Professional Documents
Culture Documents
Inspection Test Plan
Inspection Test Plan
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P01
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER DRUMS DATE : 28-05-2011
PAGE : 1
CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS
1 MATERIAL IDENTIFICATION H H
Review & Verification of Material Test Certs. & Drawing Review 100% Drawing, ASME Sec-II
Verify UT Testing for Plate & Nozzle Forgings in MTC Review 100% Material Spec.
HOT ROLLED DRUM:Simulated Heat Treatment & PWHT test coupon Review 1 Sample HT Cycle & Material
/Heat Specs./Code
Document review for Dished Ends & Manhole Rims Review 100% Drawing & Code
Intermediate SR (if D/T<20 for CS & <18 for AS) Review of 100% IBR-1950/HT
HT chart Procedure
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P01
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER DRUMS DATE : 28-05-2011
PAGE : 2
3 L-SEAM WELDING H R
NDE for CS Drum thk. >&= 100 mm & AS Drum thk. >&=50mm UT 100% Procedure UT
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P01
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER DRUMS DATE : 28-05-2011
PAGE : 3
HT chart
5 C-SEAM SETUP H H
6 C-SEAM WELDING H R
*INSP.BY /TPI
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P01
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER DRUMS DATE : 28-05-2011
PAGE : 4
NDE for CS Drum thk. >&= 100 mm & AS Drum thk. >&=50mm UT 100% Procedure UT
MARKING ON SHELL :
MARKING ON D'END :
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P01
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER DRUMS DATE : 28-05-2011
PAGE : 5
10 INSPECTION OF OPENINGS H -
1) Opening on shell
2) Opening on D'end
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P01
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER DRUMS DATE : 28-05-2011
PAGE : 6
Note No.3)
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P01
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER DRUMS DATE : 28-05-2011
PAGE : 7
Full penetration welds >=10 NPS or above 25 thk UT/RT 100% Procedure UT/RT
Full penetration set through nozzle welds UT/RT 100% Procedure UT/RT
-Full penetration Nozzle welds>=10NPS & Safety valve nozzle UT/RT 100% Procedure UT/RT
& Full penetration Nozzle welds> 25mm thick UT/RT 100% Procedure UT/RT
13 IDENTIFICATION AND DIMENSIONS OF MANHOLE COVER PLATE & PLACING INSIDE THE DRUM H R
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P01
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER DRUMS DATE : 28-05-2011
PAGE : 8
Weld reinforcement- Flush ground from outside Measurement 100% Drawing, IBR-1950
NDE for CS Drum thk. >&= 100 mm & AS Drum thk. >&=50mm UT 100% Procedure UT
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P01
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER DRUMS DATE : 28-05-2011
PAGE : 9
17 PWHT H R
NDE for CS Plate thk >&= 100mm & AS Plate thk. >&=50mm **
**All accesible pressure retaining welds(LS,CS,Nozzle Welds) PT/MT 100% Procedure PT/MT
19 HYDROSTATIC TEST H H
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P01
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER DRUMS DATE : 28-05-2011
PAGE : 10
22 DRILLING INSPECTION H -
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P01
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER DRUMS DATE : 28-05-2011
PAGE : 11
23 FINAL INSPECTION H H
24 PAINTING INSPECTION H -
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P01
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER DRUMS DATE : 28-05-2011
PAGE : 12
3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.
1) NDE Procedures
+---+-----------+-------------------------------------------+
|Sr.|Control No.|Procedure Description |
+---+-----------+-------------------------------------------+
|1) |RT12 |Radiographic Examination of Welded Joints |
+---+-----------+-------------------------------------------+
|2) |PT1 |Liquid Penetrant Examination |
+---+-----------+-------------------------------------------+
|3) |MT3 |Magnetic Particle Examination |
+---+-----------+-------------------------------------------+
|4) |UT2 |Ultrasonic Examination Of Butt Welds |
+---+-----------+-------------------------------------------+
|5) |UT4 |Straight Beam Ultrasonic Examination of |
| | |Rolled Steel Plates |
+---+-----------+-------------------------------------------+
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P01
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER DRUMS DATE : 28-05-2011
PAGE : 13
R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production
cycle marked by the AI/Customer/TPI. Record of inspection is maintained
and will be made available to AI/Customer/TPI for review during next
HOLD/WITNESS stage Inspection,as applicable.
H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P02
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
DISHED ENDS FOR BOILER DRUM DATE : 15-09-2011
PAGE : 1
CUSTOMER :
1 MATERIAL IDENTIFICATION H H
Inside Circumference-For a Pair of Dished End Measurement 100% Within +/- 5mm
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P02
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
DISHED ENDS FOR BOILER DRUM DATE : 15-09-2011
PAGE : 2
3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.
1) NDE Procedures
+---+-----------+-------------------------------------------+
|Sr.|Control No.|Procedure Description |
+---+-----------+-------------------------------------------+
|1) |RT12 |Radiographic Examination of Welded Joints |
+---+-----------+-------------------------------------------+
|2) |PT1 |Liquid Penetrant Examination |
+---+-----------+-------------------------------------------+
|3) |MT3 |Magnetic Particle Examination |
+---+-----------+-------------------------------------------+
|4) |UT2 |Ultrasonic Examination Of Butt Welds |
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P02
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
DISHED ENDS FOR BOILER DRUM DATE : 15-09-2011
PAGE : 3
+---+-----------+-------------------------------------------+
|5) |UT4 |Straight Beam Ultrasonic Examination of |
| | |Rolled Steel Plates |
SAUDI ARAMCO
R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production
cycle marked by the AI/Customer/TPI. Record of inspection is maintained
and will be made available to AI/Customer/TPI for review during next
HOLD/WITNESS stage Inspection,as applicable.
