD EXTENT REF.DOC./ PROCEDURE TL CLI

1 MATERIAL IDENTIFICATION H

Material Specification Review 100% Drawing

Verification of Specification Review 100% MTC/Code

Check Test, if no MTC Check_Test As per Material Specs.


Specs.

Dimensions Measurement 10% Drawing/Code

Surface Condition Visual 100% Free From Surface


Defects

2 INSPECTION OF EXPANSION BELLOW H

Bellow Profile Template 100% Drawing

Welding by GTAW Process for sheet thk <= 2mm Visual 100% Weld
procedure/specs.

Alignment of Flanges Measurement 100% Drawing

Flange I/S Dimensions, Hole Pitches, Height, Diagonals Measurement 100% Drawing

Weld Soundness Kerosene/PT 100% Procedure


/Air Leak T

3 FINAL INSPECTION BEFORE PAINTING H

Location & Dimensions of Shear Transfer Pin Arrangement Measurement 100% Drawing
& Visual

Free Movement of Floating Plate Visual 100% Free Movement

Expansion Provision Dimensions Measurement 100% Drawing

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N03
SAUDI ARAMCO
REVISION NO.: 1
WELDING PROCEDURE SPECIFIC
EXPANSION JOINTS DATE : 22-10-2011
PAGE : 2

SR. INSPECTION STAGES ACCEPTANCE STANDARD * INSP. BY


NO.
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT REF.DOC./ PROCEDURE TL CLI


WELDING PROCEDURE SPECIFICATIONS

Weld Inspection (Size & Finish) Visual 100% Drawing

Compliance to Drawing for Scope Verify 100% Drawing-BOM

4 PAINTING INSPECTION H

Surface Preparation for Painting Visual 100% Drawing/Specs.

Paint Shade, Make, Batch No., Expiry Date Visual 100% Drawing, Painting
Specs.,Application b
efore Expiry

Visual Inspection after painting Visual 100% Complete coverage of


area, No rundowns,
Peel-offs, Cracks

Paint-DFT Measurement 2Spots/m2 Drawing/ Painting


Specs.

Identification Marking(Job no.,Drg.no.,Part no.) Visual 100% Drawing

Flow Direction Marking by Arrow Visual 100% Drawing

5 INSPECTION RELEASE NOTE H

Final Document Review Review 100% Drawing, Technical


Specifications

Inspection Release & Certification Issuance of 100% Drawing, Technical


IRN Specifications

3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.

1. WPS,PQR,WPQ and Welding Technology sheet(WTS)


2. Material Test Certificates
3. Manufacturing Records
4. All the required Inspection Records.

IT IS MANDATORY FOR MANUFACTURER'S QUALITY CONTROL TO CARRY OUT


INSPECTION OF ALL THE STAGES COVERED IN THIS ITP.

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N03
SAUDI ARAMCO
REVISION NO.: 1
WELDING PROCEDURE SPECIFIC
EXPANSION JOINTS DATE : 22-10-2011
PAGE : 3

4.0 INSPECTION POINTS


INSPECTION POINTS ARE INDICATED BY :

SAUDI ARAMCO

R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS

cycle marked by the AI/Customer/TPI. Record of inspection is maintained


and will be made available to AI/Customer/TPI for review during next
HOLD/WITNESS stage Inspection,as applicable.

W Witness Point WITNESS POINT is defined as a notification operation in operation / production


cycle marked by the AI/Customer/TPI to excercise their option to witness
and verify a specific operation. Further processing shall proceed where the
AI/Customer/TPI do not validate their option. The notification shall be
documented in a manner acceptable to AI/Customer/TPI, as applicable.

H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.

- - Inspection option will not be exercised

5.0 RECORD OF REVISIONS :

REV NO. DATE CHANGES

PREPARED BY CHECKED BY APPROVED BY ACCEPTED BY CLIENT/CONSULTANT/TPI

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN)


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N04
SAUDI ARAMCO
REVISION NO.: 1
WELDING PROCEDURE SPECIFIC
AIR FLOW MEASURING DEVICE (AEROFOIL) DATE : 22-10-2011
PAGE : 1

1.0 JOB SPECIFIC DATA : -

CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

CONSULTANT : - PROJECT NO:

INSP. AGENCY: - ---

2.0 QUALITY STAGES & INSPECTION :

SR. INSPECTION STAGES ACCEPTANCE STANDARD * INSP. BY


NO.
CHARACTERISTICS METHOD EXTENT REF.DOC./ PROCEDURE TL CLI

1 MATERIAL IDENTIFICATION H

Material Specification Review 100% Drawing

Verification of Specification Review 100% MTC/Code

Check Test, if no MTC Check_Test As per Material Specs.


Spces.

Dimensions Measurement 10% Drawing/Code

Surface Condition Visual 100% Free From Surface


Defects

2 INSP.OF AIR FOIL H

Dimensions Measurement 100% Drawing

Profile Template 100% Avg.Gap 2mm

Air Hole Location Measurement 100% Drawing

3 ASSEMBLY INSPECTION H

Overall Dimensions Measurement 100% Drawing

Throat Size Measurement 100% Drawing

Orientation & Fitment of Air Piping Measurement 100% Drawing


& Visual

Blocking of Air Piping Air Blowing 100% No Blocking

Completion of all Welding Verify 100% Drawing

Weld Inspection (Size & Finish) Visual 100% Drawing

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N04
SAUDI ARAMCO
REVISION NO.: 1
WELDING PROCEDURE SPECIFIC
AIR FLOW MEASURING DEVICE (AEROFOIL) DATE : 22-10-2011
PAGE : 2

SR. INSPECTION STAGES ACCEPTANCE STANDARD * INSP. BY


NO.
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT REF.DOC./ PROCEDURE TL CLI


WELDING PROCEDURE SPECIFICATIONS

4 PAINTING & FINAL INSPECTION H

Compliance to Drawing for Scope Verify 100% Drawing-BOM

Surface Preparation for Painting Visual 100% Drawing/Specs.

Paint Shade, Make, Batch No., Expiry Date Visual 100% Drawing, Painting
Specs.,Application b
efore Expiry

Visual Inspection after painting Visual 100% Complete coverage of


area, No rundowns,
Peel-offs, Cracks

Paint-DFT Measurement 2Spots/m2 Drawing/ Painting


Specs.

Centreline Marking Visual 100% Drawing

Identification Marking (Job no.,Drg.no.,Part no.) Visual 100% Drawing

5 INSPECTION RELEASE NOTE H

Final Document Review Review 100% Drawing, Technical


Specifications

Inspection Release & Certification Issuance of 100% Drawing, Technical


IRN Specifications

3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.

