Project:
Design & Build Coastal Village Office Building, TRSDC, KSA
Document: Doc Ref: R03-C03B01-MAG-MTS-CI-0004 Rev.01
Method Statement for Termite control
DISCIPLINE: CIVIL
Contents
1. Scope of work
2. Purpose
3. Abbreviations
4. References
5. Responsibilities
6. Safety
7. Procedure
8. Attachments
Page 2 of 8
Design & Build Contractor: Client:
Al Majal Al Arabi Company The Red Sea Development
Company
Project:
Design & Build Coastal Village Office Building, TRSDC, KSA
Document: Doc Ref: R03-C03B01-MAG-MTS-CI-0004 Rev.01
Method Statement for Termite control
1. Scope of work
The scope of this Method Statement is to define all the procedures and inspections to be
followed during Termite Control at RS18-009 Design & Build Management Village Office
Building Project, in compliance with the project specifications and standards procedures.
2. Purpose
The purpose of this Method Statement is to describe the quality control procedure to be
followed during the Termite control at the mentioned project. Also, to ensure that the
proposed material and workmanship to be used at the site for termite control works are
complying and in accordance with TRSDC requirements.
3. Abbreviations
ITP : Inspection & Test Plan
PPE : Personal Protective equipment
QA/QC : Quality Assurance/Quality Control
ASTM : American Society for testing and materials
HSE : Health, Safety and Environment
4. References:
Approved design drawings
Construction Environmental Management Plan
MAG HSE PLAN R03-C03B01-MAG-PLN-HS-0003 Rev 3
MATERIAL APPROVAL NO. R03-C03B01-MAG-PRQ-CI-0004
TRSDC Employer’s HSE requirements
5. Responsibilities
Ensures that the content of this method statement is understood and implemented
at all times.
Coordinate with the site engineer to ensure that the necessary resources to
implement the approved Method Statement have been allocated to the task.
Page 3 of 8
Design & Build Contractor: Client:
Al Majal Al Arabi Company The Red Sea Development
Company
Project:
Design & Build Coastal Village Office Building, TRSDC, KSA
Document: Doc Ref: R03-C03B01-MAG-MTS-CI-0004 Rev.01
Method Statement for Termite control
Determine all the requirements needed in order to comply with safety standards and
regulations as required.
Will ensure that the site preparation activities are conducted according to the
approved Method Statement and project contract documents.
Shall be responsible of the implementation of this procedure.
Will ensure that the materials being delivered and used are in accordance with the
project specifications and approved material submittal.
Shall be responsible for the inspection, preparation of all documents and compiling
them for the inclusion in the final documentation packaged.
Will ensure that all the activities related to the specified task are being followed
safely and all workers are wearing PPE.
Identify and take measure control the risks associated with the hazard
Pre task briefing shall be provided by the relevant supervisor or site engineer
prior to start of work activity and to be recorded.
It will be ensured at all time that termite control shall be carried out under the
control of competent works supervisor. Assigned supervisor shall have extensive
experience in termite prevention and control works undertaken
Shall explain the Method Statement for his subordinates and responsible for
executing the works in accordance with the method statement.
To ascertain that the work is being carried out as per the instructions of site
engineer and in conformance with the approved material and manufacturers
recommendation & specs.
Also to instruct workers to eliminate hazards and encourage safety actions or
initiatives.
Page 4 of 8
Design & Build Contractor: Client:
Al Majal Al Arabi Company The Red Sea Development
Company
Project:
Design & Build Coastal Village Office Building, TRSDC, KSA
Document: Doc Ref: R03-C03B01-MAG-MTS-CI-0003 Rev.01
Method Statement for Termite control
6. Safety
Task specific safety briefing / toolbox talk has been conducted by HSE dept. prior
to start of work activity.
Safety officer and direct supervisor will ensure that PPE are wore by site personnel
at all times during this activity.
Safety officer shall ensure that all workers and workplaces are safe.
All personnel must adhere to the safety rules and regulations at the site.
Termite control permit has been issued prior to commencing of termite control
Hazard identification and control measures have been implemented.
All excavations must be barricaded. Type of barricade required will depend on the
depth as per the TRSDC safety requirements.