H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P03
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
MEMBRANE PANELS DATE : 15-09-2011
PAGE : 1
CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS
1 MATERIAL IDENTIFICATION H H
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P03
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
MEMBRANE PANELS DATE : 15-09-2011
PAGE : 2
Flow Area O.D less than 3" * Ball Test 100% Ball Size= {(0.9
OD-2.3SWT)-1.6mm}
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P03
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
MEMBRANE PANELS DATE : 15-09-2011
PAGE : 3
Flow Area for Tubes O.D less than 3" Ball Test 100% Ball Size(Cold Bend)
={(0.9 OD-2.3SWT)-
1.6mm}
Flow Area for Tubes O.D less than 3" Ball Test 100% Ball Size(Cold Bend)
={(0.9 OD-2.3SWT)-
1.6mm}
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P03
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
MEMBRANE PANELS DATE : 15-09-2011
PAGE : 4
Cleaning of Tubes from inside Air blowing 100% Free from foreign
material
Cleaning of header from inside Air blowing 100% Free from foreign
material
Inspection of Strip cutout with Template/ Gauge as appl. Verify 100% Drawing
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P03
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
MEMBRANE PANELS DATE : 15-09-2011
PAGE : 5
18 FINAL INSPECTION H H
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P03
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
MEMBRANE PANELS DATE : 15-09-2011
PAGE : 6
Dimension
19 PAINTING INSPECTION H -
Cleaning of headers from inside Air blowing 100% Free from foreign
material
3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P03
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
MEMBRANE PANELS DATE : 15-09-2011
PAGE : 7
1) NDE Procedures
+---+-----------+-------------------------------------------+
|Sr.|Control No.|Procedure Description |
+---+-----------+-------------------------------------------+
|1) |RT12 |Radiographic Examination of Welded Joints |
+---+-----------+-------------------------------------------+
|2) |PT1 |Liquid Penetrant Examination |
+---+-----------+-------------------------------------------+
|3) |MT3 |Magnetic Particle Examination |
+---+-----------+-------------------------------------------+
|4) |UT2 |Ultrasonic Examination Of Butt Welds |
+---+-----------+-------------------------------------------+
|5) |UT4 |Straight Beam Ultrasonic Examination of |
| | |Rolled Steel Plates |
+---+-----------+-------------------------------------------+
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P03
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
MEMBRANE PANELS DATE : 15-09-2011
PAGE : 8
SAUDI ARAMCO
R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS
H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P04
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER SIDE/BAFFLE/FURNACE SIDE/REAR WALL (FM) DATE : 11-06-2011
PAGE : 1
CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS
1 MATERIAL IDENTIFICATION H H
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P04
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER SIDE/BAFFLE/FURNACE SIDE/REAR WALL (FM) DATE : 11-06-2011
PAGE : 2
Flow Area O.D less than 3" * Ball Test 100% Ball Size= {(0.9
OD-2.3SWT)-1.6mm}
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P04
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER SIDE/BAFFLE/FURNACE SIDE/REAR WALL (FM) DATE : 11-06-2011
PAGE : 3
8 NDT SCHEDULE H R
Inspection of Strip cutout with Template/ Gauge as appl. Verify 100% Drawing
10 FINAL INSPECTION H H
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P04
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER SIDE/BAFFLE/FURNACE SIDE/REAR WALL (FM) DATE : 11-06-2011
PAGE : 4
11 PAINTING INSPECTION H -
Cleaning of Tubes from Inside before capping Air blowing 100% Free from foreign
material
3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.
1) NDE Procedures
+---+-----------+-------------------------------------------+
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P04
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER SIDE/BAFFLE/FURNACE SIDE/REAR WALL (FM) DATE : 11-06-2011
PAGE : 5
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P04
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER SIDE/BAFFLE/FURNACE SIDE/REAR WALL (FM) DATE : 11-06-2011
PAGE : 6
SAUDI ARAMCO
R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS
H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P05
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER TUBES DATE : 28-05-2011
PAGE : 1
CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS
1 MATERIAL IDENTIFICATION H H
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P05
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER TUBES DATE : 28-05-2011
PAGE : 2
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P05
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER TUBES DATE : 28-05-2011
PAGE : 3
Flow Area for Tubes O.D less than 3" Ball Test 100% Ball Size(Cold Bend)
={(0.9 OD-2.3SWT)-1
.6mm}
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P05
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER TUBES DATE : 28-05-2011
PAGE : 4
10 NDT SCHEDULE H R
Mock up of mating tubes of soot blower attach. with jig rod Verify 100% Drawing.
12 FINAL INSPECTION H H
Flow Area for Tubes O.D less than 3" Ball Test 100% Ball Size ={(0.9
OD-2.3SWT)-1.6mm}
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P05
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER TUBES DATE : 28-05-2011
PAGE : 5
13 SURFACE PREPARATION H -
14 PAINTING INSPECTION H -
Cleaning of tubes from inside before capping Air blowing 100% Free from foreign
material
3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P05
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER TUBES DATE : 28-05-2011
PAGE : 6
1) NDE Procedures
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS
+---+-----------+-------------------------------------------+
|Sr.|Control No.|Procedure Description |
+---+-----------+-------------------------------------------+
|1) |RT12 |Radiographic Examination of Welded Joints |
+---+-----------+-------------------------------------------+
|2) |PT1 |Liquid Penetrant Examination |
+---+-----------+-------------------------------------------+
|3) |MT3 |Magnetic Particle Examination |
+---+-----------+-------------------------------------------+
|4) |UT2 |Ultrasonic Examination Of Butt Welds |
+---+-----------+-------------------------------------------+
|5) |UT4 |Straight Beam Ultrasonic Examination of |
| | |Rolled Steel Plates |
+---+-----------+-------------------------------------------+
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P05
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER TUBES DATE : 28-05-2011
PAGE : 7
SAUDI ARAMCO
R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS
H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P09
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
CONVECTION BANK MODULE ASSEMBLY DATE : 04-11-2011
PAGE : 1
CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS
2 MATERIAL IDENTIFICATION H H
Review & Verification of Test Certificates & Drawing Review 100% Drawing, Material
Spec.