1. WPS,PQR,WPQ and Welding Technology sheet(WTS)


2. Material Test Certificates
3. Manufacturing Records
4. All the required Inspection Records.

IT IS MANDATORY FOR MANUFACTURER'S QUALITY CONTROL TO CARRY OUT


INSPECTION OF ALL THE STAGES COVERED IN THIS ITP.

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N04
SAUDI ARAMCO
REVISION NO.: 1
WELDING PROCEDURE SPECIFIC
AIR FLOW MEASURING DEVICE (AEROFOIL) DATE : 22-10-2011
PAGE : 3

4.0 INSPECTION POINTS


INSPECTION POINTS ARE INDICATED BY :

SAUDI ARAMCO

R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS

cycle marked by the AI/Customer/TPI. Record of inspection is maintained


and will be made available to AI/Customer/TPI for review during next
HOLD/WITNESS stage Inspection,as applicable.

W Witness Point WITNESS POINT is defined as a notification operation in operation / production


cycle marked by the AI/Customer/TPI to excercise their option to witness
and verify a specific operation. Further processing shall proceed where the
AI/Customer/TPI do not validate their option. The notification shall be
documented in a manner acceptable to AI/Customer/TPI, as applicable.

H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.

- - Inspection option will not be exercised

5.0 RECORD OF REVISIONS :

REV NO. DATE CHANGES

PREPARED BY CHECKED BY APPROVED BY ACCEPTED BY CLIENT/CONSULTANT/TPI

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN)


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N05
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
STACK DATE : 28-07-2011
PAGE : 1

1.0 JOB SPECIFIC DATA : -

CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

CONSULTANT : - PROJECT NO:

INSP. AGENCY: - ---

2.0 QUALITY STAGES & INSPECTION :

SR. INSPECTION STAGES ACCEPTANCE STANDARD * INSP. BY


NO.
CHARACTERISTICS METHOD EXTENT REF.DOC./ PROCEDURE TL CLI

1 MATERIAL IDENTIFICATION H

Material Specification Review 100% Drawing

Verification of MTC Review 100% MTC/Code

Check Test, if no MTC Check_Test As per Material Specs.


Specs.

Dimensions Measurement 10% Drawing/Code

Surface Condition Visual 100% Free From Surface


Defects

2 INSP.OF STACK TEMPLATE H

Butt Weld Dimensions of Sectors Measurement 100% Drawing

Dimensions-Thickness, ID,OD,PCD, Hole Equispacing Measurement 100% Drawing

No.of Holes Count 100% Drawing

Hole size & pitch Measurement 100% Drawing

Weld Inspection Visual 100% Drawing

Match Drilling Verify 100% Drawing

Identification/Match marking Verify 100% Drawing,Refer note

3 INSP.OF BASE RING H

Butt Weld Dimensions of Sectors Measurement 100% Drawing

Dimensions-Thickness, ID,OD,PCD, Hole Equispacing Measurement 100% Drawing

No.of Holes Count 100% Drawing

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N05
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
STACK DATE : 28-07-2011
PAGE : 2

SR. INSPECTION STAGES ACCEPTANCE STANDARD * INSP. BY


NO.
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT REF.DOC./ PROCEDURE TL CLI


WELDING PROCEDURE SPECIFICATIONS

Hole size & pitch Measurement 100% Drawing

Backgauging after first side welding PT 100% Procedure PT

Weld Inspection Visual 100% Drawing

Weld Soundness RT 100% Procedure RT

Match Drilling of Base Ring with Template Verify 100% Drawing,Refer Note

4 SETUP OF L-SEAMS H

Setup Dimensions Measurement 100% Drawing

Dimensions-OD, Ovality, Circulary & Mismatch, Height Measurement 100% Drawing

Backgauging after first side Welding PT 100% Procedure PT

5 SETUP OF C-SEAMS H

Mismatch & Alignment of Shells Measurement 100% Drawing

Setup Dimensions Measurement 100% Drawing

Backgauging after first side Welding PT 100% Procedure PT

6 FULL WELDING OF SHELL SEAMS H

Weld Inspection (Size & Finish) Visual & 100% Drawing


Measureme

Weld Soundness on all T-Joints RT T-joints Procedure RT

Weld Soundness of L-Seam RT 10% Procedure RT

UT of shell plate at Lifting Lug Locations UT 100% Drawing,Free from


Lamination

7 STRUCTURALS & ATTACHMENTS H

Identification & Orientaion Visual 100% Drawing

Dimensional Inspection Measurement 100% Drawing

Weld Inspection Visual 100% Drawing

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N05
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
STACK DATE : 28-07-2011
PAGE : 3

SR. INSPECTION STAGES ACCEPTANCE STANDARD * INSP. BY


NO.
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT REF.DOC./ PROCEDURE TL CLI


WELDING PROCEDURE SPECIFICATIONS

UT of shell plate at Lifting Lug Locations ** UT 100% Drawing,Free from


Lamination

**If not covered earlier

8 ALIGNMENT OF STACK SHELLS (2 ADJACENT SHELLS) H

Levelling of Shells Water Level 100% 1mm/Meter or 10 mm


whichever is less

Base Ring Squareness with respect to Shell Plumb 100% Within 3mm

Shell to Shell Matching/Mismatch (at 120 deg.apart) Measurement 100% Drawing


& Visual

Overall Length,Continuity of Monkey Ladder&Wind Breaker Measurement 100% Drawing


& Visual

Straightness Measurement 100% 1mm/Mtr, 10mm Max.

Identification & Match Marking Visual 100% Drawing

Completion of all Welding Verify 100% Drawing

9 MOCK-UP ASSLY OF PLATFORM & LADDER H

Assly of Platform & Ladders on Stack for bolted construction Verify 100% Drawing

Assly of Platform&Ladders on ground for welded construction Verify 100% Drawing

Painters Trolly Verify 100% Free Movement

10 FINAL INSPECTION BEFORE PAINTING H

Anchor Pitch & Orientation Measurement 100% Drawing


& Visual

Anchor Weld soundness Hammer Test Random No Breakages

Compliance to drawing for scope Verify 100% Drawing-BOM

Identification Marking Visual 100% Drawing

Aesthetics-Weld tacks,Hammer/Dent/Surface Marks,Sharp Corner Visual 100% Free from Surface


Discontinuities

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N05
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
STACK DATE : 28-07-2011
PAGE : 4

SR. INSPECTION STAGES ACCEPTANCE STANDARD * INSP. BY


NO.
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT REF.DOC./ PROCEDURE TL CLI


WELDING PROCEDURE SPECIFICATIONS

11 PAINTING INSPECTION H

Surface Preparation for Painting Visual 100% Drawing/Specs.

Paint Shade, Make, Batch No., Expiry Date Visual 100% Drawing, Painting
Specs., Application
before Expiry

Visual Inspection after painting Visual 100% Complete coverage of


area, No rundowns,
Peel-offs, Cracks

Paint-DFT Measurement Min.2Spot / Drawing/ Painting


Shell Specs.

