CONSTRUCTION PLAN TPSS

HALIM 2
EPCC LRT JABODEBEK POWER SUPPLY SYSTEM
PT. ADHI KARYA – EPC DEPARTMENT
SCOPE OF WORK
1. 20 KV MV Switchgear 8. Negative Bar Return Cubicle 15. Power PLC
2. Traction Transformer 9. Auxilary Transformer
16. Cable tray
3. DC Rectifier 10. LVMDP
17. Cable
4. DC Switchgear 11. UPS
5. TBS – UP 12. DC Charger 18. Grounding, & lightning
protection
6. TBS – DOWN 13. Battery For UPS
7. VLD 14. Battery For DC System

EPCC LRT JABODEBEK POWER SUPPLY SYSTEM 2


TYPICAL WORK STEP
Equipment
On base Setting/alignment
Mobilization Internall wiring
Lifting equipment equipment to jointing Preservation
equipment equpment
position equipment

Cable

Mobilization Insulation test,


Pulling cable Termination
material & continuity

Cable tray

Mobilization Fabrication
Instal support Instal cable tray
material support

Grounding, & lightning protection


Instal
Mobilization
Excavation grounding, & Earthing test
material
lightning

EPCC LRT JABODEBEK POWER SUPPLY SYSTEM 3


PREPARATION BEFORE INSTALLATION
1. Drawing for construction

2. Procedure installation

3. Readinees equipment and material

4. Readinees man power

5. Readinees heavy equipment and tools

6. Readinees civil work


Description Remark
Door Installation Finish
Leveling floor in switchgear room Finish
No hot work in switchgear room Finish
Plaster Aci inside switchgear room Finish

EPCC LRT JABODEBEK POWER SUPPLY SYSTEM 4


SQUENCE WORK
• Equipment mobilization from sarinah warehouse to TPSS Halim 2

EPCC LRT JABODEBEK POWER SUPPLY SYSTEM 5


SCHEDULE
1. DC Charger
2. UPS
3. Negative RB
Support tray 4. Aux Trafo
Cable tray
fabrication 5. DC Rectifier
installation
6. DC Switchgear

May 18 June 18 July 18 August 18 September 18 October 18 November 18 Desember 18 January 19

1. Traction 1. Battery
7. MV Switchgear
Support tray trafo
8. LVMDP
installation 9. TBS Up – Down
10. VLD

EPCC LRT JABODEBEK POWER SUPPLY SYSTEM 6


EPCC LRT JABODEBEK POWER SUPPLY SYSTEM 7