Cleaning of tubes from inside Air blowing 100% free from foreign
material
Cleaning of Header from inside Air Blowing 100% free from foreign
material
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P09
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
CONVECTION BANK MODULE ASSEMBLY DATE : 04-11-2011
PAGE : 2
Welding Insp.of Pressure Parts & Structural Attachments Visual 100% Drawing
7 PWHT H R
10 FINAL INSPECTION H H
Cleaning of header from inside before capping Air blowing 100% free from foreign
material
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P09
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
CONVECTION BANK MODULE ASSEMBLY DATE : 04-11-2011
PAGE : 3
11 PAINTING INSPECTION H -
Cleaning of header from inside before capping Air blowing 100% free from foreign
material
Capping / Blanking of all Tubes, Pipes, Openings Visual 100% All Tubes, Pipes,
Openings Shall be Co
vered /Capped
3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P09
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
CONVECTION BANK MODULE ASSEMBLY DATE : 04-11-2011
PAGE : 4
3. Manufacturing Records
4. All the required Inspection Records.
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS
1) NDE Procedures
+---+-----------+-------------------------------------------+
|Sr.|Control No.|Procedure Description |
+---+-----------+-------------------------------------------+
|1) |RT12 |Radiographic Examination of Welded Joints |
+---+-----------+-------------------------------------------+
|2) |PT1 |Liquid Penetrant Examination |
+---+-----------+-------------------------------------------+
|3) |MT3 |Magnetic Particle Examination |
+---+-----------+-------------------------------------------+
|4) |UT2 |Ultrasonic Examination Of Butt Welds |
+---+-----------+-------------------------------------------+
|5) |UT4 |Straight Beam Ultrasonic Examination of |
| | |Rolled Steel Plates |
+---+-----------+-------------------------------------------+
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P09
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
CONVECTION BANK MODULE ASSEMBLY DATE : 04-11-2011
PAGE : 5
SAUDI ARAMCO
R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS
H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P10
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
FINNED ECONOMISER ASSLY(FM) DATE : 09-09-2011
PAGE : 1
CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS
2 MATERIAL IDENTIFICATION H H
Review & Verification of Test Certificates & Drawing Review 100% Drawing, Material
Spec.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P10
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
FINNED ECONOMISER ASSLY(FM) DATE : 09-09-2011
PAGE : 2
Flow Area, (Cold Bending) Ball Test 100% Ball Size(Cold Bend)
(0.9OD-2.3SWT)-1.6mm
Flow Area, (Hot Bending) Ball Test 100% Ball Size(Hot Bend)(
0.85OD-2.3SWT)-3.2mm
Weld Inspection (Size & Finish) Visual 100% Drawing & Procedure
VT
Excess Penetration (Flow area- Cold bending) Ball Test 100% Ball Size(0.9OD-2.3S
WT)-1.6mm
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P10
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
FINNED ECONOMISER ASSLY(FM) DATE : 09-09-2011
PAGE : 3
Excess Penetration (Flow area- hot bending) Ball Test 100% Ball Size(0.85OD-2.3
SWT)-3.2mm
Cleaning of coils from inside Air blowing 100% free from foreign
material
Cleaning of Header from inside Air blowing 100% free from foreign
material
Weld Inspection (Size & Finish) Visual 100% Drawing & Procedure
VT
11 HYDROSTATIC TESTING H H
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P10
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
FINNED ECONOMISER ASSLY(FM) DATE : 09-09-2011
PAGE : 4
due date
Test pressure (on Pressure gauge) Visual 100% Test Pressure Shall
not exceed more than
6% at any time
Weld Inspection (Size & Finish) Visual 100% Drawing & Procedure
VT
15 FINAL INSPECTION H H
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P10
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
FINNED ECONOMISER ASSLY(FM) DATE : 09-09-2011
PAGE : 5
& Visual
16 PAINTING INSPECTION H -
Capping / Blanking of all Tubes, Pipes, Openings Visual 100% All Tubes, Pipes,
Openings Shall be Co
vered /Capped
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P10
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
FINNED ECONOMISER ASSLY(FM) DATE : 09-09-2011
PAGE : 6
3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.
SAUDI ARAMCO
1) NDE Procedures
+---+-----------+-------------------------------------------+
|Sr.|Control No.|Procedure Description |
+---+-----------+-------------------------------------------+
|1) |RT12 |Radiographic Examination of Welded Joints |
+---+-----------+-------------------------------------------+
|2) |PT1 |Liquid Penetrant Examination |
+---+-----------+-------------------------------------------+
|3) |MT3 |Magnetic Particle Examination |
+---+-----------+-------------------------------------------+
|4) |UT2 |Ultrasonic Examination Of Butt Welds |
+---+-----------+-------------------------------------------+
|5) |UT4 |Straight Beam Ultrasonic Examination of |
| | |Rolled Steel Plates |
+---+-----------+-------------------------------------------+
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P10
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
FINNED ECONOMISER ASSLY(FM) DATE : 09-09-2011
PAGE : 7
SAUDI ARAMCO
R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS
H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P11
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BARE TUBE ECONOMISER ASSLY(MODULAR TYPE) DATE : 04-11-2011
PAGE : 1
CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS
2 MATERIAL IDENTIFICATION H H
Review & Verification of Test Certificates & Drawing Review 100% Drawing, Material
Spec.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P11
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BARE TUBE ECONOMISER ASSLY(MODULAR TYPE) DATE : 04-11-2011
PAGE : 2
No blockage/obstacles inside the coil Ball Test 100% Free from foreign
Material
Cleaning of Header from inside Air Blowing 100% Free from foreign
Material
Weld Inspection (Size & Finish) Visual 100% Drawing & Procedure
VT
7 PWHT H R
8 HYDROSTATIC TESTING H H
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P11
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BARE TUBE ECONOMISER ASSLY(MODULAR TYPE) DATE : 04-11-2011
PAGE : 3
Test pressure (on Pressure gauge) Visual 100% Test Pressure Shall
not exceed more than
6% at any time
Weld Inspection (Size & Finish) Visual 100% Drawing & Procedure
VT
11 FINAL INSPECTION H H
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P11
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BARE TUBE ECONOMISER ASSLY(MODULAR TYPE) DATE : 04-11-2011
PAGE : 4
12 PAINTING INSPECTION H -
Capping / Blanking of all Tubes, Pipes, Openings Visual 100% All Tubes, Pipes,
Openings Shall be Co
vered /Capped
3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.