Identification Marking (Job no.,Drg.no.,Part no.) Visual 100% Drawing

Centreline/ Match Marking Visual 100% Drawing

12 REFRACTORY APPLICATION ( IF APPLICABLE) H

Refractory Material Compliance Review of 100% Drawing, Specs.


Test Cert

Validity (Shelf Life) of refractory material Verify 100% Application before


expiry date

Dimensions of Refractory Measurement 100% Drawing

Review of curing chart Review 100% Procedure/Specs.

Visual Inspection after curing Visual 100% Procedure/Specs.

Refractory soundness Sound Test Random Procedure/Specs.

13 INSPECTION RELEASE NOTE H

Final Document Review Review 100% Drawing, Compilation


of document

Inspection Release Note Issuance of


IRN

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN)


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N05
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
STACK DATE : 28-07-2011
PAGE : 5

3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.

SAUDI ARAMCO

1. WPS,PQR,WPQ and Welding Technology sheet(WTS) WELDING PROCEDURE SPECIFICATIONS

2. Material Test Certificates


3. Manufacturing Records
4. All the required Inspection Records.

IT IS MANDATORY FOR MANUFACTURER'S QUALITY CONTROL TO CARRY OUT


INSPECTION OF ALL THE STAGES COVERED IN THIS ITP.

Template shall have "Boiler Front","Top,Bottom" marking on it

Shop template shall have only pilot drill of 8mm size & reference
of final drill size shall be mentioned on it.This drilling shall be done
along with base plate.

For bolted stack,flanges made from sector,such sector weld shall be


100% RT or UT & shall be machined on mating sides.

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN)


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N05
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
STACK DATE : 28-07-2011
PAGE : 6

4.0 INSPECTION POINTS


INSPECTION POINTS ARE INDICATED BY :

SAUDI ARAMCO

R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS

cycle marked by the AI/Customer/TPI. Record of inspection is maintained


and will be made available to AI/Customer/TPI for review during next
HOLD/WITNESS stage Inspection,as applicable.

W Witness Point WITNESS POINT is defined as a notification operation in operation / production


cycle marked by the AI/Customer/TPI to excercise their option to witness
and verify a specific operation. Further processing shall proceed where the
AI/Customer/TPI do not validate their option. The notification shall be
documented in a manner acceptable to AI/Customer/TPI, as applicable.

H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.

- - Inspection option will not be exercised

5.0 RECORD OF REVISIONS :

REV NO. DATE CHANGES

PREPARED BY CHECKED BY APPROVED BY ACCEPTED BY CLIENT/CONSULTANT/TPI

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN)


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N42
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER CASING DATE : 28-07-2011
PAGE : 1

1.0 JOB SPECIFIC DATA : -

CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

CONSULTANT : - PROJECT NO:

INSP. AGENCY: - ---

2.0 QUALITY STAGES & INSPECTION :

SR. INSPECTION STAGES ACCEPTANCE STANDARD * INSP. BY


NO.
CHARACTERISTICS METHOD EXTENT REF.DOC./ PROCEDURE TL CLI

1 MATERIAL IDENTIFICATION H

Material Specification Review 100% Drawing

Verification of Specification Review 100% MTC/Code

Check Test, if no MTC Check_Test As per Code Material Specs.

Dimensions Measurement 10% Drawing/Code

Surface Condition Visual 100% Free From Surface


Defects

2 INSP.OF CASING PANELS H

Orientation Visual 100% Drawing

Dimensions Measurement 100% Drawing

Profile Layout 100% Within 3mm


Matching

Distortion / Flatness Measurement 100% Within 5mm


& Visual

Diagonals Measurement 100% Within 5mm

Weld Inspection (Size & Finish) Visual 100% Drawing & Procedure
VT

3 INSP.OF LOOSE PARTS OF INSULATION STRUCTURALS/ATTACHMENTS H

Identification & Orientation Visual 100% Drawing

Overall Dimensions Measurement 100% Drawing

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N42
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER CASING DATE : 28-07-2011
PAGE : 2

SR. INSPECTION STAGES ACCEPTANCE STANDARD * INSP. BY


NO.
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT REF.DOC./ PROCEDURE TL CLI


WELDING PROCEDURE SPECIFICATIONS

4 PAINTING & FINAL INSPECTION H

Compliance to Drawing for Scope Verify 100% Drawing-BOM

Aesthetics-Weld tacks,Hammer/Dent/Surface Marks,Sharp CorneR Visual 100% Free from Surface


Discontinuities

Surface Preparation for Painting Visual 100% Drawing/Specs.

Paint Shade, Make, Batch No., Expiry Date Visual 100% Drawing, Painting
Specs.,Application b
efore Expiry

Visual Inspection after painting Visual 100% Complete coverage of


area, No rundowns,
Peel-offs, Cracks

Paint-DFT Measurement 2Spots/m2 Drawing/ Painting


Specs.

Identification Marking (Job no.,Drg.no.,Part no.) Visual 100% Drawing

Centreline Marking Visual 100% Drawing

5 INSPECTION RELEASE NOTE H

Final Document Review Review 100% Drawing, Technical


Specifications

Inspection Release & Certification Issuance of 100% Drawing, Technical


IRN Specifications

3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.

1. WPS,PQR,WPQ and Welding Technology sheet(WTS)


2. Material Test Certificates
3. Manufacturing Records
4. All the required Inspection Records.

IT IS MANDATORY FOR MANUFACTURER'S QUALITY CONTROL TO CARRY OUT


INSPECTION OF ALL THE STAGES COVERED IN THIS ITP.

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN)


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N42
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER CASING DATE : 28-07-2011
PAGE : 3

4.0 INSPECTION POINTS


INSPECTION POINTS ARE INDICATED BY :

SAUDI ARAMCO

R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS

cycle marked by the AI/Customer/TPI. Record of inspection is maintained


and will be made available to AI/Customer/TPI for review during next
HOLD/WITNESS stage Inspection,as applicable.

W Witness Point WITNESS POINT is defined as a notification operation in operation / production


cycle marked by the AI/Customer/TPI to excercise their option to witness
and verify a specific operation. Further processing shall proceed where the
AI/Customer/TPI do not validate their option. The notification shall be
documented in a manner acceptable to AI/Customer/TPI, as applicable.

H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.

