You are on page 1of 6

Work Order Status For C

Order placing Comprative


S.No. Item Procurement status Order is given for
Status statement Status

1 CABLE TRAY In process No NO

2 CABLE In process No NO

3 TRANSFORMER In process No No

4 H.T PANNEL In process No No

5 D.G SET In process No No

6 L.T PANNEL In process No No

7 RISING MAIN In process No No

8 UPS In process No No

9 FIRE FIGHTING In process No No

10 LIGHTS In process No No

11 STP In process No No

12 PLUMBING WORK In process No No


13 ELECTRICAL WORK In process No No

14 CCTV In process No No
k Order Status For CUTTAK.
Order is given for Quotation Received from Quotation to be Received from

Date

MEM,MME CTM ENGINEERING, RM CON, RAJESH RANNA

CABLE SALES INDIA, AB PAL, HAVELLS,


ASHOAK ENTERPRISES
SKYTONE, MAX ENGINEERING

SHRI NURSINGSAHAY, SUPERTECH CONTROL


SYSTEM, FOURBEE MACHINEX, GKM POWER

SHRI NURSINGSAHAY, SUPERTECH CONTROL


SYSTEM, FOURBEE MACHINEX, GKM POWER

SHRI NURSINGSAHAY, SUPERTECH CONTROL


SYSTEM, FOURBEE MACHINEX, GKM POWER

PRECISION, EXPERT ENGINEERING, SUDHIR


POWER, SUPERTECH CONTROL SYSTEM,
PATEL & COMPANY (ABB), SPC

JHONSON CONTROL, M//S FIRE SERVICES, 7


STAR, NATIONAL CONSTRUCTION, SMART
SECURITY, PARAMOUNT BUILDING
SOLLUTIONS, ANAND FIRE INDUSTRIES,
PERFECT ENGINEERING GROUP, KALYAN
ENGINEERING GROUP

BIMAL WATER SOLLUTION, ECO WATER


SOLLUTION, PURE WATER TECH PVT. LTD.

7 STAR, SMART SECURITY, PERFECRT


ENGINEERING GROUP, ANAND FIRE
INDUSTRIES, VINAYAK SANITATION
INDIA TECH, GP TECH, TDG INFRA, A.T
ENGINEERING, MARS DEVELOPMENT, DEW
ELECTRICAL WORKS

SYSTEMATIC, CONNECTED CLOUD, L.V


ENGINEERING, SATYA AIRCON, PRIMA SONIC
Remark