1) NDE Procedures
+---+-----------+-------------------------------------------+
|Sr.|Control No.|Procedure Description |
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P11
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BARE TUBE ECONOMISER ASSLY(MODULAR TYPE) DATE : 04-11-2011
PAGE : 5
+---+-----------+-------------------------------------------+
|1) |RT12 |Radiographic Examination of Welded Joints |
+---+-----------+-------------------------------------------+
SAUDI ARAMCO
+---+-----------+-------------------------------------------+
|3) |MT3 |Magnetic Particle Examination |
+---+-----------+-------------------------------------------+
|4) |UT2 |Ultrasonic Examination Of Butt Welds |
+---+-----------+-------------------------------------------+
|5) |UT4 |Straight Beam Ultrasonic Examination of |
| | |Rolled Steel Plates |
+---+-----------+-------------------------------------------+
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P11
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BARE TUBE ECONOMISER ASSLY(MODULAR TYPE) DATE : 04-11-2011
PAGE : 6
SAUDI ARAMCO
R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS
H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P12
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
RISERS,DOWN COMERS,SUPPLY TUBES/PIPES DATE : 19-09-2011
PAGE : 1
CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS
1 MATERIAL IDENTIFICATION H H
Review & Verification of Test Certificates & Drawing Review 100% Drawing, Material
Spec.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P12
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
RISERS,DOWN COMERS,SUPPLY TUBES/PIPES DATE : 19-09-2011
PAGE : 2
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P12
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
RISERS,DOWN COMERS,SUPPLY TUBES/PIPES DATE : 19-09-2011
PAGE : 3
Weld Size & Finish After Full Welding Visual 100% Drawing
UT of Full penetration welds >=10 NPS or above 25 thk UT/RT 100% Procedure UT/RT
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P12
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
RISERS,DOWN COMERS,SUPPLY TUBES/PIPES DATE : 19-09-2011
PAGE : 4
11 FINAL INSPECTION H H
12 PAINTING INSPECTION H -
Cleaning from inside before capping Air blowing 100% Free from foreign
material
Capping / Blanking of all Tubes, Pipes, Openings Visual 100% All Tubes, Pipes,
Openings Shall be Co
vered /Capped
3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.
1) NDE Procedures
+---+-----------+-------------------------------------------+
|Sr.|Control No.|Procedure Description |
+---+-----------+-------------------------------------------+
|1) |RT12 |Radiographic Examination of Welded Joints |
+---+-----------+-------------------------------------------+
|2) |PT1 |Liquid Penetrant Examination |
+---+-----------+-------------------------------------------+
|3) |MT3 |Magnetic Particle Examination |
+---+-----------+-------------------------------------------+
|4) |UT2 |Ultrasonic Examination Of Butt Welds |
+---+-----------+-------------------------------------------+
|5) |UT4 |Straight Beam Ultrasonic Examination of |
| | |Rolled Steel Plates |
+---+-----------+-------------------------------------------+
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P12
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
RISERS,DOWN COMERS,SUPPLY TUBES/PIPES DATE : 19-09-2011
PAGE : 6
SAUDI ARAMCO
R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS
H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P13
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
COILS (ECO/SH COILS) DATE : 04-11-2011
PAGE : 1
CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS
1 MATERIAL IDENTIFICATION H H
Review & Verification of Test Certificates & Drawing Review 100% Drawing, Material
Spec.
Flow Area for Cold Bending* Ball Test 100% Ball Size=(0.9OD-2.3
SWT)-1.6mm
Flow Area for Hot bending* Ball Test 100% Ball Size=(0.85OD-2.
3SWT)-3.2mm
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P13
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
COILS (ECO/SH COILS) DATE : 04-11-2011
PAGE : 2
Weld Soundness after full welding except P15E materials RT Code or Min Procedure RT
5%*
Note :RT & PMI for P15E materials to be carried after PWHT.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P13
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
COILS (ECO/SH COILS) DATE : 04-11-2011
PAGE : 3
Heat-Treatment Compliance to Code for 180 degree bend only HT Chart 100% Drg/HT Procedure
Flow Area, (Cold Bending)* Ball Test 100% Ball Size(Cold Bend)
(0.9OD-2.3SWT)-1.6mm
Flow Area, (Hot Bending)* Ball Test 100% Ball Size(Hot Bend)(
0.85OD-2.3SWT)-3.2mm
10 PAINTING INSPECTION H -
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P13
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
COILS (ECO/SH COILS) DATE : 04-11-2011
PAGE : 4
Cleaning of coils from inside before capping Air Blowing 100% Free from foreign
material
3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.
1) NDE Procedures
+---+-----------+-------------------------------------------+
|Sr.|Control No.|Procedure Description |
+---+-----------+-------------------------------------------+
|1) |RT12 |Radiographic Examination of Welded Joints |
+---+-----------+-------------------------------------------+
|2) |PT1 |Liquid Penetrant Examination |
+---+-----------+-------------------------------------------+
|3) |MT3 |Magnetic Particle Examination |
+---+-----------+-------------------------------------------+
|4) |UT2 |Ultrasonic Examination Of Butt Welds |
+---+-----------+-------------------------------------------+
|5) |UT4 |Straight Beam Ultrasonic Examination of |
| | |Rolled Steel Plates |
+---+-----------+-------------------------------------------+
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P13
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
COILS (ECO/SH COILS) DATE : 04-11-2011
PAGE : 5
R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production
cycle marked by the AI/Customer/TPI. Record of inspection is maintained
and will be made available to AI/Customer/TPI for review during next
HOLD/WITNESS stage Inspection,as applicable.