- - Inspection option will not be exercised

5.0 RECORD OF REVISIONS :

REV NO. DATE CHANGES

PREPARED BY CHECKED BY APPROVED BY ACCEPTED BY CLIENT/CONSULTANT/TPI

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN)


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N51
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER STRUCTURE DATE : 28-07-2011
PAGE : 1

1.0 JOB SPECIFIC DATA : -

CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

CONSULTANT : - PROJECT NO:

INSP. AGENCY: - ---

2.0 QUALITY STAGES & INSPECTION :

SR. INSPECTION STAGES ACCEPTANCE STANDARD * INSP. BY


NO.
CHARACTERISTICS METHOD EXTENT REF.DOC./ PROCEDURE TL CLI

1 MATERIAL IDENTIFICATION H

Material Specification Review 100% Drawing

Verification of Specification Review 100% MTC/Code

Check Test, if no MTC Check_Test As per Code Material Specs.

Dimensions Measurement 10% Drawing/Code

Surface Condition Visual 100% Free From Surface


Defects

2 BUTT JOINTS IN MAIN LOAD CARRYING MEMBERS FOR LENGTH BUILT-UP H

Joint Location Review 100% Engg Approval

Setup Dimensions Measurement 100% Drg / Engg Document

Welding Inspection Visual 100% Drawing

Weld Soundness RT/UT 100% Procedure RT/ UT

3 SETUP OF BASE PLATE TO COLUMN H

Centre line matching Measurement 100% Within 3mm

Squareness of Base Plate Measurement 100% 1.5 gap in 12"


Length

Gap Between Base plate and Column Measurement 100% Avg.Gap 0.5to1mm &
& Visual Max.2mm at Local Spo
ts

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N51
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER STRUCTURE DATE : 28-07-2011
PAGE : 2

SR. INSPECTION STAGES ACCEPTANCE STANDARD * INSP. BY


NO.
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT REF.DOC./ PROCEDURE TL CLI


WELDING PROCEDURE SPECIFICATIONS

4 SETUP & WELDING OF DIAPHRAGM PLATES H

Setup Dimensions & Locations Measurement 100% Drawing

Weld Inspection (Size & Finish) Visual 100% Drawing

Weld Soundness PT 10% Procedure / Code

5 FINAL INSPECTION OF SINGLE PIECE COLUMN H

Box Size Measurement 100% Drawing

Total Height of Column Measurement 100% 5mm Upto 10mtr & 8mm
max.

Level Marking Measurement 100% Within +/- 2mm

Orientation of Cleats/Brackets Visual 100% Drawing

Location of Cleats/Brackets Measurement 100% Within +/- 2mm

Squareness of Cleats/Brackets Measurement 100% 1.5 gap in 12"


Length

Straightness -(Camber/Sweep) Measurement 100% 1mm/Mtr, or 10mm


Max.

Twist & Levelling Water Level 100% 1.5%of Section


, Plumb Ht/Max.5mm; Water Le
vel Within 5mm

Site Weld Preperation Visual 100% Drawing

Identification & Match Marking Visual 100% Hard Punching /


Stenciling

6 MOCKUP ASSEMBLY OF SEGMENTED COLUMNS H

Box Size Measurement 100% Drawing

Total Height of Column Measurement 100% 5mm Upto 10mtr & 8mm
max.

Level Marking Measurement 100% Within +/- 2mm

Orientation of Cleats/Brackets Visual 100% Drawing

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N51
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER STRUCTURE DATE : 28-07-2011
PAGE : 3

SR. INSPECTION STAGES ACCEPTANCE STANDARD * INSP. BY


NO.
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT REF.DOC./ PROCEDURE TL CLI


WELDING PROCEDURE SPECIFICATIONS

Location of Cleats/Brackets Measurement 100% Within +/- 2mm

Squareness of Cleats/Brackets Measurement 100% 1.5 gap in 12"


Length

Twist & Levelling Water Level 100% 1.5%of Section


, Plumb Ht/Max.5mm; Water Le
vel Within 5mm

Straightness -(Camber/Sweep) Measurement 100% 1mm/Mtr, or 10mm


Max.

Alignment of Full Length of Column Measurement 100% Drawing

Splice Joint Details & Locations Measurement 100% Drawing

Identification & Match Marking Visual 100% Hard Punching /


Stenciling

7 FINAL INSPECTION OF SEGMENTED COLUMNS AFTER SPLIT-UP H

Dimensions Measurement 100% Drawing

Straightness -(Camber/Sweep) Measurement 100% 1mm/Mtr, or 10mm


Max.

Weld Inspection (Size & Finish) Measurement 100% Drawing


& Visual

Site Weld Preperation Visual 100% Drawing

ID Marking by Tag Welding (Job no.,Drg.no.,Part no Visual 100% Drawing

8 TRIAL ASSLY FOR BOLTED STRUCTURE WITH FULLY TIGHTENED BOLTS H

Orientation Visual 100% Drawing

Overall Assembly Inspection & Dimensional check : Measurement 100% Drawing

- Frame by Frame

- Platform stages

Alignment Verify 100% Drawing

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N51
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER STRUCTURE DATE : 28-07-2011
PAGE : 4

SR. INSPECTION STAGES ACCEPTANCE STANDARD * INSP. BY


NO.
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT REF.DOC./ PROCEDURE TL CLI


WELDING PROCEDURE SPECIFICATIONS

Completion of all Welding & Bolting arrangement Verify 100% Drawing

Match Marking with matchmark sketch Visual 100% Drawing

9 FINAL INSPECTION OF GIRDERS H

Orientation Visual 100% Drawing

Overall Dimensions Measurement 100% Drawing

Length Measurement 100% +0/-3mm upto


12mtr,-9mm max.

Straightness -(Camber/Sweep) Measurement 100% 1mm/Mtr, or 10mm


Max.

Twist & Levelling Water Level 100% 1.5%of Section


, Plumb Ht/Max.5mm; Water Le
vel Within 5mm

Cleat locations, orientation, dimensions Visual & 100% Drawing


Measureme

Weld Soundness of fillet welds for plate fabricated girders PT Min.10% * Procedure PT

* or drg. whichever is stringent

Weld Inspection (Size & Finish) Measurement 100% Drawing, Procedure


& Visual VT

NDE After removal of temporary supports,after dress up MPT 100% Procedure MT

ID Marking by Tag Welding (Job no.,Drg.no.,Part no Visual 100% Drawing

10 FINAL INSPECTION OF BEAMS/BRACINGS H

Orientation Visual 100% Drawing

Overall Dimensions Measurement 100% Drawing

Length Measurement 100% +0/-3mm upto


12mtr,-5mm max.

Straightness -(Camber/Sweep) Measurement 100% 1mm/Mtr, or 10mm


Max.