Warning signs, safety tapes, safety cones, safety nets, signboards and safety
barriers will be placed around the designated excavation areas .
7. Procedures
Mixing container
Spray machine
Water truck,
Pressure pump sprayer with adequate capacity
Various tradesmen hand and power tools.
7.2.1 General
1. All applicator and handlers will be professional and must wear a dust/mist filtering
approved respirator. Termite control is usually a job for the licensed pest management
professional.
2. Clean water for eyewash will be provided and should be available for eyewash, face
wash and body wash all the time in case of emergency.
Page 5 of 8
Design & Build Contractor: Client:
Al Majal Al Arabi Company The Red Sea Development
Company
Project:
Design & Build Coastal Village Office Building, TRSDC, KSA
Document: Doc Ref: R03-C03B01-MAG-MTS-CI-0003 Rev.01
Method Statement for Termite control
3. Applicator/ handlers must wear the long sleeved shirt and long pants, safety shoes plus
sock chemical resistant gloves.
4. The Storage of the SNIPER (FIPRONOL 5% w/v) SC will be in its original container
shall be kept in the designated area approved by TRSDC.
5. The treatment will be done in accordance with the manufacturer recommendation and
shall be approved by TRSDC.
6. The MSDS and Technical data sheet is attached for the easy reference. All the work
activity sequence shall be accordance to manufacturer’s recommendation.
Page 6 of 8
Design & Build Contractor: Client:
Al Majal Al Arabi Company The Red Sea Development
Company
Project:
Design & Build Coastal Village Office Building, TRSDC, KSA
Document: Doc Ref: R03-C03B01-MAG-MTS-CI-0003 Rev.01
Method Statement for Termite control
Page 7 of 8
Design & Build Contractor: Client:
Al Majal Al Arabi Company The Red Sea Development
Company
Project:
Design & Build Coastal Village Office Building, TRSDC, KSA
Document: Doc Ref: R03-C03B01-MAG-MTS-CI-0003 Rev.01
Method Statement for Termite control
Application Rate: -
The following table can be used as this rate
16. Use low nozzle pressure of 25 psi or less, do not treat the entire crawl space unless
covered with untreated soil or barrier and do not treat areas intended for use as plenums.
17. The treated area will be covered by the polyethylene vapor sheet immediately after
spraying finished, Polyethylene sheet will be removed as the concrete pouring activity
commence.
18. The concrete pouring activity will start immediately after the treatment finished.
19. The pouring of concrete shall be finished within 24 hours of the treatment.
8. Attachment
Page 8 of 8
Design and Built Coastal Village Office Building, TRSDC, KSA
PROJECT: RS18-009 Design & Build Management Village Office Building, TRSDC, KSA
ASSESSED BY
REV. No: 00
(NAME): SIGNATURE:
REVIEWED BY (MAG HSEM)
(NAME): REV. DATE:
SIGNATURE:
APPROVED BY
(NAME):
SIGNATURE:
Inspection & Test Plan I&TP APPROVED DATE DISCIPLINE
INSPECTION RESPONSIBILITY
ITEM
OUTPUT TASK / ACTIVITY Reference Checklist Employer REMARKS
NO. Contractor
Representative
1.0 DOCUMENT REVIEW
Manufacturers
1.1 Pre Qualification Documents and MSDS data sheet NA R R Approved document trnasmittal
catalouge
Approved method
1.2 Method statement NA R R
statement
TRSDC
1.3 Works permits NA R R
Requirements
Manufacturers
3.1 Spraying Spray nozzle pressure of 25 psi N/A R R
recommendation
The treated area will be covered by the polyethylene vapor sheet Manufacturers
3.1 Protection N/A R R
immediately. recommendation
4.0 PRE-COMMISSIONING
GENERAL NOTES
1. The Work Inspection Request (WIR) and the laboratory reports shall only be transmitted through PMIS - Aconex electronic platform.
2. The material should be approved by TRSDC
The first three incidents of each Inspection or testing activity listed require 100 % participation by the Consultant. After this period, the Employer or the Consultanat may adjust the levels of the Employer participation
1
upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
3 Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC
organization representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization
4
representative in attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Consultant.
LEGEND
H Hold Point for QC Inspection/ Test R Review Documents and Reports
W Witness Inspection/Test
S Surveillance