H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P15
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
HEADERS DATE : 04-11-2011
PAGE : 1
CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS
1 MATERIAL IDENTIFICATION H H
Review & Verification of Test Certificates & Drawing Review 100% Drawing, Material
Spec.
Flow Area for Cold Bending* Ball Test 100% Ball Size=(0.9OD-2.3
SWT)-1.6mm
Flow Area for Hot bending* Ball Test 100% Ball Size=(0.85OD-2.
3SWT)-3.2mm
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P15
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
HEADERS DATE : 04-11-2011
PAGE : 2
Weld Size & Finish After Full Welding Visual 100% Drawing & Procedure
VT
5 BUTT WELD SETUP & WELDING FOR HDR PIPE, (IF ANY) H H
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P15
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
HEADERS DATE : 04-11-2011
PAGE : 3
7 DRILLING INSPECTION H -
Peripheral edges of End cover if mfg.from plate** PT/MT 100% Procedure PT/MT
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P15
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
HEADERS DATE : 04-11-2011
PAGE : 4
Weld Size & Finish After Full Welding Visual 100% Drawing
UT of Full penetration welds >=10 NPS or above 25 thk UT/RT 100% Procedure UT/RT
11 WELDING OF ABOVE H R
Butt Weld Soundness after Final Welding except P15 materials RT 100% Procedure RT
Peripheral edges & remaining exposed surface of weld jt.** PT/MT 100% Procedure PT/MT
Weld Inspection (Size & Finish) Measurement 100% Drawing & Procedure
& Visual VT
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P15
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
HEADERS DATE : 04-11-2011
PAGE : 5
PMI for Alloy Verificaion of Accessible welds PMI Check 100% Procedure PMI/
Specs.
PMI for Alloy Verificaion of Parent Material PMI Check Random Procedure PMI/
Specs.
14 PWHT H R
NDE of all weld joints (for alloy steel hdr only) MT/PT 100% Procedure MT/PT
Butt Weld Soundness after Full Welding for P15E materials RT 100% Procedure RT
17 FINAL INSPECTION H H
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P15
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
HEADERS DATE : 04-11-2011
PAGE : 6
Cleaning of header from inside before capping Air blowing 100% free from foreign
material
18 PAINTING INSPECTION H -
Cleaning of header from inside before capping Air blowing 100% free from foreign
material
Capping / Blanking of all Tubes, Pipes, Openings Visual 100% All Tubes, Pipes,
Openings Shall be Co
vered /Capped
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P15
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
HEADERS DATE : 04-11-2011
PAGE : 7
3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.
SAUDI ARAMCO
1) NDE Procedures
+---+-----------+-------------------------------------------+
|Sr.|Control No.|Procedure Description |
+---+-----------+-------------------------------------------+
|1) |RT12 |Radiographic Examination of Welded Joints |
+---+-----------+-------------------------------------------+
|2) |PT1 |Liquid Penetrant Examination |
+---+-----------+-------------------------------------------+
|3) |MT3 |Magnetic Particle Examination |
+---+-----------+-------------------------------------------+
|4) |UT2 |Ultrasonic Examination Of Butt Welds |
+---+-----------+-------------------------------------------+
|5) |UT4 |Straight Beam Ultrasonic Examination of |
| | |Rolled Steel Plates |
+---+-----------+-------------------------------------------+
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P15
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
HEADERS DATE : 04-11-2011
PAGE : 8
SAUDI ARAMCO
R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS
H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P16
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
HEADERS (SHOP ASSLY) DATE : 04-11-2011
PAGE : 1
CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS
1 MATERIAL IDENTIFICATION H H
Review & Verification of Test Certificates & Drawing Review 100% Drawing, Material
Spec.
Weld Size & Finish After Full Welding Visual 100% Drawing & Procedure
VT
3 BUTT WELD SETUP & WELDING FOR HDR PIPE, (IF ANY) H H
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P16
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
HEADERS (SHOP ASSLY) DATE : 04-11-2011
PAGE : 2
Peripheral edges of End cover if mfg.from plate** PT/MT 100% Procedure PT/MT
6 DRILLING INSPECTION H -
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P16
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
HEADERS (SHOP ASSLY) DATE : 04-11-2011
PAGE : 3
Weld Size & Finish After Full Welding Visual 100% Drawing
UT of Full penetration welds >=10 NPS or above 25 thk UT/RT 100% Procedure UT2/RT
9 WELDING OF ABOVE H R
Peripheral edges & remaining exposed surface of weld jt.** PT/MT 100% Procedure PT/MT
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P16
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
HEADERS (SHOP ASSLY) DATE : 04-11-2011
PAGE : 4
Weld Inspection (Size & Finish) Measurement 100% Drawing & Procedure
& Visual VT
PMI for Alloy Verificaion of Accessible welds PMI Check 100% Procedure PMI/
Specs.
PMI for Alloy Verificaion of Parent Material PMI Check Random Procedure PMI/
Specs.
3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P16
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
HEADERS (SHOP ASSLY) DATE : 04-11-2011
PAGE : 5
3. Manufacturing Records
4. All the required Inspection Records.
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS
1) NDE Procedures
+---+-----------+-------------------------------------------+
|Sr.|Control No.|Procedure Description |
+---+-----------+-------------------------------------------+
|1) |RT12 |Radiographic Examination of Welded Joints |
+---+-----------+-------------------------------------------+
|2) |PT1 |Liquid Penetrant Examination |
+---+-----------+-------------------------------------------+
|3) |MT3 |Magnetic Particle Examination |
+---+-----------+-------------------------------------------+
|4) |UT2 |Ultrasonic Examination Of Butt Welds |
+---+-----------+-------------------------------------------+
|5) |UT4 |Straight Beam Ultrasonic Examination of |
| | |Rolled Steel Plates |
+---+-----------+-------------------------------------------+
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P16
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
HEADERS (SHOP ASSLY) DATE : 04-11-2011
PAGE : 6
SAUDI ARAMCO
R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS
H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P17
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
ATTEMPERATOR ASSLY DATE : 02-06-2011
PAGE : 1
CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS
1 MATERIAL IDENTIFICATION H H
Review & Verification of Test Certificates & Drawing Review 100% Drawing, Material
Spec.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P17
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
ATTEMPERATOR ASSLY DATE : 02-06-2011
PAGE : 2
6 WELDING OF ABOVE H R
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P17
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
ATTEMPERATOR ASSLY DATE : 02-06-2011
PAGE : 3
Weld Inspection after full welding Visual 100% Drawing & Procedure
VT
PMI for Alloy Verification of accessible welds PMI Check 100% Procedure PMI /
Specs.