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N51
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER STRUCTURE DATE : 28-07-2011
PAGE : 5

SR. INSPECTION STAGES ACCEPTANCE STANDARD * INSP. BY


NO.
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT REF.DOC./ PROCEDURE TL CLI


WELDING PROCEDURE SPECIFICATIONS

Twist & Levelling Water Level 100% 1.5%of Section


, Plumb Ht/Max.5mm; Water Le
vel Within 5mm

Cleat locations, orientation, dimensions Visual & 100% Drawing


Measureme

Weld Inspection (Size & Finish) Measurement 100% Drawing, Procedure


& Visual VT

ID Marking by Tag Welding (Job no.,Drg.no.,Part no Visual 100% Drawing

11 FINAL INSPECTION OF BUCKSTAYS H

Orientation Visual 100% Drawing

Overall Dimensions Measurement 100% Drawing

Alignment & Levelling Water level 100% Within 5mm

Corner Links - Pin fitment Measurement 100% Drawing

Straightness -(Camber/Sweep) Measurement 100% 1mm/Mtr, or 10mm


Max.

Weld Inspection (Size & Finish) Measurement 100% Drawing


& Visual

ID Marking by Tag Welding (Job no.,Drg.no.,Part no Visual 100% Drawing

12 FINAL INSPECTION OF LADDERS H

Overall Dimensions Measurement 100% Drawing

Alignment Visual 100% Drawing

Weld Inspection Visual 100% Drawing

Straightness Measurement 100% 1mm/Mtr, or 10mm


Max.

Match Marking Visual 100% Drawing

ID Marking by Tag Welding (Job no.,Drg.no.,Part no Visual 100% Drawing

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N51
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER STRUCTURE DATE : 28-07-2011
PAGE : 6

SR. INSPECTION STAGES ACCEPTANCE STANDARD * INSP. BY


NO.
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT REF.DOC./ PROCEDURE TL CLI


WELDING PROCEDURE SPECIFICATIONS

13 FINAL INSP.OF STAIRCASES,HAND RAILINGS H

Overall Dimensions Measurement 100% Drawing

Inclination Angle Layout 100% Within 2mm


Matching

Weld Inspection Visual 100% Drawing

Straightness Measurement 100% 1mm/Mtr, or 10mm


Max.

ID Marking by Tag Welding (Job no.,Drg.no.,Part no Visual 100% Drawing

Aesthetics-Weld tacks,Surface Marks, Sharp Corners Visual 100% Free from Surface
Discontinuities

14 FINAL INSP.OF CANOPY STRUCTURE H

Orientation Visual 100% Drawing

Overall Dimensions Measurement 100% Drawing

Weld Inspection Visual 100% Drawing

Straightness & Alignment Visual 100% Drawing

ID Marking by Tag Welding (Job no.,Drg.no.,Part no Visual 100% Drawing

15 FINAL INSP.OF MONORAIL STR, TEMP.ERECTION & PR.PART SUPPORTS H

Orientation Visual 100% Drawing

Overall Dimensions Measurement 100% Drawing

Weld Inspection Visual 100% Drawing

Straightness & Alignment Measurement 100% Drawing

ID Marking by Tag Welding (Job no.,Drg.no.,Part no Visual 100% Drawing

16 SURFACE PREPARATION H

Surface Preparation & Cleaning Visual 100% Drawing, Painting


Specs.

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N51
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER STRUCTURE DATE : 28-07-2011
PAGE : 7

SR. INSPECTION STAGES ACCEPTANCE STANDARD * INSP. BY


NO.
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT REF.DOC./ PROCEDURE TL CLI


WELDING PROCEDURE SPECIFICATIONS

17 PAINTING INSPECTION H

Compliance to Drawing for Scope Verify 100% Drawing-BOM

Paint Shade, Make, Batch No., Expiry Date Visual 100% Drawing, Painting
Specs.,Application b
efore expiry

Visual Inspection after painting Visual 100% Complete coverage of


area, No rundowns,
Peel-offs, Cracks

Paint-DFT Measurement Random Drawing/ Painting


Specs.

ID Marking by Tag Welding (Job no.,Drg.no.,Part no.) Visual 100% Drawing

18 INSPECTION RELEASE NOTE H

Final Document Review Review 100% Drawing, Compilation


of document

Inspection Release Note Issuance of


IRN

3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.

1. WPS,PQR,WPQ and Welding Technology sheet(WTS)


2. Material Test Certificates
3. Manufacturing Records
4. All the required Inspection Records.

IT IS MANDATORY FOR MANUFACTURER'S QUALITY CONTROL TO CARRY OUT


INSPECTION OF ALL THE STAGES COVERED IN THIS ITP.

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N51
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER STRUCTURE DATE : 28-07-2011
PAGE : 8

4.0 INSPECTION POINTS


INSPECTION POINTS ARE INDICATED BY :

SAUDI ARAMCO

R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS

cycle marked by the AI/Customer/TPI. Record of inspection is maintained


and will be made available to AI/Customer/TPI for review during next
HOLD/WITNESS stage Inspection,as applicable.

W Witness Point WITNESS POINT is defined as a notification operation in operation / production


cycle marked by the AI/Customer/TPI to excercise their option to witness
and verify a specific operation. Further processing shall proceed where the
AI/Customer/TPI do not validate their option. The notification shall be
documented in a manner acceptable to AI/Customer/TPI, as applicable.

H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.

- - Inspection option will not be exercised

5.0 RECORD OF REVISIONS :

REV NO. DATE CHANGES

PREPARED BY CHECKED BY APPROVED BY ACCEPTED BY CLIENT/CONSULTANT/TPI

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN)


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N52
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
FOUNDATION BOLTS & PACKER PLATES DATE : 28-07-2011
PAGE : 1

1.0 JOB SPECIFIC DATA : -

CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

CONSULTANT : - PROJECT NO:

INSP. AGENCY: - ---

2.0 QUALITY STAGES & INSPECTION :

SR. INSPECTION STAGES ACCEPTANCE STANDARD * INSP. BY


NO.
CHARACTERISTICS METHOD EXTENT REF.DOC./ PROCEDURE TL CLI

1 MATERIAL IDENTIFICATION H

Material Specification Review 100% Drawing

Verification of Specification Review 100% MTC/Code

Check Test, if no MTC Check_Test As per Code Material Specs.

Dimensions Measurement 10% Drawing/Code

Surface Condition Visual 100% Free From Surface


Defects

Nut Proof Load in black condition Mech. 2 Samples Code


Testing /Size

2 FINAL INSPECTION (FOUNDATION BOLT) H

Bolt Dimensions: Overall Length, Thread Lenght Measurement 10% Drawing

Anchor Plate Dimensions: Length X Width x Thickness Measurement 10% Drawing

Plain Washers / Taper Washers Measurement 10% Drawing

Bolt thread, finish & Size Visual, 10% Drawing


Thread ga

Nut Proof Load in black condition Review Review Drawing/code

Nut,Locknut fitment with Bolt Threads Visual 10% Drawing/Code

Weld Inspection (Size & Finish) of anchoring Plates/Rods Measurement 10% Drawing
& Visual

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N52
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
FOUNDATION BOLTS & PACKER PLATES DATE : 28-07-2011
PAGE : 2

SR. INSPECTION STAGES ACCEPTANCE STANDARD * INSP. BY


NO.
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT REF.DOC./ PROCEDURE TL CLI


WELDING PROCEDURE SPECIFICATIONS

3 FINAL INSPECTION (PACKER PLATES) H

Dimensions: Length x Width x Thickness Measurement 10% Drawing

Edge Finish Visual 10% Free From Burrs

4 PAINTING INSPECTION H

Compliance to Drawing for Scope Review 100% Drawing-BOM

Greasing/Oiling on Threaded Portion Visual 100% TBW Practice

Painting Visual 100% Drawing/ Painting


Specs.

