Professional Documents
Culture Documents
5 OTHERS
ii
iii
2 OTHERS
Allow for items not specifically mentioned elsewhere in this Section or
shown in the Drawings and Specifications but necessary for the full
satisfactory completion of works under the Contract. (Note: Bidder to list
items and show the breakdown cost)
i
ii
iii
2 OTHERS
ii
iii
Supply and Installation of all specified concrete blocks with all necessary
reinforcing steel, lintels and ties including supervision, labour, equipment,
tools, scaffold and miscellaneous items required for a complete masonry
job in accordance with plans and specifications. First Quality Hollow
Blocks laid in approved bond. Beddinq jointing and pointing in cement
mortar (1:3), including necessary lintel and stiffener.
CHB 4" - Comfort room Interior Walls and masonry partition at embalming
1 m2
room area
3 OTHERS
ii
iii
Supply and Installation for the repair of existing double swing door at
viewing area (2-way heavy duty hinges)
2 Tile Works m2
Supply and Installation of A-1 Viewing room floor tiles using Porcelein tiles
(600mmx 600mm) and other miscellaneous items required as specified in
the drawings and specifications (PC RATE: 185.00/PC)
Supply and Installation of comfort room wall tiles using 600mmx 600mm
porceilin tiles and other miscellaneous items required as specified in the
drawings and specifications (PC RATE: 185.00/PC)
3 OTHERS
ii
iii
Supply and Application of paint at Steel Columns and Roof framing using
1 m2
Epoxy Primer 3x (with sanding) and top coat
Supply and Application of paint and skim coat at second floor comfort
2 room new masonry wall and ground floor masonry wall partition at m2
embalming room area
4 OTHERS
ii
iii
2 OTHERS
ii
iii
3 OTHERS
Allow for items not specifically mentioned elsewhere in this Section or
shown in the Drawings and Specifications but necessary for the full
satisfactory completion of works under the Contract. (Note: Bidder to list
items and show the breakdown cost)
i
ii
iii
TOTAL COST
CONTENGENCY(10%)
SAY
BUDGET
-