PMI for Alloy Verification of Parent Material PMI Check Random Procedure PMI /
Specs.
12 PWHT H R
NDT on all welds for Alloy steel PT/MT 100% Procedure PT/MT
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P17
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
ATTEMPERATOR ASSLY DATE : 02-06-2011
PAGE : 4
14 FINAL INSPECTION H H
Cleaning of header from inside before capping Air blowing 100% free from foreign
material
15 PAINTING INSPECTION H -
Cleaning from inside before capping Air blowing 100% Free from foreign
material
Capping / Blanking of all Tubes, Pipes, Openings Visual 100% All Tubes, Pipes,
Openings Shall be Co
vered /Capped
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P17
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
ATTEMPERATOR ASSLY DATE : 02-06-2011
PAGE : 5
3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.
1) NDE Procedures
+---+-----------+-------------------------------------------+
|Sr.|Control No.|Procedure Description |
+---+-----------+-------------------------------------------+
|1) |RT12 |Radiographic Examination of Welded Joints |
+---+-----------+-------------------------------------------+
|2) |PT1 |Liquid Penetrant Examination |
+---+-----------+-------------------------------------------+
|3) |MT3 |Magnetic Particle Examination |
+---+-----------+-------------------------------------------+
|4) |UT2 |Ultrasonic Examination Of Butt Welds |
+---+-----------+-------------------------------------------+
|5) |UT4 |Straight Beam Ultrasonic Examination of |
| | |Rolled Steel Plates |
+---+-----------+-------------------------------------------+
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P17
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
ATTEMPERATOR ASSLY DATE : 02-06-2011
PAGE : 6
SAUDI ARAMCO
R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS
H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P20
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
INTEGRAL& NON INTEGRAL PIPING - IBR DATE : 02-06-2011
PAGE : 1
CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS
1 MATERIAL IDENTIFICATION H H
Verification of MTC with Material Specs. & Drg Review 100% Drg / Matrl.Specs.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P20
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
INTEGRAL& NON INTEGRAL PIPING - IBR DATE : 02-06-2011
PAGE : 2
Matching
** 5% per welder
UT of Full penetration welds >=10 NPS or above 25 thk UT/RT 100% Procedure UT/RT
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P20
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
INTEGRAL& NON INTEGRAL PIPING - IBR DATE : 02-06-2011
PAGE : 3
PMI for Alloy Verification of welds PMI Check 10% Random Procedure PMI/ Spec.
PMI for Alloy Verification of Parent Material PMI Check Random Procedure PMI/ Spec.
10 FINAL INSPECTION H H
11 PAINTING INSPECTION H -
Site weld joints to be kept unpainted @1" portion Visual 100% Apply Packing tape
or Cap the ends afte
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P20
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
INTEGRAL& NON INTEGRAL PIPING - IBR DATE : 02-06-2011
PAGE : 4
r greasing
Cleaning from inside before capping/blanking Air blowing 100% Free from foreign
material
Capping / Blanking of all Pipes, Openings Visual 100% All Pipes, Openings
Shall be Covered /Ca
pped
3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.
1) NDE Procedures
+---+-----------+-------------------------------------------+
|Sr.|Control No.|Procedure Description |
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P20
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
INTEGRAL& NON INTEGRAL PIPING - IBR DATE : 02-06-2011
PAGE : 5
+---+-----------+-------------------------------------------+
|1) |RT12 |Radiographic Examination of Welded Joints |
+---+-----------+-------------------------------------------+
SAUDI ARAMCO
+---+-----------+-------------------------------------------+
|3) |MT3 |Magnetic Particle Examination |
+---+-----------+-------------------------------------------+
|4) |UT2 |Ultrasonic Examination Of Butt Welds |
+---+-----------+-------------------------------------------+
|5) |UT4 |Straight Beam Ultrasonic Examination of |
| | |Rolled Steel Plates |
+---+-----------+-------------------------------------------+
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /P20
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
INTEGRAL& NON INTEGRAL PIPING - IBR DATE : 02-06-2011
PAGE : 6
SAUDI ARAMCO
R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS
H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPASME /P21
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
NON-INTEGRAL PIPING DATE : 16-06-2011
PAGE : 1
CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS
1 MATERIAL IDENTIFICATION H
Verification of MTC with Material Specs. & Drg Review 100% Drg / Matrl.Specs.
PMI for Alloy Verification of welds PMI Check 10% Random Procedure PMI
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPASME /P21
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
NON-INTEGRAL PIPING DATE : 16-06-2011
PAGE : 2
PMI for Alloy Verification of welds PMI Check 10% Random Procedure PMI/ Spec.
PMI for Alloy Verification of Parent Material PMI Check Random Procedure PMI/ Spec.