Identification Marking (Size & Job no.) Visual 100% Drawing/PO

5 INSPECTION RELEASE NOTE H

Final Document Review Review 100% Compillation of


stage IR's & MTC's

Inspection Release Note Issuance of 100% IRN


IRN

3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.

1. WPS,PQR,WPQ and Welding Technology sheet(WTS)


2. Material Test Certificates
3. Manufacturing Records
4. All the required Inspection Records.

IT IS MANDATORY FOR MANUFACTURER'S QUALITY CONTROL TO CARRY OUT


INSPECTION OF ALL THE STAGES COVERED IN THIS ITP.

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N52
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
FOUNDATION BOLTS & PACKER PLATES DATE : 28-07-2011
PAGE : 3

4.0 INSPECTION POINTS


INSPECTION POINTS ARE INDICATED BY :

SAUDI ARAMCO

R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS

cycle marked by the AI/Customer/TPI. Record of inspection is maintained


and will be made available to AI/Customer/TPI for review during next
HOLD/WITNESS stage Inspection,as applicable.

W Witness Point WITNESS POINT is defined as a notification operation in operation / production


cycle marked by the AI/Customer/TPI to excercise their option to witness
and verify a specific operation. Further processing shall proceed where the
AI/Customer/TPI do not validate their option. The notification shall be
documented in a manner acceptable to AI/Customer/TPI, as applicable.

H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.

- - Inspection option will not be exercised

5.0 RECORD OF REVISIONS :

REV NO. DATE CHANGES

PREPARED BY CHECKED BY APPROVED BY ACCEPTED BY CLIENT/CONSULTANT/TPI

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN)


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N53
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
GRATINGS(GRILLS) DATE : 28-07-2011
PAGE : 1

1.0 JOB SPECIFIC DATA : -

CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

CONSULTANT : - PROJECT NO:

INSP. AGENCY: - ---

2.0 QUALITY STAGES & INSPECTION :

SR. INSPECTION STAGES ACCEPTANCE STANDARD * INSP. BY


NO.
CHARACTERISTICS METHOD EXTENT REF.DOC./ PROCEDURE TL CLI

1 MATERIAL IDENTIFICATION H

Material Specification Review 100% Drawing

Verification of Specification Review 100% MTC/Code

Check Test, if no MTC Check_Test As per Code Material Specs.

Dimensions Measurement At Random Drawing/ Specs.

Surface Condition Visual 100% Free From Surface


Defects

2 DIMENSIONAL INSPECTION H

Length & Width Measurement 10% +0/-5mm

Span Orientation Visual Random Drawing/ Pattern

Diagonals Measurement 10% Within 5mm

Ups & Downs of Load Members & Secondary Members Measurement 10% Within 1mm

Dimensions & Thickness Measurement At Random Drawing/ Specs.

Transverse Bow Measurement 10% Within 3mm

Logitudinal Bow Measurement 10% Within 5mm

Weld Inspection (Size & Finish) Visual 10% Free from


Significant Defects,
Spatters/Slag

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N53
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
GRATINGS(GRILLS) DATE : 28-07-2011
PAGE : 2

SR. INSPECTION STAGES ACCEPTANCE STANDARD * INSP. BY


NO.
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT REF.DOC./ PROCEDURE TL CLI


WELDING PROCEDURE SPECIFICATIONS

3 CHECK TEST FOR GALVANISING,(IF APPLICABLE) H

Uniformity in thickness of coating Preece Test Sample IS:2633

Mass of Zinc coating Mass of Sample IS:6745


Zinc coat

Adherence of Zinc coating Adhesion Sample IS:2629


Test

DFT of Zinc coating Measurement Sample Drawing/IS:2629

4 PAINTING/COATING AND FINAL INSPECTION H

Compliance to Drawing/PO for Scope Verify 100% Drawing-BOM/PO

Surface Preparation Visual 100% Drawing/Specs.

Paint Shade, Make, Batch No., Expiry Date Visual 100% Drawing, Painting
Specs.,Application b
efore expiry

Visual Inspection after painting Visual 10% Complete coverage of


area, No rundowns,
Peel-offs, Cracks

Paint-DFT Measurement Random Drawing/ Painting


Specs.

Visual Inspection for Galvanised items (if Applicable) Visual 10% IS:2629

DFT of zinc coat for Galvanised items (If applicable) Measurement Random Drawing/IS:2629

Identification Marking (Grill Size, Job No., Mark no.) Visual 100% Drawing

5 INSPECTION RELEASE NOTE H

Final Document Review Review 100% Compilation of IR's


& TC , Drawing

Inspection Release note Issuance of


IRN

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N53
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
GRATINGS(GRILLS) DATE : 28-07-2011
PAGE : 3

3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.

SAUDI ARAMCO

1. WPS,PQR,WPQ and Welding Technology sheet(WTS) WELDING PROCEDURE SPECIFICATIONS

2. Material Test Certificates


3. Manufacturing Records
4. All the required Inspection Records.

IT IS MANDATORY FOR MANUFACTURER'S QUALITY CONTROL TO CARRY OUT


INSPECTION OF ALL THE STAGES COVERED IN THIS ITP.

4.0 INSPECTION POINTS


INSPECTION POINTS ARE INDICATED BY :

R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production
cycle marked by the AI/Customer/TPI. Record of inspection is maintained
and will be made available to AI/Customer/TPI for review during next
HOLD/WITNESS stage Inspection,as applicable.

W Witness Point WITNESS POINT is defined as a notification operation in operation / production


cycle marked by the AI/Customer/TPI to excercise their option to witness
and verify a specific operation. Further processing shall proceed where the
AI/Customer/TPI do not validate their option. The notification shall be
documented in a manner acceptable to AI/Customer/TPI, as applicable.

H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.

