CRITICAL TASKS

A task is critical if there is no room in the schedule for it to slip.


Learn more about managing your project's critical path.

Name Start Finish % Complete Remaining Work Resource Names


ordin incepere Mon Mon 01.04.24 0% 0 hrs
01.04.24
docmentare teren Tue 02.04.24 Wed 03.04.24 0% 32 hrs sp;rez
Studiu Geotehnic Thu 04.04.24 Thu 02.05.24 0% 168 hrs geo
studiu topografic Thu 04.04.24 Thu 02.05.24 0% 168 hrs topo
Status: Future Task documentatie avize Thu 04.04.24 Thu 02.05.24 0% 840 hrs arh;el, term,
vent;rez;sant;sp
SF Fri 03.05.24 Thu 11.07.24 0% 0 hrs
Solutionare obs Fri 12.07.24 Thu 25.07.24 0% 0 hrs
predare documentatie Fri 26.07.24 Fri 26.07.24 0% 8 hrs geo
avizare Mon Mon 29.07.24 0% 0 hrs
29.07.24