PT/MT on all accessible alloy steel welds PT/MT 100% Procedure PT1/MT3
Weld soundness of Butt welds for P-Nos 3,4,5 materials if - RT Code ASME B31.3 Para
341.3
Hardness of production weld,hot bend & hot formed piping- Test Code ASME B31.3 para
331.1.7
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPASME /P21
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
NON-INTEGRAL PIPING DATE : 16-06-2011
PAGE : 3
9 PAINTING INSPECTION H
Paint Shade, Make, Batch No., Expiry Date Visual 100% Drawing, Painting
Specs.,Application b
efore Expiry
3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPASME /P21
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
NON-INTEGRAL PIPING DATE : 16-06-2011
PAGE : 4
SAUDI ARAMCO
R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS
H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N01
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
DUCTS / HOPPERS DATE : 28-07-2011
PAGE : 1
CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS
1 MATERIAL IDENTIFICATION H -
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N01
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
DUCTS / HOPPERS DATE : 28-07-2011
PAGE : 2
Completion of stiffner/ spider Welding (As applicable) Visual 100% Drawing/ Suitable
for Handling
Weld Inspection (Size & Finish) Visual 100% Drawing & Procedure
VT
4 SURFACE PREPARATION H -
5 PAINTING INSPECTION H -
Paint Shade, Make, Batch No., Expiry Date Verify 100% Drawing, Painting
Specs., Application
before Expiry
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N01
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
DUCTS / HOPPERS DATE : 28-07-2011
PAGE : 3
3.0 NOTES :
IT IS MANDATORY FOR MANUFACTURER'S QUALITY CONTROL TO CARRY OUT
INSPECTION OF ALL THE STAGES COVERED IN THIS ITP.
R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production
cycle marked by the AI/Customer/TPI. Record of inspection is maintained
and will be made available to AI/Customer/TPI for review during next
HOLD/WITNESS stage Inspection,as applicable.
H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N02
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
DAMPER DATE : 28-07-2011
PAGE : 1
CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS
1 MATERIAL IDENTIFICATION H
3 PAINTING INSPECTION H
Paint Shade, Make, Batch No., Expiry Date Visual 100% Drawing, Painting
Specs., Application
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N02
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
DAMPER DATE : 28-07-2011
PAGE : 2
Before Painting
3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N02
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
DAMPER DATE : 28-07-2011
PAGE : 3
SAUDI ARAMCO
R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS
H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N03
SAUDI ARAMCO
REVISION NO.: 1
WELDING PROCEDURE SPECIFIC
EXPANSION JOINTS DATE : 22-10-2011
PAGE : 1
CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS
1 MATERIAL IDENTIFICATION H
Welding by GTAW Process for sheet thk <= 2mm Visual 100% Weld
procedure/specs.
Flange I/S Dimensions, Hole Pitches, Height, Diagonals Measurement 100% Drawing
Location & Dimensions of Shear Transfer Pin Arrangement Measurement 100% Drawing
& Visual
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N03
SAUDI ARAMCO
REVISION NO.: 1
WELDING PROCEDURE SPECIFIC
EXPANSION JOINTS DATE : 22-10-2011
PAGE : 2
4 PAINTING INSPECTION H
Paint Shade, Make, Batch No., Expiry Date Visual 100% Drawing, Painting
Specs.,Application b
efore Expiry
3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N03
SAUDI ARAMCO
REVISION NO.: 1
WELDING PROCEDURE SPECIFIC
EXPANSION JOINTS DATE : 22-10-2011
PAGE : 3
SAUDI ARAMCO
R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS
H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N04
SAUDI ARAMCO
REVISION NO.: 1
WELDING PROCEDURE SPECIFIC
AIR FLOW MEASURING DEVICE (AEROFOIL) DATE : 22-10-2011
PAGE : 1
CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS
1 MATERIAL IDENTIFICATION H
3 ASSEMBLY INSPECTION H
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N04
SAUDI ARAMCO
REVISION NO.: 1
WELDING PROCEDURE SPECIFIC
AIR FLOW MEASURING DEVICE (AEROFOIL) DATE : 22-10-2011
PAGE : 2
Paint Shade, Make, Batch No., Expiry Date Visual 100% Drawing, Painting
Specs.,Application b
efore Expiry
3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N04
SAUDI ARAMCO
REVISION NO.: 1
WELDING PROCEDURE SPECIFIC
AIR FLOW MEASURING DEVICE (AEROFOIL) DATE : 22-10-2011
PAGE : 3
SAUDI ARAMCO
R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS
H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N05
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
STACK DATE : 28-07-2011
PAGE : 1
CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS
1 MATERIAL IDENTIFICATION H
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N05
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
STACK DATE : 28-07-2011
PAGE : 2
Match Drilling of Base Ring with Template Verify 100% Drawing,Refer Note
4 SETUP OF L-SEAMS H
5 SETUP OF C-SEAMS H
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N05
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
STACK DATE : 28-07-2011
PAGE : 3
Base Ring Squareness with respect to Shell Plumb 100% Within 3mm
Assly of Platform & Ladders on Stack for bolted construction Verify 100% Drawing
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N05
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
STACK DATE : 28-07-2011
PAGE : 4
11 PAINTING INSPECTION H
Paint Shade, Make, Batch No., Expiry Date Visual 100% Drawing, Painting
Specs., Application
before Expiry
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N05
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
STACK DATE : 28-07-2011
PAGE : 5
3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.
SAUDI ARAMCO
Shop template shall have only pilot drill of 8mm size & reference
of final drill size shall be mentioned on it.This drilling shall be done
along with base plate.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N05
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
STACK DATE : 28-07-2011
PAGE : 6
SAUDI ARAMCO
R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS
H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N42
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER CASING DATE : 28-07-2011
PAGE : 1
CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS
1 MATERIAL IDENTIFICATION H
Weld Inspection (Size & Finish) Visual 100% Drawing & Procedure
VT
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N42
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER CASING DATE : 28-07-2011
PAGE : 2
Paint Shade, Make, Batch No., Expiry Date Visual 100% Drawing, Painting
Specs.,Application b
efore Expiry
3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N42
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER CASING DATE : 28-07-2011
PAGE : 3
SAUDI ARAMCO
R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS
H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N51
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER STRUCTURE DATE : 28-07-2011
PAGE : 1
CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS
1 MATERIAL IDENTIFICATION H
Gap Between Base plate and Column Measurement 100% Avg.Gap 0.5to1mm &
& Visual Max.2mm at Local Spo
ts
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N51
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER STRUCTURE DATE : 28-07-2011
PAGE : 2
Total Height of Column Measurement 100% 5mm Upto 10mtr & 8mm
max.