- - Inspection option will not be exercised

5.0 RECORD OF REVISIONS :

REV NO. DATE CHANGES

PREPARED BY CHECKED BY APPROVED BY ACCEPTED BY CLIENT/CONSULTANT/TPI

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN)


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N54
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
DRUM INTERNALS & EXTERNALS DATE : 28-07-2011
PAGE : 1

1.0 JOB SPECIFIC DATA : -

CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

CONSULTANT : - PROJECT NO:

INSP. AGENCY: - ---

2.0 QUALITY STAGES & INSPECTION :

SR. INSPECTION STAGES ACCEPTANCE STANDARD * INSP. BY


NO.
CHARACTERISTICS METHOD EXTENT REF.DOC./ PROCEDURE TL CLI

1 MATERIAL IDENTIFICATION H XX

Material Specification Review 100% Drawing

Verification of Specification Review 100% MTC/Code

Check Test, if no MTC Check_Test As per Code Material Specs.

Dimensions Measurement 10% Drawing/Code

Surface Condition Visual 100% Free From Surface


Defects

2 INSPECTION OF DRUM INTERNALS H XX

Orientation of Assembly w.r.to Boiler Front Visual 100% Drawing

Overall Assembly Dimensions Measurement 100% Drawing

3 INSPECTION OF DRUM EXTERNALS H XX

Dimensions on Layout Measurement 100% Drawing

NDE of Lifting Lug UT 100% Free from


Laminations

NDE of Saddle pad plates after rolling UT 100% Free from


Laminations

NDE on plates edges of > 8mm thick PT 100% Free from


Laminations

4 FINAL INSPECTION H XX

Completion of all Welding Visual 100% Drawing

Weld Inspection Visual 100% Drawing

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N54
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
DRUM INTERNALS & EXTERNALS DATE : 28-07-2011
PAGE : 2

SR. INSPECTION STAGES ACCEPTANCE STANDARD * INSP. BY


NO.
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT REF.DOC./ PROCEDURE TL CLI


WELDING PROCEDURE SPECIFICATIONS

Application of Rust Prevension Oil on Drum Internals Visual 100% TBW Practice

Painting on Drum Externals Visual 100% Drawing/Specs.

Compliance to Drawing for Scope Verify 100% Drawing-BOM

Identification Marking (Job no.,Drg.no.,Part no Visual 100% Drawing

5 INSPECTION RELEASE NOTE H XX

Final Document Review Review 100% Drawing, Technical


Specifications

Inspection Release & Certification Issuance of 100% Drawing, Technical


IRN Specifications

3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.

1. WPS,PQR,WPQ and Welding Technology sheet(WTS)


2. Material Test Certificates
3. Manufacturing Records
4. All the required Inspection Records.

IT IS MANDATORY FOR MANUFACTURER'S QUALITY CONTROL TO CARRY OUT


INSPECTION OF ALL THE STAGES COVERED IN THIS ITP.

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N54
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
DRUM INTERNALS & EXTERNALS DATE : 28-07-2011
PAGE : 3

4.0 INSPECTION POINTS


INSPECTION POINTS ARE INDICATED BY :

SAUDI ARAMCO

R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS

cycle marked by the AI/Customer/TPI. Record of inspection is maintained


and will be made available to AI/Customer/TPI for review during next
HOLD/WITNESS stage Inspection,as applicable.

W Witness Point WITNESS POINT is defined as a notification operation in operation / production


cycle marked by the AI/Customer/TPI to excercise their option to witness
and verify a specific operation. Further processing shall proceed where the
AI/Customer/TPI do not validate their option. The notification shall be
documented in a manner acceptable to AI/Customer/TPI, as applicable.

H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.

- - Inspection option will not be exercised

XX INTERNAL INSPECTION Inspection option for 'XX' points will be excercised by Thermax/Vendor QC and
will not applicable to TPI/Client Inspection.

5.0 RECORD OF REVISIONS :

REV NO. DATE CHANGES

PREPARED BY CHECKED BY APPROVED BY ACCEPTED BY CLIENT/CONSULTANT/TPI

*INSP.BY /TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN)


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N55
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER BASE FRAME(FM) DATE : 28-07-2011
PAGE : 1

1.0 JOB SPECIFIC DATA : -

CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

CONSULTANT : - PROJECT NO:

INSP. AGENCY: - ---

2.0 QUALITY STAGES & INSPECTION :

SR. INSPECTION STAGES ACCEPTANCE STANDARD * INSP. BY


NO.
CHARACTERISTICS METHOD EXTENT REF.DOC./ PROCEDURE TL CLI

1 MATERIAL IDENTIFICATION H

Material Specification Review 100% Drawing

Verification of Specification Review 100% MTC/Code

Check Test, if no MTC Check_Test As per Code Material Specs.

Dimensions Measurement 10% Drawing/Code

Surface Condition Visual 100% Free From Surface


Defects

2 SPLICE JOINTS IN MAIN LOAD CARRYING MEMBERS H

Splice Joint Details Review 100% Engg Approval

Setup Dimensions Measurement 100% Drg/Engg Document

Welding Inspection Visual 100% Drawing

Weld Soundness RT 100% Procedure/Code

3 INSP.OF PAD PLATES H

Layout Inspection Measurement 100% Drawing

Dimensions on Layout-Profile, Centre Height Layout 100% Within 1mm


Matching

Circumference & Alignment Layout 100% Drawing


Matching

Location & Size of Tell-Tale Hole & Squareness Measurement 100% Drawing

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N55
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER BASE FRAME(FM) DATE : 28-07-2011
PAGE : 2

SR. INSPECTION STAGES ACCEPTANCE STANDARD * INSP. BY


NO.
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT REF.DOC./ PROCEDURE TL CLI


WELDING PROCEDURE SPECIFICATIONS

4 FINAL INSPECTION H

Orientation Visual 100% Drawing

Overall Assembly Dimensions Measurement 100% Drawing

Twist & Levelling Water Level 100% Within 5mm


, Plumb

Squareness Measurement 100% Within 5mm

Pad Plate Profile & Concetricity Template 100% Within 3mm

Completion of all Welding Verify 100% Drawing

Weld Inspection (Size & Finish) Visual 100% Drawing

Compliance to drawing for Scope Verify 100% Drawing-BOM

Identification Marking (Job No.,Drg No.,Part No.) Visual 100% Drawing

5 PAINTING INSPECTION H

Surface Preparation for Painting Visual 100% Drawing/Specs.

Paint Shade, Make, Batch No., Expiry Date Visual 100% Drawing, Painting
Specs., Application
before Expiry

Visual Inspection after painting Visual 100% Complete coverage of


area, No rundowns,
Peel-offs, Cracks

Paint-DFT Measurement 2Spots/m2 Drawing/ Painting


Specs.

Identification Marking (Job no.,Drg.no.,Part no.) Visual 100% Drawing

3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.

1. WPS,PQR,WPQ and Welding Technology sheet(WTS)


2. Material Test Certificates
3. Manufacturing Records
4. All the required Inspection Records.

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N55
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER BASE FRAME(FM) DATE : 28-07-2011
PAGE : 3

SAUDI ARAMCO

IT IS MANDATORY FOR MANUFACTURER'S QUALITY CONTROL TO CARRY OUT WELDING PROCEDURE SPECIFICATIONS

INSPECTION OF ALL THE STAGES COVERED IN THIS ITP.

4.0 INSPECTION POINTS


INSPECTION POINTS ARE INDICATED BY :

R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production
cycle marked by the AI/Customer/TPI. Record of inspection is maintained
and will be made available to AI/Customer/TPI for review during next
HOLD/WITNESS stage Inspection,as applicable.

W Witness Point WITNESS POINT is defined as a notification operation in operation / production


cycle marked by the AI/Customer/TPI to excercise their option to witness
and verify a specific operation. Further processing shall proceed where the
AI/Customer/TPI do not validate their option. The notification shall be
documented in a manner acceptable to AI/Customer/TPI, as applicable.

H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.

- - Inspection option will not be exercised

5.0 RECORD OF REVISIONS :

REV NO. DATE CHANGES

PREPARED BY CHECKED BY APPROVED BY ACCEPTED BY CLIENT/CONSULTANT/TPI

*INSP.BY - CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN)


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N56
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
ECONOMISER CASING & STRUCTURE DATE : 28-07-2011
PAGE : 1

1.0 JOB SPECIFIC DATA : -

CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

CONSULTANT : - PROJECT NO:

INSP. AGENCY: - ---

2.0 QUALITY STAGES & INSPECTION :

SR. INSPECTION STAGES ACCEPTANCE STANDARD * INSP. BY


NO.
CHARACTERISTICS METHOD EXTENT REF.DOC./ PROCEDURE TL CLI

1 MATERIAL IDENTIFICATION H

Material Specification Review 100% Drawing

Verification of Specification Review 100% MTC/Code

Check Test, if no MTC Check_Test As per Code Material Specs.

Dimensions Measurement 10% Drawing/Code

Surface Condition Visual 100% Free From Surface


Defects

2 INSPECTION OF COLUMNS H

Orientation of Assembly w.r.to Boiler Front Visual 100% Drawing

Overall Dimensions Measurement 100% Drawing

Level Marking Visual 100% Drawing

Squareness of Connections Measurement 100% 1.5 gap in 12"


length

Straightness - (Camber / Sweep) Measurement 100% 1mm/Mtr, or 10mm


Max.

Twist & Levelling Water level 100% Within 5mm


, Plumb

Site Weld Preperation Visual 100% Drawing

Identification & Match Marking Visual 100% Drawing

*INSP.BY - CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N56
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
ECONOMISER CASING & STRUCTURE DATE : 28-07-2011
PAGE : 2

SR. INSPECTION STAGES ACCEPTANCE STANDARD * INSP. BY


NO.
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT REF.DOC./ PROCEDURE TL CLI


WELDING PROCEDURE SPECIFICATIONS

3 INSP.OF TOP & BOTTOM FRAME H

Orientation Visual 100% Drawing

Overall Assembly Dimensions Measurement 100% Drawing

Alignment & Squareness Measurement 100% Drawing

4 INSP.OF STUDS & U-BOLTS H

Verification of Stud Material and Size Verify 100% Drawing

Check Test, if no MTC Check_Test As per Code Material Specs.

Thread Length & Nut Fitment Verify 100% Free Fitment with
Stud/U-Bolt Threads

U-Bolt Dimensions on Layout Layout 100% Within 2mm


Matching

Application of Rust Prevension Oil Verify 100% TBW Practice

5 INSP.OF COIL SUPPORTS H

Overall Dimensions Measurement 100% Drawing

Location of Supports Measurement 100% Drawing

Matching of Holes with Respective Flats Verify 100% Drawing

Weld Inspection Visual 100% Drawing

6 INSP.OF CASING H

Orientation Visual 100% Drawing

Overall Dimensions Measurement 100% Drawing

Opening Dimensions Measurement 100% Drawing

Identification & Match Marking Visual 100% Drawing

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN) Contd...


SAUDI ARAMCO
THERMAX LIMITED WELDING PROCEDURE SPECIFICATIONS
BOILER & HEATER GROUP

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N56
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
ECONOMISER CASING & STRUCTURE DATE : 28-07-2011
PAGE : 3

SR. INSPECTION STAGES ACCEPTANCE STANDARD * INSP. BY


NO.
SAUDI ARAMCO

CHARACTERISTICS METHOD EXTENT REF.DOC./ PROCEDURE TL CLI


WELDING PROCEDURE SPECIFICATIONS

7 PAINTING & FINAL INSPECTION H

Compliance to Drawing for Scope Verify 100% Drawing-BOM

Surface Preparation for Painting Visual 100% Drawing/Specs.

Paint Shade, Make, Batch No., Expiry Date Visual 100% Drawing, Painting
Specs.,Application b
efore Expiry

Visual Inspection after painting Visual 100% Complete coverage of


area, No rundowns,
Peel-offs, Cracks

Paint-DFT Measurement 2Spots/m2 Drawing/ Painting


Specs.

Identification Marking (Job no.,Drg.no.,Part no.) Visual 100% Drawing

8 INSPECTION RELEASE NOTE H

Final Document Review Review 100% Drawing, Technical


Specifications

Inspection Release & Certification Issuance of 100% Drawing, Technical


IRN Specifications

3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.

1. WPS,PQR,WPQ and Welding Technology sheet(WTS)


2. Material Test Certificates
3. Manufacturing Records
4. All the required Inspection Records.

IT IS MANDATORY FOR MANUFACTURER'S QUALITY CONTROL TO CARRY OUT


INSPECTION OF ALL THE STAGES COVERED IN THIS ITP.

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN)


SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS

INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N56
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
ECONOMISER CASING & STRUCTURE DATE : 28-07-2011
PAGE : 4

4.0 INSPECTION POINTS


INSPECTION POINTS ARE INDICATED BY :

SAUDI ARAMCO

R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS

cycle marked by the AI/Customer/TPI. Record of inspection is maintained


and will be made available to AI/Customer/TPI for review during next
HOLD/WITNESS stage Inspection,as applicable.

W Witness Point WITNESS POINT is defined as a notification operation in operation / production


cycle marked by the AI/Customer/TPI to excercise their option to witness
and verify a specific operation. Further processing shall proceed where the
AI/Customer/TPI do not validate their option. The notification shall be
documented in a manner acceptable to AI/Customer/TPI, as applicable.

H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.

- - Inspection option will not be exercised

5.0 RECORD OF REVISIONS :

REV NO. DATE CHANGES

PREPARED BY CHECKED BY APPROVED BY ACCEPTED BY CLIENT/CONSULTANT/TPI

*INSP.BY CLI -CLIENT/TPI

Session : tccom9420m040 INSPECTION & TEST PLAN (QA PLAN)

You might also like