Total Height of Column Measurement 100% 5mm Upto 10mtr & 8mm
max.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N51
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER STRUCTURE DATE : 28-07-2011
PAGE : 3
- Frame by Frame
- Platform stages
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N51
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER STRUCTURE DATE : 28-07-2011
PAGE : 4
Weld Soundness of fillet welds for plate fabricated girders PT Min.10% * Procedure PT
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N51
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER STRUCTURE DATE : 28-07-2011
PAGE : 5
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N51
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER STRUCTURE DATE : 28-07-2011
PAGE : 6
Aesthetics-Weld tacks,Surface Marks, Sharp Corners Visual 100% Free from Surface
Discontinuities
16 SURFACE PREPARATION H
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N51
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER STRUCTURE DATE : 28-07-2011
PAGE : 7
17 PAINTING INSPECTION H
Paint Shade, Make, Batch No., Expiry Date Visual 100% Drawing, Painting
Specs.,Application b
efore expiry
3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N51
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER STRUCTURE DATE : 28-07-2011
PAGE : 8
SAUDI ARAMCO
R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS
H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N52
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
FOUNDATION BOLTS & PACKER PLATES DATE : 28-07-2011
PAGE : 1
CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS
1 MATERIAL IDENTIFICATION H
Weld Inspection (Size & Finish) of anchoring Plates/Rods Measurement 10% Drawing
& Visual
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N52
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
FOUNDATION BOLTS & PACKER PLATES DATE : 28-07-2011
PAGE : 2
4 PAINTING INSPECTION H
3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N52
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
FOUNDATION BOLTS & PACKER PLATES DATE : 28-07-2011
PAGE : 3
SAUDI ARAMCO
R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS
H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N53
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
GRATINGS(GRILLS) DATE : 28-07-2011
PAGE : 1
CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS
1 MATERIAL IDENTIFICATION H
2 DIMENSIONAL INSPECTION H
Ups & Downs of Load Members & Secondary Members Measurement 10% Within 1mm
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N53
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
GRATINGS(GRILLS) DATE : 28-07-2011
PAGE : 2
Paint Shade, Make, Batch No., Expiry Date Visual 100% Drawing, Painting
Specs.,Application b
efore expiry
Visual Inspection for Galvanised items (if Applicable) Visual 10% IS:2629
DFT of zinc coat for Galvanised items (If applicable) Measurement Random Drawing/IS:2629
Identification Marking (Grill Size, Job No., Mark no.) Visual 100% Drawing
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N53
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
GRATINGS(GRILLS) DATE : 28-07-2011
PAGE : 3
3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.
SAUDI ARAMCO
R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production
cycle marked by the AI/Customer/TPI. Record of inspection is maintained
and will be made available to AI/Customer/TPI for review during next
HOLD/WITNESS stage Inspection,as applicable.
H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N54
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
DRUM INTERNALS & EXTERNALS DATE : 28-07-2011
PAGE : 1
CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS
1 MATERIAL IDENTIFICATION H XX
4 FINAL INSPECTION H XX
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N54
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
DRUM INTERNALS & EXTERNALS DATE : 28-07-2011
PAGE : 2
Application of Rust Prevension Oil on Drum Internals Visual 100% TBW Practice
3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N54
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
DRUM INTERNALS & EXTERNALS DATE : 28-07-2011
PAGE : 3
SAUDI ARAMCO
R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS
H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.
XX INTERNAL INSPECTION Inspection option for 'XX' points will be excercised by Thermax/Vendor QC and
will not applicable to TPI/Client Inspection.
*INSP.BY /TPI
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N55
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER BASE FRAME(FM) DATE : 28-07-2011
PAGE : 1
CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS
1 MATERIAL IDENTIFICATION H
Location & Size of Tell-Tale Hole & Squareness Measurement 100% Drawing
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N55
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER BASE FRAME(FM) DATE : 28-07-2011
PAGE : 2
4 FINAL INSPECTION H
5 PAINTING INSPECTION H
Paint Shade, Make, Batch No., Expiry Date Visual 100% Drawing, Painting
Specs., Application
before Expiry
3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N55
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
BOILER BASE FRAME(FM) DATE : 28-07-2011
PAGE : 3
SAUDI ARAMCO
IT IS MANDATORY FOR MANUFACTURER'S QUALITY CONTROL TO CARRY OUT WELDING PROCEDURE SPECIFICATIONS
R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production
cycle marked by the AI/Customer/TPI. Record of inspection is maintained
and will be made available to AI/Customer/TPI for review during next
HOLD/WITNESS stage Inspection,as applicable.
H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N56
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
ECONOMISER CASING & STRUCTURE DATE : 28-07-2011
PAGE : 1
CUSTOMER :
SAUDI ARAMCO
WELDING PROCEDURE SPECIFICATIONS
1 MATERIAL IDENTIFICATION H
2 INSPECTION OF COLUMNS H
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N56
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
ECONOMISER CASING & STRUCTURE DATE : 28-07-2011
PAGE : 2
Thread Length & Nut Fitment Verify 100% Free Fitment with
Stud/U-Bolt Threads
6 INSP.OF CASING H
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N56
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
ECONOMISER CASING & STRUCTURE DATE : 28-07-2011
PAGE : 3
Paint Shade, Make, Batch No., Expiry Date Visual 100% Drawing, Painting
Specs.,Application b
efore Expiry
3.0 NOTES :
1) Following documents, as applicable are to be reviewed during inspection.
INSPECTION & TEST PLAN (QA PLAN) FOR CONTROL NO. : ITP/ERPLN /N56
SAUDI ARAMCO
REVISION NO.: 0
WELDING PROCEDURE SPECIFIC
ECONOMISER CASING & STRUCTURE DATE : 28-07-2011
PAGE : 4
SAUDI ARAMCO
R Record Review Point RECORD REVIEW POINT is a recording operation in the operation / production WELDING PROCEDURE SPECIFICATIONS
H Hold Point HOLD POINT is defined as a verification of the operation by the requesting
authority AI,Customer/TPI.Further processing is prohibited until acceptance
of the operation & documentation is completed by the requesting authority.